GLOBAL SOLAR PV + BESS + 100 MW AI DATA CENTER
全球太陽能電廠+儲能+100 MW AI 資料中心
International Investment, Joint Venture & Pre-Feasibility Study
國際投資、合資及初步可行性研究報告
Version 2.0 | 9 November 2026 | English first · Traditional Chinese second
Investment screening / Not bankable / Not for construction
投資篩選用途/非銀行融資定案報告/不得作為施工依據
Evidence codes: [O] official published data; [A] assumption; [C] calculated; [P] pending verification.
證據標記:[O] 官方公開資料;[A] 研究假設;[C] 計算值;[P] 待查證。
Executive Decision Summary
投資決策摘要
Reference design: 100 MW IT, PUE 1.25, 125 MW facility demand, 300 MWp DC PV and 100 MW / 400 MWh BESS. These are study assumptions, not optimized or contracted capacities.
研究基準:100 MW IT、PUE 1.25、125 MW 全廠需求、300 MWp DC 太陽能及 100 MW/400 MWh BESS。此為研究假設,並非已最佳化或簽約容量。
| Metric / 指標 | Value / 數值 | Evidence / 依據 |
| Annual facility energy / 年用電 | 1,095 GWh | [C] 125×8,760 |
| PV annual output / PV 年發電 | 499.32 GWh | [C] 300×8,760×19% |
| PV annual equivalent / 年能源等效 | 45.60% | [C] 499.32/1,095 |
| Base infrastructure CAPEX / 基建資本支出 | US$1.40 bn | [A] illustrative |
| Base unlevered project IRR / 基準未槓桿 IRR | ~6.79% | [C] simplified |
| Base NPV at 9% / 9% NPV | −US$213.3m | [C] simplified |
Investment gate: secure a credible grid connection path and customer offtake before land acquisition and full EPC commitment. Annual PV equivalence is not hourly 24/7 clean energy.
投資門檻:在購地及全面 EPC 承諾前,應先確認接電路徑與客戶承購。太陽能年度能源等效不等於逐時 24/7 無碳供電。
1. Scope, Method and Evidence
第一章 研究範圍、方法與證據
This report is a structured pre-feasibility package, not a claim that country-specific interconnection offers, land titles, hourly meteorological datasets or vendor quotes have been obtained. All financial outputs are reproducible illustrative calculations.
本報告為架構化初步可行性研究,並不宣稱已取得各國正式接電函、地籍權狀、逐時氣象資料或供應商報價。財務結果均為可重現的示範計算。
2. Global Market Screening
第二章 全球市場篩選
| Market / 市場 | Opportunity / 機會 | Constraint / 限制 |
| United States / 美國 | AI demand; deep capital markets / AI需求、資本市場 | Utility queue, tariffs / 接電排隊、費率 |
| Brazil / 巴西 | Renewables, land / 再生能源、土地 | Transmission and taxes / 輸電、稅務 |
| Saudi Arabia / 沙烏地阿拉伯 | Solar and investment / 日照與投資 | Water and cooling / 水與散熱 |
| UAE / 阿聯酋 | Cloud ecosystem / 雲端生態 | Heat, grid allocation / 高溫、電網配置 |
| Bahrain / 巴林 | Demonstration cases / 示範案例 | Scale and land / 規模、土地 |
| Australia / 澳洲 | Solar and land / 日照與土地 | Transmission distance / 輸電距離 |
| Japan / 日本 | High-value compute / 高價值算力 | Grid, seismic / 電網、地震 |
| Taiwan / 台灣 | Server supply chain / 伺服器供應鏈 | Land, power / 土地、電力 |
| Spain / 西班牙 | EU market / 歐盟市場 | Grid, water / 電網、水 |
| India / 印度 | Growing digital market / 數位成長 | Grid reliability / 電網可靠度 |
No ranking is asserted as an official government assessment. The screening order should be updated only after site-level grid and customer data are obtained.
本表並非政府官方排名;須取得場址級接電及客戶資料後才能更新優先順序。
3. Official Grid and Land Due Diligence
第三章 官方接電與土地盡職調查
Required for each candidate: utility/operator name, candidate substation and voltage, firm import capacity (MW/MVA), N-1 basis, queue position, reinforcement works, cost, target energization, land parcel, zoning, title, environmental approvals, water and fiber. A national installed-generation figure is not available capacity at a site.
