Fire Risk Reduction for Fab
Fab 防火減災專題研究
Management System and Detailed Implementation Plan
防火管理制度與詳細執行規劃
Complete consolidated report with six reviewable deliverables and editable forms
完整整合報告暨六項可審查交付成果與可編輯表單
26 October 2026 • Revision 0.1
2026 年 10 月 26 日 • 版本 0.1
Purpose and principal conclusion
目的與主要結論
Fab fire resilience depends on prevention, engineered protection, controlled work, emergency coordination and qualified production recovery. A cleared alarm or restored power supply does not establish readiness for qualified production.
晶圓廠防火韌性取決於預防、工程防護、受控作業、緊急協調與合格生產復原。警報解除或恢復供電,本身不代表已具備恢復合格生產的條件。
This report consolidates the fire risk framework, management system and detailed implementation plan discussed for this project. It is intended for owners, EHS, facilities, equipment, process, manufacturing, quality, procurement and contractors.
本報告整合本專案前述防火風險架構、管理制度及詳細執行規劃,供業主、環安衛、廠務、設備、製程、製造、品質、採購與承攬管理使用。
No site survey, engineering calculation, physical test, legal compliance review or operational approval is represented as completed. Proposed controls require site-specific validation. Unknown information remains TBD; example records are not observed defects.
本報告不將現勘、工程計算、實體試驗、法規符合性審查或運轉核准列為已完成。建議措施須經廠址專屬驗證。未知資訊保留 TBD/待確認;示例紀錄不是現場已觀察缺失。
Document Control and Reading Guide
文件管制與閱讀指引
| Field 欄位 |
Entry 內容 |
| Document ID / Revision 文件編號/版本 |
FAB-FIRE-MGT-001 / 0.1 — Proposed 建議編號與版本 |
| Site / Owner 廠址/業主 |
TBD / 待確認 |
| Preparer / Reviewer / Approver 編製/審查/核准 |
TBD / 待確認 |
| Status 狀態 |
DRAFT FOR SITE REVIEW 現場審查草案 |
| Accepted scope / Effective date 接受範圍/生效日期 |
TBD — No operational authorization 待確認;尚未授權現場執行 |
The following chapters distinguish published reference scope, proposed management requirements and information requiring site verification. The programme establishes a baseline and a first verification cycle; it does not promise a post-fire recovery deadline.
以下章節區分公開參考依據、建議管理要求與待現場驗證資訊。推動計畫用於建立基線與首輪驗證,不構成火災後復工期限承諾。
| Chapters 章節 |
Contents 內容 |
| 01–03 | Research basis, objectives, scope and governance 研究依據、目標、範圍與治理 |
| 04–06 | Risk inventory, engineering protection and control interfaces 風險盤點、工程防護與控制介面 |
| 07–09 | Work permits, maintenance, change and procurement 作業許可、維護、變更與採購 |
| 10–12 | Training, response and production release 訓練、應變與生產放行 |
| 13–16 | Implementation, investment, metrics and deliverable acceptance 推動時程、投資、指標與成果驗收 |
| Appendices A–F | Editable records for D1–D6 D1–D6 可編輯紀錄 |
01 Research Basis and Evidence
01 研究依據與證據
NFPA 318 addresses protection of semiconductor fabrication facilities and comparable processes, including relevant research and development areas. SEMI S14 addresses fire risk assessment and mitigation for semiconductor manufacturing equipment. These references support the assessment scope, not certification of an individual fab. [1,2]
NFPA 318 涵蓋半導體製造設施及相近製程的防護,包括相關研發區域。SEMI S14 涵蓋半導體製造設備火災風險評估與減災。引用資料支持評估範圍,不構成個別晶圓廠的認證。[1,2]
OSHA 1910.39 identifies elements of a fire prevention plan, including major fire hazards, hazardous-material handling and storage, ignition-source controls, combustible-waste control, maintenance and responsible personnel. It is a US reference and is not automatically applicable to a site elsewhere. [3]
OSHA 1910.39 列出防火計畫要素,包括主要火災危害、危害物質處理與儲存、火源控制、可燃廢棄物控制、維護與負責人。此為美國參考要求,不自動適用於其他地區廠址。[3]
Before design or procedure release, responsible professionals must confirm jurisdictional requirements, approved drawings, permit conditions, insurer and customer obligations, project-adopted editions and evaluation scope. This report does not assert compliance with inaccessible full standard clauses.
