Global AIDC Power Market

Global AIDC Power Market Research Report

AIDC 電力全球市場研究報告

Research cut-off 15 November 2026
資料截止 2026 年 11 月 15 日

All monetary comparisons in US dollars
金額比較統一採美元計價

Includes 12 chapters, Appendices A–G and linked references
含十二章正文、附錄 A 至 G 及可點閱參考來源

Purpose

Assess global demand, competing architectures, supplier positions, electricity costs and market-entry opportunities. The report separates observed data, corporate claims and calculated scenarios.

評估全球需求、競爭架構、供應商定位、電費與市場進入機會;區分已公布數據、企業主張及計算情境。

Principal conclusion

Investments should be gated by deliverable power, complete electricity contracts and verified system performance. Regional average prices support screening, not final procurement.

投資應以可交付電力、完整購電契約與經驗證系統性能為關卡。區域均價用於初篩,不作為最終採購依據。

 

 

Contents 目錄

1 Executive Summary
一 執行摘要

2 Market Definition and Boundaries
二 市場定義與範圍

3 Demand Outlook and Market Sizing
三 需求展望與市場規模

4 Technology Competition
四 技術競爭

5 Competitive Landscape
五 競爭格局

6 Global Electricity Cost Comparison
六 全球電費比較

7 Regional Market Entry Priorities
七 區域市場進入重點

8 Economics of a 100 MW AIDC
八 100 MW AIDC 經濟性

9 Storage Backup and Operational Resilience
九 儲能備援與營運韌性

10 Opportunities for Taiwanese Suppliers
十 台灣供應商商機

11 Proposed Development Roadmap
十一 建議發展路線圖

12 Conclusions and Investment Criteria
十二 結論與投資準則

Appendix A Research Scope and Evidence
附錄 A 研究範圍與證據分類

Appendix B Calculation Methods
附錄 B 計算方法與假設

Appendix C Electricity Price Comparability
附錄 C 電價可比較性與限制

Appendix D Technical Validation and Procurement
附錄 D 技術驗證與採購檢核

Appendix E Claim to Source Mapping
附錄 E 主要論點與來源對照

Appendix F References
附錄 F 參考文獻

Appendix G Citation and Document Control
附錄 G 引用與文件管理

 

 

1 Executive Summary

一 執行摘要

The global AI data center power market is expanding across grid connections, electrical distribution, power conversion, backup systems, energy storage and electricity procurement. Its commercial value increasingly depends on delivering usable power on schedule, maintaining computing continuity and reducing electricity consumption per completed workload.

全球 AI 資料中心電力市場正擴展至電網接入、配電、電力轉換、備援、儲能及電力採購。其商業價值越來越取決於能否如期交付可用電力、維持運算不中斷,以及降低每項完成工作負載的用電量。

The IEA projects total global data center electricity consumption to rise from approximately 485 TWh in 2025 to 950 TWh in 2030. These figures cover all data centers, not AI facilities alone. The implied compound annual growth rate is approximately 14.4%, calculated from the endpoints. AI-focused electricity consumption is projected to triple over that period. [R1]

IEA 預估全球資料中心總用電量將由 2025 年約 485 TWh 增加至 2030 年約 950 TWh。這些數字涵蓋所有資料中心,並非僅限 AI 設施。依起訖數值計算,年複合成長率約 14.4%;同期 AI 導向資料中心用電量預估增至三倍。[R1]

Strategic conclusion
策略結論
Investment implication
投資意義
Grid availability and energization dates
可用接電容量與送電日期
Essential investment gates
投資必要決策關卡
Coexistence of AC and 800 VDC
AC 與 800 VDC 並存
Match architecture to platform and deployment stage
配合平台與部署階段選擇架構
Complete power-path efficiency
完整供電路徑效率
Do not equate module efficiency with facility efficiency
不可將模組效率等同場站效率
Storage with defined operating roles
明確定義儲能運轉角色
Specify MW, MWh, controls and backup reserves
明定 MW、MWh、控制與備援保留
Site-specific electricity contracts
場址專屬購電契約
Validate regional price benchmarks before investment
投資前驗證區域電價參考值
Integrated lifecycle services
整合全生命週期服務
Opportunities beyond equipment sales
設備銷售以外的商機

 

These conclusions are research interpretations, not guarantees of technology adoption or investment returns.

上述結論屬研究判斷,不代表技術採用或投資報酬保證。

2 Market Definition and Boundaries

二 市場定義與範圍

AIDC power comprises several related markets. Electricity expenditure, equipment revenue and total data center construction investment must be measured separately to avoid double counting.