每個候選場址需取得:電網營運商、候選變電站與電壓、正式可輸入容量(MW/MVA)、N-1 基準、排隊順位、強化工程、費用、送電日、地籍、分區、權狀、環評、水源及光纖。國家發電裝置容量不等於場址可用接電容量。
| Country / 國家 | Official authority or primary source / 官方來源 | Site-specific firm MW / 場址確認 MW |
| US / 美國 | DOE; relevant ISO/RTO and utility / DOE、區域電網與電力公司 | [P] |
| Brazil / 巴西 | ANEEL; ONS; EPE; distributor / 電力監管、系統與規劃機構 | [P] |
| Saudi Arabia / 沙國 | Saudi Electricity Company; regulator / 電力公司與監管機關 | [P] |
| UAE / 阿聯酋 | Relevant emirate utility / 各酋長國電力機關 | [P] |
| Bahrain / 巴林 | Electricity and Water Authority / 電水主管機關 | [P] |
| Australia / 澳洲 | AEMO; relevant network operator / 市場與電網營運商 | [P] |
| Japan / 日本 | OCCTO; regional utility / 廣域機構及區域電力公司 | [P] |
| Taiwan / 台灣 | Taipower / 台灣電力公司 | [P] |
| Spain / 西班牙 | REE; relevant distribution operator / 輸電及配電業者 | [P] |
| India / 印度 | CTUIL; state transmission utilities / 中央及邦輸電機構 | [P] |
Land planning allowance [A]: PV 300–600 ha, AIDC 15–35 ha, BESS/substation 5–15 ha; combined 320–650 ha before external rights-of-way. Off-site PV via PPA reduces contiguous land needs.
用地初估 [A]:PV 300–600 公頃、AIDC 15–35 公頃、BESS/變電站 5–15 公頃;不含外部線路通行權合計 320–650 公頃。異地 PPA 可減少連續用地需求。
4. Demand and Solar Energy Balance
第四章 負載與太陽能能源平衡
Facility power [C] = IT load × PUE = 100 × 1.25 = 125 MW. Annual load [C] = 125 × 8,760 = 1,095,000 MWh. Solar output [C] = PV MWp × 8,760 × assumed capacity factor 19%.
全廠功率 [C]=IT 負載×PUE=100×1.25=125 MW。年耗電 [C]=125×8,760=1,095,000 MWh。太陽能發電 [C]=PV MWp×8,760×假設容量因數 19%。
| PV / 光電 | Annual generation / 年發電 GWh | Equivalent of load / 年能源等效 |
| 100 MWp | 166.4 | 15.2% |
| 200 MWp | 332.9 | 30.4% |
| 300 MWp | 499.3 | 45.6% |
| 400 MWp | 665.8 | 60.8% |
| 500 MWp | 832.2 | 76.0% |
| 660 MWp | 1098.5 | 100.3% |
5. 8,760-Hour PV/BESS Optimization Specification
第五章 全年 8,760 小時 PV/BESS 最佳化規格
A validated 8,760-hour optimum cannot be reported without site-specific hourly irradiance, ambient temperature, PV layout, tariffs, grid limits and facility load profile. The following is the executable optimization specification, not a completed hourly run.
未取得場址逐時日照、氣溫、PV 配置、電價、接電限制及負載曲線前,不得宣稱已完成 8,760 小時最適解。以下為可執行的最佳化規格,非已完成逐時模擬。
| Scenario / 情境 | PV DC | BESS MW / MWh |
| A | 100 MWp | 50 / 200 |
| B | 200 MWp | 100 / 400 |
| C | 300 MWp | 100 / 400 |
| D | 400 MWp | 125 / 800 |
| E | 500 MWp | 125 / 1,000 |
| F | 660 MWp | 150 / 1,500 |
Hourly balance: GridImport[t] + PVUsed[t] + Discharge[t] = FacilityLoad[t] + Charge[t] + Export[t]. PV generation = PVUsed + PVCharge + Export + Curtailment. SOC[t+1] = SOC[t] + ηcharge×Charge[t]×Δt − Discharge[t]×Δt/ηdischarge. Respect PCS limits, SOC bounds, export caps and battery degradation.
逐時平衡:電網輸入+PV 自用+電池放電=全廠負載+電池充電+外送。PV 發電=PV 自用+PV 充電+外送+棄光。SOC 下一時段=本時段 SOC+充電效率×充電量−放電量/放電效率。需限制 PCS 功率、SOC、外送上限及電池衰退。
Objective: minimize discounted PV/BESS capital, grid purchases, demand charges, maintenance and replacement, net of permitted exports and grid-service revenue. Report hourly CFE, curtailment, imports, peak demand, battery cycles and sensitivity to tariffs and yield.