設計或程序放行前,負責專業人員須確認所在地要求、核准圖說、許可條件、保險及客戶義務、專案採用版本與評估範圍。本報告不宣稱符合未取得全文的標準條文。
| Evidence class 證據類別 |
Use and limitation 用途與限制 |
| Published facts 公開事實 |
Official scope and published requirements; cite source and access date. 官方範圍與公開要求;記錄來源及查閱日期。 |
| Engineering proposals 工程建議 |
Priorities, workflows and ninety-day programme require project adoption. 優先級、流程及九十天計畫須由專案核定。 |
| Site verification 現場驗證 |
Capacity, inventories, conditions and performance remain TBD until evidenced. 能力、庫存、現況與性能須有證據後才能確認。 |
Fire protection media, detector thresholds, time delays, flows, pressure, design duration and impairment limits must follow the approved site basis. No generic values are prescribed here.
消防介質、偵測門檻、延遲、流量、壓力、設計持續時間及停用限制須依核准現場基準;本報告不設定通用數值。
02 Objectives and Assessment Scope
02 目標與評估範圍
| Objective 目標 |
Requirement and evidence 要求與證據 |
| Life safety 人員安全 |
Notification, evacuation, access control and rescue handover; training and accountability records. 通報、疏散、進入管制與救援交接;訓練及清點紀錄。 |
| Ignition prevention 預防起火 |
Control electrical, thermal, reaction and hot-work hazards; assessments, permits and maintenance records. 控制電氣、熱源、反應及動火危害;評估、許可與維護紀錄。 |
| Containment 限制擴散 |
Verify compartments, detection, isolation, protection and utility interfaces. 驗證區劃、偵測、隔離、防護及公用介面。 |
| Asset protection 資產保護 |
Evaluate fire, smoke, corrosive products and suppression impacts on tools and wafers. 評估火、煙、腐蝕產物及滅火作業對機台與晶圓的影響。 |
| Qualified recovery 合格復原 |
Separate facilities, tool, process and quality release evidence. 分開確認廠務、設備、製程與品質放行證據。 |
Include cleanrooms, subfabs, service areas, gas and chemical supply, storage, exhaust and abatement, power and backup systems, fire water, loading areas, construction and maintenance. Map shared services that can turn a local event into plant-wide interruption.
範圍包括無塵室、次製程層、服務區、氣體化學品供應、倉儲、排氣與尾氣處理、電力與備援、消防供水、裝卸、施工與維修。標示可能使局部事件擴大為全廠中斷的共用服務。
The integrated strategy is to reduce ignition and fuel, detect and isolate abnormal conditions, contain and suppress the event, maintain essential safety functions and restore qualified production through controlled gates.
整合策略為減少火源與燃料、偵測及隔離異常、限制與控制事件、維持必要安全功能,並經受控關卡恢復合格生產。
Readiness requires named owners, controlled work, traceable evidence, tracked corrective actions and authorized recovery. A completed document alone does not demonstrate operational readiness.