AIDC 電力包含數個相互關聯的市場。電力支出、設備營收與資料中心總建設投資必須分開計算,以避免重複計入。

Market segment
市場區段
Products and services
產品與服務
Commercial model
商業模式
Grid connection
電網接入
Substations, transformers, protection
變電站、變壓器、保護
Equipment and EPC
設備及 EPC
Facility distribution
場內配電
Switchgear, busways, cables, metering
開關設備、母線槽、電纜、電表
Supply, installation, maintenance
供貨、安裝、維護
Critical power
關鍵電力
UPS, rectifiers, transfers, backup generation
UPS、整流器、切換、備援發電
Equipment and service agreements
設備及服務合約
Rack and chip power
機櫃與晶片供電
Power shelves, DC/DC, BBU, protection
電源架、DC/DC、BBU、保護
Platform qualification and supply
平台認證及供貨
Storage and microgrids
儲能與微電網
BESS, PCS, EMS, source coordination
BESS、PCS、EMS、多電源協調
Integration and energy services
整合及能源服務
Electricity procurement
電力採購
Utility supply, PPAs, network services
公用電力、PPA、網路服務
Recurring electricity contracts
持續性購電契約
Engineering and operations
工程與營運
Studies, commissioning, monitoring
分析、試運轉、監測
Project fees and recurring services
專案費及持續性服務

 

GPU servers, networking equipment and cooling plants are excluded from the narrow electrical-equipment market unless explicitly included in a project scope.

狹義電力設備市場不包含 GPU 伺服器、網路設備與冷卻主機,除非專案範圍明確納入。

3 Demand Outlook and Market Sizing

三 需求展望與市場規模

The IEA reports that data center electricity demand increased 17% in 2025, while AI-focused demand increased 50%. These are electricity-demand growth rates, not revenue growth rates for UPS, transformers or other equipment. [R1–R2]

IEA 指出,2025 年資料中心用電需求增加 17%,AI 導向用電需求增加 50%。這些是用電需求成長率,不是 UPS、變壓器或其他設備的營收成長率。[R1–R2]

Illustrative electricity expenditure in 2030

2030 年電力支出情境

Applying assumed electricity prices to the IEA’s 950 TWh projection gives the following expenditure scenarios for all data centers. These are calculated scenarios, not an AIDC-only market forecast. [R1; report calculations]

將假設電價套用於 IEA 的 950 TWh 預測,可得全部資料中心的電力支出情境。以下為計算情境,不是 AIDC 專屬市場預測。[R1;本報告計算]

Assumed price
假設電價 US$/kWh
Annual expenditure
年度支出 US$ billion
0.05 47.5
0.10 95.0
0.15 142.5

 

These amounts exclude equipment investment and cannot be added directly to supplier revenues.

以上未包含設備投資,不能直接與供應商營收相加。

For electrical equipment, a defensible model separates new installations from retrofits and replacement demand:

電力設備市場應將新建、改造與汰換分開估算:

Annual equipment market = New IT capacity × Electrical investment per IT MW + Retrofits and replacements

年度設備市場=新增 IT 容量 × 每 IT MW 電力設備投資+改造與汰換

The reviewed sources do not establish a single, consistently defined global AIDC electrical-equipment market value. A credible estimate requires project capacity, commissioning schedules, redundancy levels and supplier quotations.

本次查閱來源尚不足以建立定義一致的全球 AIDC 電力設備市場總額。可信估算仍需專案容量、投運時程、備援等級與供應商報價。

4 Technology Competition

四 技術競爭

NVIDIA describes a transition from existing AC infrastructure through hybrid power racks to facility-level 800 VDC. Schneider Electric identifies adjacent power racks as a practical route for initial adoption. [R6–R7]

NVIDIA 提出從既有 AC 基礎設施,經混合式電源櫃,逐步發展至場站級 800 VDC 的路徑。Schneider Electric 將鄰近運算櫃的電源櫃視為初期導入的可行方式。[R6–R7]

Architecture
架構
Commercial advantage
商業優勢
Validation requirement
驗證要求
Conventional AC
傳統 AC
Established ecosystem and compatibility
成熟生態系與相容性
Density, feeders, weighted efficiency
密度、饋線、加權效率
Hybrid AC–800 VDC
混合式 AC–800 VDC
Phased deployment and upstream reuse
分階段導入、利用上游設備
Interfaces, space, protection coordination
介面、空間、保護協調
Native 800 VDC
原生 800 VDC
Potentially simpler conversion paths
有機會簡化轉換路徑
DC isolation, grounding, maintenance
DC 隔離、接地、維護
SST conversion
SST 轉換
Integrated medium-voltage conversion and control
整合中壓轉換與控制
Lifetime, repair strategy, field evidence
壽命、維修、現場證據

 

800 VDC is a distribution architecture; it does not supply the GPU core directly. Downstream conversion remains necessary. Infineon’s announced work includes GaN intermediate-bus conversion and SiC high-voltage battery-backup reference designs. Reference-design performance is not equivalent to complete facility performance. [R13a–R13b]