目標函數:最小化折現後 PV/BESS 資本成本、電網購電、需量費、維護與汰換,扣除可行的外送及電網服務收入。輸出逐時無碳比例、棄光、購電、尖峰需量、電池循環及電價/發電量敏感度。
6. Conceptual Electrical Single-Line Architecture
第六章 概念電力單線架構
UTILITY GRID / 公共電網
│
GRID CONNECTION & HV SWITCHYARD / 接電點與高壓開關場
│
MAIN HV/MV TRANSFORMERS / 主高壓中壓變壓器
│
MV BUS & PROTECTION / 中壓母線與保護
├── Critical Path A → UPS A → IT PDUs / 關鍵 A 路
├── Critical Path B → UPS B → IT PDUs / 關鍵 B 路
└── Cooling & Auxiliaries / 冷卻及輔助負載
PV ARRAY → INVERTERS → STEP-UP → APPROVED GRID/MV PCC
太陽能陣列 → 逆變器 → 升壓 → 核准併網點
BESS → PCS → STEP-UP → APPROVED GRID/MV PCC
儲能 → 變流器 → 升壓 → 核准併網點
INDEPENDENT EMERGENCY GENERATION → CRITICAL DISTRIBUTION
獨立緊急發電 → 關鍵配電
Engineering hold points: fault levels, protection selectivity, earthing, harmonic studies, arc flash, dynamic transfer, black-start/islanding permissions, A/B common-mode failures, UPS autonomy, emergency fuel and local code compliance. BESS 100 MW cannot alone support 125 MW facility demand.
工程審查關卡:短路容量、保護選擇性、接地、諧波、電弧閃光、動態切換、黑啟動/孤島許可、A/B 共因失效、UPS 備援時間、緊急燃料及當地法規。100 MW BESS 無法單獨支援 125 MW 全廠負載。
7. Cooling, Water, Fiber and Permitting
第七章 冷卻、水資源、光纖與許可
Evaluate liquid cooling, heat rejection, water-use effectiveness, seasonal PUE, dry-cooling penalties, water rights, wastewater permits, dual fiber routes and physical security. Environmental studies must address PV land disturbance, battery fire protection, noise and heat discharge.
需評估液冷、散熱排放、用水效率、季節性 PUE、乾冷效率損失、水權、廢水許可、雙路光纖及實體安全。環評應涵蓋 PV 土地擾動、電池消防、噪音及排熱。
8. CAPEX, OPEX and Procurement
第八章 資本支出、營運成本與採購
| Investment / 投資項目 | Low / 低 US$m | Base / 基準 | High / 高 |
| PV 300 MWp | 180 | 240 | 360 |
| BESS 400 MWh | 80 | 120 | 180 |
| AIDC building/MEP | 700 | 900 | 1,300 |
| Land/grid | 40 | 80 | 160 |
| Engineering/contingency | 40 | 60 | 120 |
| TOTAL / 合計 | 1,040 | 1,400 | 2,120 |
All CAPEX values [A] are preliminary scenario allowances, not current country quotes. Excludes GPUs, AI networking, financing interest, tax and some owner costs. Obtain EPC BOQs and binding proposals before financing.
全部 CAPEX [A] 為初步情境額度,非各國即時報價。不含 GPU、AI 網路、融資利息、稅金及部分業主成本。融資前需取得 EPC 工程數量表與具約束力報價。
| Grid tariff / 電網電價 | Full-grid annual bill / 全電網年費 [C] |
| US$50/MWh | US$54.75m |
| US$70/MWh | US$76.65m |
| US$90/MWh | US$98.55m |
| US$120/MWh | US$131.40m |
Actual OPEX must reconcile grid energy, PV O&M, BESS efficiency and augmentation, staffing, cooling water, insurance, land leases, demand charges and transmission fees. Avoid double-counting PV savings and PPA payments.
實際 OPEX 需統合電網能源、PV 維護、BESS 效率與增補、人員、冷卻用水、保險、土地租金、需量費與輸電費。不可重複計算 PV 節費與 PPA 支出。
9. PPA and Commercial Agreements
第九章 PPA 與商務契約
Evaluate on-site supply, sleeved physical PPA, virtual PPA and hourly clean-energy matching. Term sheets must define delivery point, volume shape, curtailment, balancing, renewable attributes, credit support, indexation, change in law and termination.
評估場內供電、轉供實體 PPA、虛擬 PPA 及逐時綠電匹配。條款須定義交付點、電量曲線、棄光、平衡責任、環境屬性、信用擔保、調價、法律變更與終止。
| Illustrative PPA / 示範單價 | 300 MWp gross annual energy value / 年度能源交易額 |
| US$35/MWh | US$17.48m |
| US$45/MWh | US$22.47m |
| US$55/MWh | US$27.46m |
| US$70/MWh | US$34.95m |
10. Twenty-Year Financial Model and Cash Flows
第十章 二十年財務模型與逐年現金流
Simplified unlevered, pre-tax infrastructure illustration [A]: Year 0 CAPEX US$1,400m; years 1–20 annual revenue US$230m and cash OPEX US$100m, so annual net cash US$130m. No financing, tax, terminal value, ramp-up or replacement capex. It is not a bankable project forecast.