制度就緒須具備明確責任人、受控作業、可追溯證據、改善追蹤與復原授權。文件完成本身不能證明現場已具備執行能力。
03 Governance and Approval Authority
03 組織治理與核准權責
| Role 角色 |
Accountability 責任與核准 |
| Site management 廠區主管 |
Approve policy and resources; resolve conflicts; accept defined recovery scope and review residual risks. 核定政策與資源、處理衝突、接受明確復產範圍並審查剩餘風險。 |
| EHS coordinator 環安衛統籌 |
Maintain system, risk register, training, audits and action tracking; review controls within delegated authority. 維護制度、風險、訓練、稽核與改善追蹤;依授權審查管制。 |
| Facilities 廠務 |
Own compartments, fire protection, utilities, impairment, restoration and facilities acceptance. 負責區劃、消防、公用服務、停用、復歸及廠務驗收。 |
| Equipment and process 設備與製程 |
Own tool protection, material and process limits, interlocks, maintenance, changes and supplier coordination. 負責設備防護、物料與製程界限、連鎖、保養、變更及供應商協調。 |
| Quality and manufacturing 品質與製造 |
Control work in process, qualification, capacity release and ramp monitoring. 管理在製品、資格確認、產能放行及爬升監測。 |
| Incident command and responders 事故指揮及應變人員 |
Direct notification, evacuation, access and rescue handover within training and authorization. 依訓練與授權執行通報、疏散、管制及救援交接。 |
| Procurement and contractors 採購與承攬商 |
Implement supplier requirements, work permits, installation records and acceptance evidence. 落實供應商要求、作業許可、安裝紀錄及驗收證據。 |
Assign a primary and alternate for each critical role across nights, holidays and absences. Anyone identifying immediate danger may report it and stop affected work under site rules; only authorized personnel may release work to resume.
每一關鍵角色須指定主責與代理人,涵蓋夜班、假日及缺席。發現立即危險者可依現場規則通報並停止相關作業;恢復作業須由授權人核准。
Separate execution, verification and closure according to risk. Safety-critical items require independent review. Management acceptance of residual risk cannot waive applicable legal duties or necessary engineering verification.
依風險區分執行、驗證與結案角色;安全關鍵項目須獨立複核。管理層接受剩餘風險不得取代適用法定義務或必要工程驗證。
04 Baseline Survey and Fire Risk Register
04 基線調查與火災風險清冊
| Data group 資料群組 |
Required input 必要輸入 |
| Building and compartments 建築與區劃 |
Floors, uses, barriers, penetrations, doors, escape routes and responder access. 樓層、用途、區劃、貫穿、防火門、逃生及救援入口。 |
| Equipment 設備 |
Asset ID, model, configuration, heat sources, electrical load, combustible materials and safeguards. 資產編號、型號、組態、熱源、電氣負載、可燃材料及防護。 |
| Chemicals and gases 化學品與氣體 |
Hazards, maximum anticipated inventory, locations, supply method and safety data sheets. 危害、最大預期庫存、位置、供應方式與安全資料表。 |
| Exhaust and abatement 排氣與尾氣處理 |
Service scope, materials, deposits, cleaning and shutdown dependencies. 服務範圍、材質、沉積、清理及停機相依條件。 |
| Protection and production 防護與生產 |
Detection, suppression, water, backup, tests, bottlenecks, spares and affected products. 偵測、滅火、供水、備援、測試、瓶頸、備品及受影響產品。 |
Each risk record requires ID, asset and location, initiating event, failure mechanism, consequences, existing protection, evidence, gaps, priority, interim controls, owner, due date and residual risk. Include normal, abnormal, maintenance and construction states.
每筆風險須記錄編號、資產位置、起始事件、失效機制、後果、現有防護、證據、缺口、優先級、臨時措施、負責人、期限及剩餘風險。涵蓋正常、異常、維修及施工狀態。
Hazard maps and registers must use the same asset IDs and drawing revisions. Show material areas, compartments, utilities, isolation points, access restrictions and shared dependencies. Do not invent locations without a verified plan.
危害地圖與清冊須使用相同資產編號及圖說版本,標示物料區、區劃、公用系統、隔離點、進入限制與共用相依關係;無確認平面圖時不得虛構位置。
Example only: FR-001 / EQ-TBD / location TBD / protection evidence unavailable / potential undetected tool fire / documentation and engineering review required / owner and due date TBD / OPEN. This is not an observed defect.