800 VDC 是配電架構,不是直接向 GPU 核心供電;下游仍需電壓轉換。Infineon 已公告 GaN 中間匯流排轉換及 SiC 高電壓電池備援參考設計。參考設計性能不等於整座場站性能。[R13a–R13b]

5 Competitive Landscape

五 競爭格局

The following companies illustrate different positions in the value chain. This is not a market-share ranking. [R6, R8–R13]

以下企業代表供應鏈中的不同位置,並非市占率排名。[R6、R8–R13]

Company
企業
Position
定位
Research implication
研究意義
Schneider Electric Distribution, UPS, energy management
配電、UPS、能源管理
Facility integration
場站整合
Vertiv Critical power, thermal systems, services
關鍵電力、熱管理、服務
Power and cooling coordination
電力冷卻協同
Eaton Electrical distribution and infrastructure
配電與電力基礎設施
Capacity and delivery
產能與交付
Hitachi Energy Transformers, protection, grid interfaces
變壓器、保護、電網介面
Upstream infrastructure
上游基礎設施
Delta Electronics
台達電子
Conversion, 800 VDC, modular facilities
轉換、800 VDC、模組化設施
Taiwanese system integration
台灣系統整合
Infineon Power semiconductors and reference designs
功率半導體與參考設計
Component design opportunities
元件設計商機
NVIDIA and OCP ecosystem
NVIDIA 與 OCP 生態系
Power interfaces and architecture coordination
供電介面與架構協調
Platform compatibility
平台相容性

 

Vertiv reported approximately US$4.31 billion in third-quarter 2026 sales, up 61.2% year over year. Eaton reported US$8.9 billion, up 28%. These are company-wide revenues and must not be interpreted as AIDC power revenue or market share. [R8–R9]

Vertiv 公布 2026 年第三季營收約 43.1 億美元,年增 61.2%;Eaton 公布營收 89 億美元,年增 28%。這些是公司整體營收,不能直接解讀為 AIDC 電力營收或市占率。[R8–R9]

6 Global Electricity Cost Comparison

六 全球電費比較

The model assumes 100 MW IT load, PUE 1.20 and continuous full-load operation, producing annual consumption of 1.0512 TWh. Annual costs below are calculated scenarios, not utility offers.

模型假設 100 MW IT 負載、PUE 1.20、全年滿載運轉,年用電量為 1.0512 TWh。下列年度費用為情境計算,不是購電報價。

Market
市場
Price
US$/kWh
Annual cost
US$ million
Basis
口徑
Texas US
美國德州
0.0677 71.17 A
Washington US
美國華盛頓州
0.0717 75.37 A
Saudi Arabia
沙烏地阿拉伯
0.0740 77.79 C
Arizona US
美國亞利桑那州
0.0794 83.47 A
Finland
芬蘭
0.08228 86.49 B
Virginia US
美國維吉尼亞州
0.1007 105.86 A
Sweden
瑞典
0.1067 112.16 B
India
印度
0.1100 115.63 C
Malaysia
馬來西亞
0.1170 122.99 C
China
中國
0.1190 125.09 C
South Korea
韓國
0.1320 138.76 C
Taiwan
台灣
0.1334375 140.27 D
South Africa
南非
0.1380 145.07 C
Brazil
巴西
0.1460 153.48 C
Japan
日本
0.1780 187.11 C
California US
美國加州
0.2111 221.91 A
Singapore
新加坡
0.2120 222.85 C
Australia
澳洲
0.2430 255.44 C
Germany
德國
0.24904 261.79 B
Ireland
愛爾蘭
0.28072 295.09 B

 

A — US industrial averages, January–August 2026. [R3]

A — 美國 2026 年 1–8 月工業平均電價。[R3]

B — Eurostat non-household prices for the second half of 2025, annual consumption of 500–2,000 MWh. Converted using an assumed US$1.10 per euro. [R4]

B — Eurostat 2025 年下半年非住宅電價,年用電 500–2,000 MWh;以每歐元 1.10 美元假設換算。[R4]

C — Third-party March 2026 business benchmarks, not large-AIDC contract quotations. [R15–R24]

C — 第三方 2026 年 3 月企業電價,不是大型 AIDC 合約報價。[R15–R24]

D — Taiwan’s published industrial average, converted using US$1 = NT$32 as a fixed modeling assumption. [R5]

D — 台灣公布的工業平均電價,採 US$1=NT$32 固定模型假設換算。[R5]

Categories, dates and consumption bands differ. The table is a screening tool rather than a procurement ranking and does not establish that any listed site can supply 120 MW. See Appendix C.

各組類別、日期與用電級距不同。本表屬初篩工具,不是採購排名,也不代表任何場址已能供應 120 MW。詳見附錄 C。

7 Regional Market Entry Priorities

七 區域市場進入重點

The following priorities are proposed evaluation criteria, not verified findings for individual sites.