簡化未槓桿、稅前基建示範 [A]:第 0 年 CAPEX 14 億美元;第 1–20 年每年收入 2.30 億、現金 OPEX 1.00 億、淨現金 1.30 億。未計融資、稅務、殘值、爬坡或設備汰換,非銀行級預測。
| Year / 年 | Revenue / 收入 | OPEX / 費用 | CAPEX / 資本 | Net CF / 淨現金 | PV @9% / 現值 | Cum. CF / 累計 |
| 0 | 0 | 0 | 1400 | -1400 | -1400.0 | -2800 |
| 1 | 230 | 100 | 0 | 130 | 119.3 | -2670 |
| 2 | 230 | 100 | 0 | 130 | 109.4 | -2540 |
| 3 | 230 | 100 | 0 | 130 | 100.4 | -2410 |
| 4 | 230 | 100 | 0 | 130 | 92.1 | -2280 |
| 5 | 230 | 100 | 0 | 130 | 84.5 | -2150 |
| 6 | 230 | 100 | 0 | 130 | 77.5 | -2020 |
| 7 | 230 | 100 | 0 | 130 | 71.1 | -1890 |
| 8 | 230 | 100 | 0 | 130 | 65.2 | -1760 |
| 9 | 230 | 100 | 0 | 130 | 59.9 | -1630 |
| 10 | 230 | 100 | 0 | 130 | 54.9 | -1500 |
| 11 | 230 | 100 | 0 | 130 | 50.4 | -1370 |
| 12 | 230 | 100 | 0 | 130 | 46.2 | -1240 |
| 13 | 230 | 100 | 0 | 130 | 42.4 | -1110 |
| 14 | 230 | 100 | 0 | 130 | 38.9 | -980 |
| 15 | 230 | 100 | 0 | 130 | 35.7 | -850 |
| 16 | 230 | 100 | 0 | 130 | 32.7 | -720 |
| 17 | 230 | 100 | 0 | 130 | 30.0 | -590 |
| 18 | 230 | 100 | 0 | 130 | 27.6 | -460 |
| 19 | 230 | 100 | 0 | 130 | 25.3 | -330 |
| 20 | 230 | 100 | 0 | 130 | 23.2 | -200 |
Calculated [C]: base NPV at 9% = US$-213.3m; base IRR = 6.79%. Breakeven annual net cash at 9% = US$153.4m.
計算值 [C]:9% 折現率下基準 NPV 約負 2.133 億美元,基準 IRR 約 6.79%;要達 9% NPV=0,年度淨現金流約需 1.534 億美元。
A bankable model must add construction draws, tax/depreciation, debt amortization, DSCR/LLCR, inflation, PPA settlement, grid charges, customer ramp-up, battery replacement and GPU refresh where owned.
銀行級模型須加入建造期撥款、稅務折舊、償債、DSCR/LLCR、通膨、PPA 結算、電網費用、客戶爬坡、電池更換及持有 GPU 時的汰換。
11. JV, SPV and Financing
第十一章 合資、專案公司與融資
Proposed ring-fenced structure: JV HoldCo owns Energy SPV (PV, BESS, PPA), AIDC Infra SPV (land, buildings, power and cooling) and Compute OpCo (GPU/customer contracts). Separate asset lives, debt covenants and related-party contracts.
建議隔離架構:JV 控股公司持有 Energy SPV(PV、BESS、PPA)、AIDC Infra SPV(土地、建築、配電與冷卻)及 Compute OpCo(GPU/客戶合約)。分開管理資產年限、債務契約與關係人交易。
| Illustrative investor / 示範股東 | Equity / 股權 |
| Infrastructure capital / 基建資本 | 40% |
| Local energy/land partner / 當地能源土地夥伴 | 30% |
| AIDC technology/operator / 技術營運夥伴 | 20% |
| Strategic investor / 策略投資人 | 10% |
Reserved matters: new debt, equity dilution, EPC award, PPA pricing, related-party transactions, dividend policy, asset sale, default cure and exit rights. Local counsel must verify foreign ownership, tax treaties and data rules.