僅供示例:FR-001/EQ-TBD/位置待確認/防護證據未取得/可能無法及時偵測設備火災/需文件及工程審查/負責人與期限待確認/未結。此紀錄不是已觀察缺失。
05 Priorities and Engineering Protection
05 優先級與工程防護
| Priority 優先級 |
Basis and response 依據與處置 |
| P1 Immediate 立即控制 |
Identified immediate danger, uncontrolled hazard or failed critical protection: restrict affected work, establish interim controls and escalate immediately. 已識別立即危險、未受控危害或關鍵保護失效:立即限制作業、建立臨時控制並升級通報。 |
| P2 Critical 優先改善 |
Potential major event, cross-zone spread or common-cause interruption: define corrective scope, deadline and interim restrictions. 可能重大事故、跨區擴散或共因中斷:訂定改善範圍、期限及期間限制。 |
| P3 Planned 計畫改善 |
Existing controls can be improved or recovery shortened: include engineering, maintenance, spares and training in planned investment. 既有控制仍可改善或縮短復原:納入工程、保養、備品及訓練投資。 |
Do not rank solely by a risk-score product. Establish separate escalation rules for severe personnel consequences and protection failures. Unknown protection capacity remains unverified rather than safe by default.
不得僅依單一風險乘積排序;嚴重人員後果與保護失效須另設升級條件。未知防護能力維持待驗證,不得預設安全。
Review tool overheating, electrical faults, material combustion, leaks and combustion byproducts. For chemicals and gases, review compatibility, storage and supply isolation. For exhaust and abatement, review deposits, propagation, treatment failure and cleaning access.
審查設備過熱、電氣故障、材料燃燒、洩漏與燃燒產物;化學品與氣體檢查相容性、儲存及供應隔離;排氣與尾氣處理檢查沉積、傳播、處理失效與清理可及性。
Verify compartment integrity, new penetrations, detector and suppression suitability, supply capability, power isolation and essential backups. Match evidence to the actual installation and configuration; substitutions require an applicability review.
驗證區劃完整性、新增貫穿、偵測與滅火適用性、供應能力、電力隔離及必要備援。證據須對應實際安裝與組態;替代品須適用性審查。
Compound earthquake and fire scenarios should cover displaced piping and leaks, damaged fire-water supports or valves, compromised compartments, common-cause loss of sensing or isolation and obstructed access.
地震與火災複合情境應涵蓋管線位移洩漏、消防供水支承或閥件受損、區劃破壞、偵測或隔離共因失效,以及進出動線受阻。
06 Interfaces and Analysis Verification
06 介面與分析驗證
D2 records each protection interface and complete dependency path. D3 establishes what was assessed, by which method, for which configuration, and what the evidence supports. Keep containment, protective function and production quality as separate conclusions.
D2 記錄每項防護介面與完整相依路徑。D3 說明評估對象、方法、組態及證據支持範圍。密封保持、防護功能與生產品質須分別作成結論。
| Record 紀錄 |
Required information 必要資訊 |
| Interface matrix 介面矩陣 |
Interface ID; asset IDs; drawing revision; demand and demonstrated capability; source; parties; gap; corrective action; status. 介面編號、資產編號、圖說版本、需求與已證明能力、來源、責任、缺口、改善及狀態。 |
| Scenario and action matrix 情境與動作矩陣 |
Trigger; confirmation; isolation; safety functions to maintain; loss of power or signal response; manual authority; reset criteria. 觸發、確認、隔離、須維持功能、斷電或訊號遺失反應、手動權限及復歸準則。 |
| Analysis basis 分析基準 |
Objectives, criteria, inputs, models, assumptions, configurations, exclusions and uncertainty. 目標、準則、輸入、模型、假設、組態、排除項與不確定性。 |
| Test plan and results 試驗計畫與結果 |
Approved procedure, representative state, instrumentation, prechecks, acceptance, abort criteria, raw results and deviations. 核准程序、代表狀態、儀器、試前檢查、驗收、中止條件、原始結果及偏差。 |
Blanket removal of power or shutdown of all exhaust is not a universal safe action. Exhaust, abatement, cooling, purge and monitoring may be required. Determine safe states from the material, equipment and approved incident scenario.