以下為建議評估重點,不是對個別場址已完成查證的結論。

Region
區域
Commercial focus
商業重點
Required diligence
必要查核
United States
美國
Campus electrical packages and phased expansion
園區電力套案與分期擴建
Capacity, tariffs, energization milestones
容量、費率、送電里程碑
Northern Europe
北歐
Efficient facilities and low-carbon procurement
高能效設施與低碳購電
Grid capacity, hourly supply, network costs
容量、逐時供電、網路費
Taiwan and Japan
台灣與日本
High-density integration and retrofit services
高密度整合與改造服務
Site constraints, tariffs, continuity
場址限制、費率、連續性
Southeast Asia
東南亞
Modular deployment and power–cooling integration
模組部署與電力冷卻整合
Climate-specific PUE and utility contracts
氣候條件下 PUE 與購電契約
Middle East
中東
Campus power and thermal design
園區電力與熱管理
Temperature derating, water, eligibility
高溫降額、水資源、契約資格
Brazil and Latin America
巴西與拉丁美洲
Site-specific procurement and integration
場址購電與整合
Network fees, capacity, currency exposure
網路費、容量、匯率曝險
Africa
非洲
Continuity and integrated backup
連續供電與整合備援
Local supply and lifecycle backup costs
當地供電與備援生命週期成本
Australia
澳洲
Procurement optimization and flexible systems
購電最佳化與彈性系統
Regional tariffs, transmission and PPAs
區域費率、輸電與 PPA

 

8 Economics of a 100 MW AIDC

八 100 MW AIDC 經濟性

Electricity cost should be evaluated alongside connection investment, equipment replacement, maintenance, backup fuel and service continuity.

電費應與接電投資、設備汰換、維護、備援燃料及服務連續性共同評估。

Price
US$/kWh
Annual electricity cost
US$ million
Ten-year undiscounted cost
US$ billion
0.05 52.56 0.526
0.10 105.12 1.051
0.15 157.68 1.577
0.20 210.24 2.102
0.25 262.80 2.628

 

Assumptions: constant prices, constant PUE and full utilization. Ten-year figures exclude escalation, discounting and ramp-up. Every US$0.01/kWh difference changes annual cost by US$10.512 million.

假設電價、PUE 及滿載率不變。十年數值未計電價調升、折現與投運爬坡。每度電相差 US$0.01,年度成本即相差 US$10.512 million。

Reducing PUE from 1.20 to 1.10 at the same 100 MW IT load saves 87.6 GWh annually. At US$0.10/kWh, the calculated saving is US$8.76 million per year.

相同 100 MW IT 負載下,PUE 由 1.20 降至 1.10,每年可減少 87.6 GWh 用電。以 US$0.10/kWh 計算,每年節省 US$8.76 million。

A valid efficiency comparison preserves workload output, service quality, redundancy and environmental conditions. GPU utilization is not the same as electrical load factor.

有效能效比較須維持工作產出、服務品質、備援與環境條件一致。GPU 使用率不等於電力負載率。

9 Storage Backup and Operational Resilience

九 儲能備援與營運韌性

UPS, BBU and BESS serve overlapping but different functions. A system suitable for peak shaving does not automatically provide uninterrupted power or islanded operation.

UPS、BBU 與 BESS 功能部分重疊,但並不相同。適合削峰的系統,不會自動具備不斷電或孤島運轉能力。

System
系統
Primary role
主要角色
Critical specification
關鍵規格
UPS Power quality and transition support
電力品質與切換支援
Response, bypass, autonomy
反應、旁路、備援時間
Rack BBU
機櫃 BBU
Local short-duration support
局部短時間供電
Protected loads and usable energy
受保護負載、可用電量
BESS Energy shifting, smoothing, engineered backup
能量移轉、平滑、經設計的備援
MW, MWh, SOC, grid-forming where required
MW、MWh、SOC、必要構網能力
Generator
發電機
Extended outage supply
停電期間較長時間供電
Start sequence, load acceptance, fuel
啟動、負載接受、燃料

 

For example, 50 MW / 200 MWh describes nominal four-hour discharge at 50 MW. It cannot independently supply a 100 MW IT load because its power rating is insufficient.

例如 50 MW/200 MWh 表示名目上可按 50 MW 放電四小時;由於功率不足,無法獨立供應 100 MW IT 負載。

Supplier testing distinguishes output-voltage regulation from upstream power smoothing. The latter may require cycling storage, affecting reserve management and battery life. [R25–R26]

供應商測試區分輸出電壓穩定與上游功率平滑。後者可能需要儲能反覆充放電,影響備援容量管理與電池壽命。[R25–R26]

10 Opportunities for Taiwanese Suppliers

十 台灣供應商商機

A practical strategy combines qualified components with system engineering, commissioning and international service support.