保留事項:新增債務、股權稀釋、EPC 授標、PPA 定價、關係人交易、股利、資產出售、違約補救及退出權。當地律師須核實外資、租稅協定與資料法規。
12. Development Roadmap and Investment Gates
第十二章 開發路線圖與投資關卡
| Phase / 階段 | Months / 月份 | Gate / 核准關卡 |
| Market and customer screening / 市場客戶 | 0–3 | Customer interest / 客戶意向 |
| Land/grid feasibility / 土地接電 | 2–9 | Utility response / 電力公司回覆 |
| Pre-FS and FEED / 初研基本設計 | 3–12 | Engineering basis / 設計基準 |
| PPA/JV/financing / 購電合資融資 | 6–18 | Signed terms / 簽署條款 |
| EPC procurement / EPC 採購 | 9–20 | Binding bids / 正式報價 |
| Construction / 建設 | 18–42 | Commissioning readiness / 驗收準備 |
| Testing/operation / 測試營運 | 30–48 | Acceptance / 驗收 |
Stage development at 25, 50 and 100 MW IT as customers, grid capacity and financing become firm. These timelines are planning estimates, not utility commitments.
建議依客戶、接電與融資落實程度,分 25、50、100 MW IT 建設。以上為規劃時程,非電力公司承諾。
13. Risk Register and Mitigation
第十三章 風險清冊與對策
| Risk / 風險 | Severity / 程度 | Mitigation / 對策 |
| Grid delivery / 接電 | Critical / 極高 | Utility studies and staged COD / 正式研究與分期送電 |
| Customer offtake / 客戶承購 | Critical / 極高 | Prelease and credit support / 預租與信用保障 |
| Cooling/water / 冷卻用水 | High / 高 | Water rights, dry-cooling study / 水權及乾冷研究 |
| PV curtailment / 棄光 | High / 高 | Hourly dispatch optimization / 逐時調度 |
| Battery safety / 電池安全 | High / 高 | Fire engineering, OEM warranty / 消防與保固 |
| Construction inflation / 工程通膨 | High / 高 | EPC risk sharing / EPC 風險分攤 |
| FX/tax/regulatory / 匯率稅法 | High / 高 | Hedging and local counsel / 避險及法律顧問 |
| GPU obsolescence / GPU 汰換 | High / 高 | Separate Compute OpCo / 算力法人獨立 |
14. Evidence Register and Official Sources
第十四章 證據清冊與官方來源
The following are official organizations or institutional reference portals for subsequent verification. URLs are source entry points, not proof of specific site capacity, prices or land rights. Retrieval dates and exact document editions must be recorded during country due diligence.
以下為後續查核的官方機構或機構資料入口,並非特定場址容量、電價或地權證明。各國盡調時須記錄查閱日期及確切文件版本。
| Source / 來源 | Official portal / 官方入口 | Evidence status / 證據狀態 |
| IEA Energy and AI | https://www.iea.org/reports/energy-and-ai | [O] portal; site facts [P] |
| IRENA renewable costs | https://www.irena.org/Publications | [O] portal; site facts [P] |
| US DOE | https://www.energy.gov/ | [O] portal; site facts [P] |
| US EIA | https://www.eia.gov/ | [O] portal; site facts [P] |
| Brazil ANEEL | https://www.gov.br/aneel/pt-br | [O] portal; site facts [P] |
| Brazil ONS | https://www.ons.org.br/ | [O] portal; site facts [P] |
| Brazil EPE | https://www.epe.gov.br/ | [O] portal; site facts [P] |
| Saudi SEC | https://www.se.com.sa/ | [O] portal; site facts [P] |
| Bahrain EWA | https://www.ewa.bh/ | [O] portal; site facts [P] |
| Australia AEMO | https://aemo.com.au/ | [O] portal; site facts [P] |
| Japan OCCTO | https://www.occto.or.jp/ | [O] portal; site facts [P] |
| Taiwan Taipower | https://www.taipower.com.tw/ | [O] portal; site facts [P] |
| Spain REE | https://www.ree.es/ | [O] portal; site facts [P] |
| India CTUIL | https://www.ctuil.in/ | [O] portal; site facts [P] |
15. Final Investment Recommendation
第十五章 最終投資建議
Proceed to a gated, multi-country site-screening program. Do not commit major construction capital until utility deliverability, land rights, anchor-customer contracts, environmental permits and financeable EPC/PPA terms are evidenced. The reference 300 MWp PV / 400 MWh BESS design remains a benchmark—not a global optimum.
建議採分階段跨國選址計畫。在正式取得可交付接電、土地權利、主要客戶合約、環境許可及可融資 EPC/PPA 條款前,不宜投入重大建設資本。300 MWp PV/400 MWh BESS 仍是比較基準,而非全球最佳解。