全面斷電或停止所有排氣不是通用安全動作;排氣、尾氣處理、冷卻、吹掃與監測可能仍須維持。安全狀態須依物料、設備及核准事故情境決定。
An interface remains OPEN when required performance or demonstrated capability is unverified. Raw evidence must be traceable; disclose failed tests and deviations. Testing must be authorized and controlled so that verification does not create an uncontrolled operational hazard.
需求性能或已證明能力未確認時,介面維持未結。原始證據須可追溯,揭露試驗失敗與偏差。測試須經授權及受控,避免驗證本身造成未受控運轉危害。
07 Work Permits and Operational Restrictions
07 作業許可與運轉限制
| Activity 作業 |
Before work 作業前 |
During and after work 作業中與完工後 |
| Hot work 動火 |
Review nearby and concealed hazards, isolation and fire watch. 審查周邊、隱蔽危害、隔離與監火。 |
Monitor permit conditions; inspect completion and apply risk-based post-work watch. 監控許可條件、完工檢查與依風險核定後續監火。 |
| Protection impairment 防護停用 |
Define scope, alternatives, duration, notifications and approval. 定義範圍、替代措施、期限、通知及核准。 |
Track restrictions; escalate expiry; test restoration before closure. 追蹤限制、逾期升級、復歸測試後結案。 |
| Interlock bypass 連鎖旁路 |
Specify purpose, impact, temporary controls and authority. 明定目的、影響、臨時控制及權限。 |
Record status; verify full function after removal. 記錄狀態;解除後驗證完整功能。 |
| Chemical maintenance 化學系統維修 |
Verify isolation, residues and work conditions under dedicated procedures. 依專用程序確認隔離、殘留與作業條件。 |
Control interfaces and contamination; verify integrity and function before handback. 管制介面污染;交回前驗證完整性與功能。 |
| Temporary electricity 臨時用電 |
Review load, protection, routing, environment and expiry. 審查負載、保護、配線、環境及期限。 |
Inspect; stop abnormal use; remove or formally accept after work. 檢查、異常停用、完工拆除或正式驗收。 |
| Penetrations 施工貫穿 |
Review compartments and existing services. 審查區劃及既有服務。 |
Inspect firestopping and update drawings. 查驗防火封堵並更新圖說。 |
Every permit identifies location, scope, validity, owner, supervisor, stop conditions and closure. Reconfirm conditions and responsibility when work crosses shifts or changes scope. No hot work begins before permit and field confirmation.
許可須記錄位置、範圍、有效期、主責、監督、停止條件與結案。跨班或範圍變更須重新確認條件與責任。未完成許可及現場確認不得動火。
Do not bypass protection without authorization. Restrict affected operations when safety-critical defects are uncontrolled. Keep egress, fire doors and fire-equipment access usable. New tools, materials and major changes require pre-start review.
不得未經授權旁路防護;安全關鍵缺失未受控時限制受影響運轉。維持逃生、防火門及消防操作空間可用。新機台、物料及重大變更須啟用前審查。
08 Inspection Maintenance and Impairment
08 檢查維護與防護停用
Create asset-level inspection and maintenance tasks with method, interval basis, acceptance criteria, required competence and abnormal-condition response. Statutory, approved design and manufacturer requirements must be identified before scheduling.
依資產建立檢查維護項目,列明方法、週期依據、驗收準則、人員資格及異常處置。排程前須識別法定、核准設計與製造商要求。
| Timing 時機 |
Management activity 管理活動 |
| Each shift or before work 每班或作業前 |
Review alarms, impairments, bypasses, egress and high-risk work. 確認警報、停用、旁路、逃生及高風險作業。 |
| Weekly coordination 每週協調 |
Coordinate construction, maintenance, protection outages and production windows; avoid overlapping protection losses. 協調施工、維修、防護停用與生產窗口,避免防護同時失效。 |
| Monthly review 每月檢討 |
Review overdue work, repeated faults, impairment duration, spares and corrective progress. 檢視逾期工單、重複異常、停用時間、備品及改善。 |
| Scheduled technical checks 排定技術檢測 |
Apply relevant requirements, supplier instructions and risk-based intervals. 依適用要求、供應商指引與風險排定。 |
| After change or incident 變更或事件後 |
Confirm affected functions, update records and perform necessary revalidation. 確認受影響功能、更新紀錄及必要重驗。 |
This cadence is a management proposal, not a universal statutory test frequency. Record actual completion and evidence rather than marking a calendar task complete without verification.