可行策略是將合格元件與系統工程、試運轉及國際服務支援結合。

Opportunity
商機
Deliverable
交付內容
Qualification priority
驗證重點
Power conversion
電力轉換
Rectifiers, DC/DC, power shelves
整流器、DC/DC、電源架
Efficiency, thermal limits, transients
效率、熱限制、暫態
DC distribution
直流配電
Busways, connectors, protection
母線槽、連接器、保護
Interruption, insulation, servicing
切斷、絕緣、維修
Battery integration
電池整合
BBU, BMS, PCS, reserve control
BBU、BMS、PCS、備援控制
Lifetime, usable energy, containment
壽命、可用電量、故障限制
Modular electrical systems
模組化電力
Prefabricated electrical rooms
預製電力機房
Factory tests and site integration
工廠測試與現場整合
Engineering services
工程服務
Protection studies, commissioning
保護分析、試運轉
Reproducible acceptance evidence
可重現驗收證據
Workforce development
人才培訓
AC/DC safety, UPS/BESS, diagnosis
AC/DC 安全、UPS/BESS、診斷
Practical operational assessment
實務操作考核

 

Delta’s public portfolio includes 800 VDC in-row power, modular AI facilities and microgrid integration. This demonstrates an existing Taiwanese presence; it does not establish market share or guaranteed project performance. [R12]

台達公開產品涵蓋 800 VDC 列間供電、模組化 AI 設施與微電網整合,顯示台灣廠商已有布局,但不代表市占率或個別專案性能保證。[R12]

11 Proposed Development Roadmap

十一 建議發展路線圖

This is a proposed business roadmap for 2027–2030, not an official industry forecast.

以下為 2027–2030 年建議商業路線圖,不是官方產業預測。

Period
期間
Priority
優先工作
Decision gate
決策關卡
2027 AC and hybrid references; supplier qualification
AC 與混合式參考設計、供應商驗證
Compatibility and acceptance tests
相容性與驗收測試
2028 Modular delivery and overseas service
模組交付與海外服務
Repeatable cost, schedule, maintenance
可重複的成本、交期、維護
2029 Storage coordination and power analytics
儲能協調與電力分析
Verified savings without resilience loss
驗證節省且不降低韌性
2030 Scale validated native DC and energy solutions
擴大經驗證的原生 DC 與能源方案
Multi-year reliability and economics
多年可靠度與經濟性

 

12 Conclusions and Investment Criteria

十二 結論與投資準則

The AIDC power opportunity spans established electrical infrastructure and emerging high-density conversion systems. Defensible business models connect equipment performance with dependable delivery, commissioning evidence and long-term service capability.

AIDC 電力商機涵蓋成熟電力基礎設施與新興高密度轉換系統。較具競爭基礎的商業模式,應將設備性能與可靠交付、試運轉證據及長期服務能力連結。

Before committing to a major project, document five conditions: deliverable capacity and schedule; complete electricity pricing; architecture compatibility; integrated operational testing; and lifecycle economics.

大型專案投資前應取得五項條件的書面證據:可交付容量與時程、完整購電價格、架構相容性、整合運轉測試及全生命週期經濟性。

  1. Deliverable power: confirm available MW, connection scope and energization milestones.
  2. 可交付電力:確認可用 MW、接電範圍與送電里程碑。
  3. Complete pricing: include energy, capacity, network charges, adjustments and non-recoverable taxes.
  4. 完整價格:納入電能、容量、網路費、調整項與不可回收稅費。
  5. Architecture: match the power system to actual IT platforms and redundancy objectives.
  6. 架構:供電系統須符合實際 IT 平台與備援目標。
  7. Testing: validate failures, transitions, dynamic loads and cooling continuity.
  8. 測試:驗證故障、切換、動態負載及冷卻連續性。
  9. Economics: include replacement, maintenance, financing, utilization and migration.
  10. 經濟性:納入汰換、維護、融資、使用率與技術轉換。

The central investment metric is the cost of reliably delivered computing output, supported by a verifiable power system and electricity contract.

核心投資指標是可靠交付運算產出的成本,其基礎必須是可驗證的供電系統與購電契約。

Appendix A Research Scope and Evidence

附錄 A 研究範圍與證據分類

This report examines electricity supply, electrical infrastructure, conversion, backup, storage and associated services. Global data center statistics provide context and must not be interpreted as AI-only figures.

本報告研究電力供應、電力基礎設施、轉換、備援、儲能與相關服務。全球資料中心統計用於背景,不得直接解讀為 AI 專屬數值。

Classification
分類
Meaning
定義
Treatment
處理方式
Official statistics
官方統計
Public agencies or intergovernmental bodies
政府或跨政府機構公布
Preserve period, scope and units
保留期間、範圍、單位
Official projections
官方預測
Model-based forward estimates
依模型提出的未來估計
Label as forecasts
標示為預測
Corporate disclosures
企業揭露
Financial reports and specifications
財報與規格
Attribute claims; separate company and AIDC sales
註明來源,區分公司與 AIDC 營收
Third-party benchmarks
第三方資料
Aggregated electricity prices
彙整電價
Screen then validate contracts
初篩後驗證契約
Calculated scenarios
計算情境
Explicit assumptions and formulas
明確假設與公式
Show boundaries and exclusions
揭露邊界與排除項
Recommendations
研究建議
Proposed commercial or technical actions
建議商業或技術行動
No guaranteed outcomes
不保證結果

 

Research cut-off: 15 November 2026. Publication dates and underlying data periods differ by source.