上述節奏為管理建議,並非通用法定檢測頻率。應記錄實際完成及證據,不得只勾選日曆任務而未驗證。
Impairment workflow: request → impact assessment → interim measures → approval and notification → implementation → restoration test → field confirmation → closure. Reassess if risk changes, alternatives fail or validity expires; extensions are not automatic.
停用流程:申請→影響評估→臨時措施→核准通知→執行→恢復測試→現場確認→結案。風險改變、替代措施失效或期限屆滿時須重評,不得自動展延。
Every defect requires ID, location, risk, interim measures, owner, due date, verification evidence and closure authority. Notification or a completed meeting is not closure evidence.
缺失均須有編號、位置、風險、臨時措施、主責、期限、驗證證據及結案權責。已通知或已開會不是結案證據。
09 Change Management and Procurement
09 變更管理與採購
Trigger reassessment for tool relocation, new materials or quantities, altered pipes or exhaust, changes to safety logic, electrical loads or compartments, revised design information and damage after an event. A single change record must identify all affected D1–D6 documents.
設備搬遷、新物料或數量、管線排氣改動、安全邏輯、電氣負載或區劃變更、設計資料修訂及事件後損傷,均須觸發重評。透過同一變更紀錄識別全部受影響 D1–D6 文件。
The change process comprises request, risk and interface review, design approval, installation control, pre-start verification, training, drawing updates and authorized handover. Temporary changes require expiry and a return-to-normal plan.
變更流程包括申請、風險與介面審查、設計核准、安裝管制、啟用前驗證、訓練、圖說更新及授權交接。臨時變更須有期限及恢復原狀計畫。
| Procurement requirement 採購要求 |
Acceptance evidence 驗收證據 |
| Configuration-specific safety data 組態專屬安全資料 |
Applicable tool version, materials, interfaces, limits and residual risks. 適用機台版本、物料、介面、界限與剩餘風險。 |
| Installation and commissioning 安裝與試運轉 |
Approved instructions, installation checks and functional test records. 核准指引、安裝檢查與功能測試。 |
| Maintenance and support 維護與支援 |
Inspection methods, spare availability, response arrangements and post-event support. 檢查方法、備品可得性、應變安排及事件後支援。 |
| Substitution control 替代品管制 |
Documented engineering applicability review before acceptance. 接受前完成工程適用性審查。 |
| Final handover 最終交付 |
Accepted evidence, updated drawings, training and open-item disposition. 已接受證據、更新圖說、訓練及未結事項處置。 |
Procurement completion is not engineering completion. Close a work package only after installation, functional verification and affected documentation are accepted. Do not treat supplier claims as demonstrated site performance without an applicability review.
完成採購不等於工程完成。安裝、功能驗證及受影響文件獲接受後才能結案;未經適用性審查,不得將供應商聲明直接視為現場已證明性能。
10 Training and Recovery Exercises
10 教育訓練與復原演練
| Audience 對象 |
Competence and verification 能力與確認 |
| All personnel 全體人員 |
Recognize alarms, report, evacuate and account for people; verify routes and scenario responses. 辨識警報、通報、疏散及清點;確認路線與情境反應。 |
| Operators 操作人員 |
Recognize abnormal signs and authorized safe actions; demonstrate stop conditions. 辨識異常與授權安全操作;確認停止條件。 |
| Facilities and equipment 廠務與設備 |
Control isolation, bypass, impairment and reset; verify procedures and records. 管理隔離、旁路、停用及復歸;驗證程序與紀錄。 |
| Emergency responders 應變人員 |
Command, hazard assessment, boundaries and rescue handover within qualification. 依資格執行指揮、危害辨識、管制與救援交接。 |
| Contractors 承攬商 |
Understand permits, restrictions, reporting and handover; inspect field compliance. 理解許可、限制、通報及交接;抽查現場符合性。 |
| Management and quality 管理層與品質 |
Decide restrictions, resources, WIP disposition and release; test decisions through tabletop exercises. 決策限制、資源、在製品處置及放行;桌上演練確認。 |
Proposed first exercise: a tool alarm and suspected leak coincide with limited exhaust while one protection system is under maintenance. Inject night-shift resource shortages or delayed supplier support. Participants identify affected scope, essential functions and blocked release gates.