資料截止:2026 年 11 月 15 日。各來源發布日期與實際資料期間不同。

Appendix B Calculation Methods

附錄 B 計算方法與假設

B1 Annual electricity consumption

B1 年度用電量

For the full-load comparison, annual energy in kWh equals IT power in MW multiplied by PUE, annual hours and 1,000.

滿載比較中,年度電量 kWh 等於 IT 功率 MW 乘以 PUE、年度小時數及 1,000。

Eannual = PIT × PUE × 8,760 × 1,000

100 × 1.20 × 8,760 × 1,000 = 1,051,200,000 kWh/year

For actual operations, use interval measurements or a forecast including variable IT demand and facility overhead. GPU utilization must not be substituted directly for electrical load factor.

實際營運應使用分時量測或預測,納入 IT 需求與場站附屬用電變化。GPU 使用率不得直接代替電力負載率。

Eannual = Σt (PIT,t + Pfacility overhead,t) × Δt

B2 Electricity expenditure

B2 電費支出

Reference expenditure equals annual energy multiplied by the reference US$/kWh price. Itemized bills require energy, demand, network charges, adjustments and applicable taxes. Published averages may already contain these items; do not count them twice.

參考支出等於年電量乘以 US$/kWh 電價。分項帳單須納入電能、需量、網路費、調整項及稅費。公布均價可能已含相關費用,不得重複計算。

Creference = Eannual × p

B3 Exchange rate assumptions

B3 匯率假設

Conversion
換算
Fixed assumption
固定假設
Euro to US dollar
歐元轉美元
€1 = US$1.10
Taiwan dollar to US dollar
新台幣轉美元
US$1 = NT$32

 

These are modeling assumptions, not verified spot rates. Third-party US-dollar prices retain that source’s conversion basis.

以上為模型假設,不是經查核即期匯率。第三方美元電價沿用其自身換算基礎。

B4 Sensitivity calculations

B4 敏感度計算

Scenario
情境
Annual impact
年度影響
Price increases by US$0.01/kWh
電價增加 US$0.01/kWh
Cost increases US$10.512 million
成本增加 1,051.2 萬美元
PUE decreases 1.20 to 1.10 at 100 MW IT
PUE 由 1.20 降至 1.10
Saves 87.6 GWh
節電 87.6 GWh
Above saving at US$0.10/kWh
上述節電按 US$0.10/kWh
Saves US$8.76 million
節省 876 萬美元

 

These scenarios exclude implementation costs, changes in maintenance and financing effects.

以上未計改善工程成本、維護變化及融資影響。

Appendix C Electricity Price Comparability

附錄 C 電價可比較性與限制

The electricity table combines different statistical populations. Use it for preliminary screening followed by site-specific quotations.

電價表整合不同統計母體,適合初篩;後續仍須取得個別場址報價。

Source
來源
Coverage
範圍
Principal limitation
主要限制
EIA [R3] State industrial averages, Jan–Aug 2026
2026 年 1–8 月州級工業均價
Data center classification may differ
資料中心分類可能不同
Eurostat [R4] 500–2,000 MWh/year, H2 2025
2025 下半年年用電 500–2,000 MWh
Much smaller consumption band
用電級距遠小於本案
Taiwan [R5]
台灣
Published industrial average
公布工業平均價
Not an AIDC high-voltage quotation
不是 AIDC 高壓報價
GlobalPetrolPrices [R15–R24] March 2026 business benchmarks
2026 年 3 月企業參考價
Aggregation does not capture individual contracts
彙整無法反映個別契約

 

Reference expenditure does not automatically include connection construction, private substations, backup equipment, fuel, green-energy premiums or financing. Inclusion depends on tariff and project boundaries.

參考電費不會自動涵蓋接電工程、自有變電站、備援設備、燃料、綠電溢價或融資;是否包含取決於費率與專案邊界。

A lower national or state average price does not establish that sufficient capacity is available at the selected site.

國家或州平均電價較低,不代表選定場址已有足夠容量可供接入。

Appendix D Technical Validation and Procurement

附錄 D 技術驗證與採購檢核

This proposed checklist does not replace applicable codes, utility requirements or detailed engineering.

本建議檢核表不取代適用法規、公用電力要求或詳細工程設計。

Evaluation area
評估項目
Required evidence
所需證據
Grid availability
接電可用性
Written MW confirmation, scope and schedule
書面 MW 確認、範圍與時程
Tariff structure
費率結構
Energy, demand, network, adjustment and tax schedules
電能、需量、網路、調整項與稅費表
Architecture compatibility
架構相容性
IT requirements, voltage tolerances, interface specifications
IT 要求、電壓容許範圍、介面規格
Electrical protection
電氣保護
Short-circuit, coordination, grounding and applicable DC studies
短路、協調、接地及適用 DC 分析
Efficiency
效率
Curves for representative loads, temperatures and redundancy
代表性負載、溫度、備援模式效率曲線
Storage and backup
儲能與備援
MW, usable energy, reserves and end-of-life capability
MW、可用電量、備援、壽命末期能力
Dynamic response
動態反應
Load-step, transfer and recovery tests
階躍、切換與恢復測試
Cooling continuity
冷卻連續性
Power for pumps, CDUs, controls and heat rejection
泵浦、CDU、控制與排熱設備供電
Maintainability
維護性
Isolation procedures, spares, repair times, service coverage
隔離程序、備品、修復時間、服務範圍
Integrated acceptance
整合驗收
Documented operating and failure-condition tests
具紀錄的運轉與故障條件測試

 

An N+1 or 2N label alone does not establish a Uptime Institute Tier classification. Tier III emphasizes concurrent maintainability; Tier IV adds fault tolerance. [R14]

僅有 N+1 或 2N 標示不能建立 Uptime Institute Tier 等級。Tier III 強調可同時維護;Tier IV 再加入容錯。[R14]

Appendix E Claim to Source Mapping

附錄 E 主要論點與來源對照

Claim or section
論點或章節
Reference
文獻
Interpretation boundary
解讀邊界
Global demand
全球需求
R1–R2 All data centers versus AI-only
全部資料中心與 AI 專屬須區分
US prices
美國電價
R3 Industrial averages, not quotations
工業均價,不是報價
European prices
歐洲電價
R4 Preserve consumption band and tax basis
保留用電級距與稅費口徑
Taiwan benchmark
台灣電價
R5 Industrial average, not AIDC tariff
工業均價,不是 AIDC 費率
800 VDC transition
800 VDC 轉型
R6–R7 Corporate guidance, not universal deployment
企業指引,不是全面部署證據
Supplier financials
供應商財務
R8–R10 Company sales are not AIDC sales
公司營收不等於 AIDC 營收
Grid interfaces
電網介面
R11 Capability does not establish delivery date
能力不代表交付日期
Taiwan opportunities
台灣商機
R12 Announcements do not establish share
公告不代表市占率
GaN and SiC
GaN 與 SiC
R13a–R13b Reference design is not facility efficiency
參考設計不等於場站效率
Reliability
可靠度
R14 Complete topology and operations
完整拓撲與運轉
Other regional prices
其他區域電價
R15–R24 Third-party screening
第三方初篩
UPS dynamics
UPS 動態
R25–R26 Equipment and test-condition dependent
取決於設備與測試條件
Finance and roadmap
財務與路線圖
Report analysis
本報告分析
Scenarios and recommendations
情境與建議

 

Appendix F References

附錄 F 參考文獻

Sources below support the report’s evidence chain. Product claims are attributed to vendors. Historical data periods are retained even when a page was accessed later.

以下來源構成本報告證據鏈。產品主張歸屬供應商;即使較晚查閱頁面,仍保留原始資料期間。

[R1] International Energy Agency

Key Questions on Energy and AI

2026-04-16
Global demand outlook and AI energy implications
全球需求展望與 AI 能源影響

Source link 來源連結

[R2] International Energy Agency

Data centre electricity use surged in 2025, even with tightening bottlenecks driving a scramble for solutions

2026-04-16
Demand growth and infrastructure constraints
需求成長與基礎設施限制

Source link 來源連結

[R3] U.S. Energy Information Administration

Electric Power Monthly Table 5.6.B

2026-10-23; data Jan–Aug 2026
State industrial average prices
州級工業平均電價

Source link 來源連結

[R4] Eurostat

Non-household electricity prices in 2nd half of 2025: -3.5%

2026-05-08
Annual consumption band 500–2,000 MWh
年用電級距 500–2,000 MWh

Source link 來源連結

[R5] Ministry of Economic Affairs Taiwan

Electronic Newsletter

2026-09-21
Published industrial-average price and tariff context
工業平均電價與審議背景

Source link 來源連結

[R6] NVIDIA

Why Scaling AI Compute Performance Requires a New Power Architecture

2026-08-11
AC, hybrid and 800 VDC transition
AC、混合式與 800 VDC 轉型

Source link 來源連結

[R7] Schneider Electric

5 Principles for 800 VDC in AI Data Centers: Rack-level Architectures as the Immediate Enabler

2026-03-02; SPD_WP213_EN
Architecture and adoption principles
架構與導入原則

Source link 來源連結

[R8] Vertiv

Third Quarter 2026 Financial Results

2026 Q3
Company-wide sales and growth; not AIDC-only sales
公司整體營收與成長,非 AIDC 專屬營收

Source link 來源連結

[R9] Eaton

Eaton Reports Record Third Quarter 2026 Results

2026 Q3
Company financials and electrical business commentary
公司財務與電力業務說明

Source link 來源連結

[R10] Schneider Electric

Quarterly Financial Results

Accessed 2026-11-15
Financial disclosures and data center demand commentary
財務揭露與資料中心需求說明

Source link 來源連結

[R11] Hitachi Energy

Data Center Energy Solutions

Accessed 2026-11-15
Transformers, protection and grid interfaces
變壓器、保護與電網介面

Source link 來源連結

[R12] Delta Electronics

Data Center Solutions

Accessed 2026-11-15
Modular AI facilities, 800 VDC and microgrids
模組化 AI 設施、800 VDC 與微電網

Source link 來源連結

[R13a] Infineon

Infineon collaborates with NVIDIA on gallium nitride-based power conversion systems for 800 VDC AI data centers

2026-10-21
GaN intermediate-bus conversion
GaN 中間匯流排轉換

Source link 來源連結

[R13b] Infineon

Infineon introduces industry-first 24 kW SiC-based battery backup unit reference design for high-voltage AI data center architecture

2026-06-02
Reference-design performance; industry-first is the vendor description
參考設計性能;業界首創為企業自身描述

Source link 來源連結

[R14] Uptime Institute

Explaining the Uptime Institute’s Tier Classification System

April 2021 update
Concurrent maintainability and fault tolerance
可同時維護與容錯

Source link 來源連結

[R15] GlobalPetrolPrices

Saudi Arabia business electricity prices

March 2026 observations
Third-party screening benchmark
沙烏地阿拉伯企業電價,第三方初篩參考

Source link 來源連結

[R16] GlobalPetrolPrices

India business electricity prices

March 2026 observations
Third-party screening benchmark
印度企業電價,第三方初篩參考

Source link 來源連結

[R17] GlobalPetrolPrices

Malaysia business electricity prices

March 2026 observations
Third-party screening benchmark
馬來西亞企業電價,第三方初篩參考

Source link 來源連結

[R18] GlobalPetrolPrices

China business electricity prices

March 2026 observations
Third-party screening benchmark
中國企業電價,第三方初篩參考

Source link 來源連結

[R19] GlobalPetrolPrices

South Korea business electricity prices

March 2026 observations
Third-party screening benchmark
韓國企業電價,第三方初篩參考

Source link 來源連結

[R20] GlobalPetrolPrices

South Africa business electricity prices

March 2026 observations
Third-party screening benchmark
南非企業電價,第三方初篩參考

Source link 來源連結

[R21] GlobalPetrolPrices

Brazil business electricity prices

March 2026 observations
Third-party screening benchmark
巴西企業電價,第三方初篩參考

Source link 來源連結

[R22] GlobalPetrolPrices

Japan business electricity prices

March 2026 observations
Third-party screening benchmark
日本企業電價,第三方初篩參考

Source link 來源連結

[R23] GlobalPetrolPrices

Singapore business electricity prices

March 2026 observations
Third-party screening benchmark
新加坡企業電價,第三方初篩參考

Source link 來源連結

[R24] GlobalPetrolPrices

Australia business electricity prices

March 2026 observations
Third-party screening benchmark
澳洲企業電價,第三方初篩參考

Source link 來源連結

[R25] Vertiv

Understanding AI power demands: How standard Vertiv UPS systems support AI factory load dynamics

Accessed 2026-11-15
Supplier evidence under stated operating conditions
特定運轉條件下的供應商資料

Source link 來源連結

[R26] Vertiv

Advanced UPS controls mitigate risks of infrastructure stress from AI workloads’ power swings

Accessed 2026-11-15
Input smoothing and storage-assisted control
輸入功率平滑與儲能輔助控制

Source link 來源連結

Appendix G Citation and Document Control

附錄 G 引用與文件管理

Reference numbers appear after supported claims. Tables identify source groups and report calculations. Fixed assumptions and research recommendations are not external forecasts.

文獻編號列於受支持論點後。表格識別來源組別與本報告計算;固定假設與研究建議不是外部預測。

Live websites, tariff tables and investor pages may change. Before formal submission or procurement, retain dated source copies and update site-specific tariffs, quotations and delivery commitments.

網站、費率表與投資人頁面可能更新。正式提案或採購前,應保存具日期來源副本,並更新個別場址費率、報價與交付承諾。

Suggested attribution for calculated tables: Source: cited public data. Calculations by this report using 100 MW IT load, PUE 1.20 and 8,760 annual operating hours. Results are illustrative and are not supplier quotations.

計算表格建議註記:來源為所列公開資料。本報告依 100 MW IT 負載、PUE 1.20 及每年 8,760 小時運轉計算。結果為情境試算,不是供應商報價。

Document version 1.0. Research cut-off 15 November 2026. Prepared from the bilingual report and appendices in this conversation; no new tariff refresh was performed during Word production.

文件版本 1.0。資料截止 2026 年 11 月 15 日。依本次對話雙語報告與附錄整編;Word 製作階段未另行更新電價。