建議首輪演練:設備警報與疑似洩漏同時發生,局部排氣受限且一項防護正在維修;再加入夜班人力不足或供應商延遲。參與者須識別影響範圍、必要功能與不可放行關卡。
Record scenario assumptions, boundaries, notifications, decisions, inspections, simulated release times, delays, missing information and resource conflicts. Separate actual from simulated actions. Tabletop exercises do not prove physical protection capability or actual recovery duration.
記錄情境假設、邊界、通報、決策、檢查、模擬放行時間、延遲、缺漏資訊與資源衝突。實際與模擬動作分開記錄;桌上演練不證明實體防護能力或實際復原時間。
Findings require cause analysis, owner, action, due date, evidence and independent closure review. Repeat an exercise or test when needed to demonstrate effectiveness.
缺失須有原因分析、主責、措施、期限、證據與獨立結案審查;必要時重新演練或測試以證明有效。
11 Emergency Response and Safe States
11 緊急應變與安全狀態
Site procedures must identify alarm and reporting channels, internal command, external emergency contacts, evacuation and accountability arrangements, access boundaries, hazardous-material information and rescue handover. Names and numbers remain TBD until site confirmation.
現場程序須明定警報通報管道、內部指揮、外部緊急聯絡、疏散清點、進入邊界、危害物質資訊及救援交接。姓名與電話在現場確認前保留待確認。
| Response phase 應變階段 |
Required decision or record 必要決策或紀錄 |
| Recognition and notification 辨識與通報 |
Record location, observed signs, affected assets and information uncertainty; follow approved reporting channels. 記錄位置、觀察徵兆、受影響資產與不確定性,依核准管道通報。 |
| People and boundaries 人員與範圍 |
Evacuate and account for personnel; define exclusion and authorized access boundaries. 疏散清點;劃定禁止及授權進入範圍。 |
| Authorized safe-state actions 授權安全狀態動作 |
Apply only validated scenario-specific isolation and utility actions. 僅執行經驗證且對應情境的隔離與公用動作。 |
| External response handover 外部救援交接 |
Provide site layout, materials, utilities, missing-person status and known restrictions. 提供配置、物料、公用服務、人員清點及已知限制。 |
| Stabilization and recovery 穩定與復原 |
Preserve records; assess residual hazards and transfer to controlled release gates. 保留紀錄、評估殘餘危害並轉入受控放行。 |
Initial intervention is limited to trained and authorized personnel under permitted conditions. Do not use this management framework as a substitute for incident-specific firefighting or hazardous-material procedures.
初期應變限受訓且獲授權人員在允許條件下執行。本管理架構不取代特定事故的消防或危害物質處置程序。
Keep essential safety functions available as defined by the approved scenario. A loss of exhaust, cooling, purge, monitoring or fire protection may require a different restricted operating state even when production equipment appears intact.
依核准情境維持必要安全功能。即使生產設備外觀完整,排氣、冷卻、吹掃、監測或消防防護失效,仍可能需要採取不同的限制運轉狀態。
12 Inspection and Production Release
12 檢查與生產放行
| Gate 關卡 |
Required evidence 必要證據 |
Proposed authority 建議權責 |
| G1 Access 進入安全 |
Hazards, access boundaries, residual risk and personnel control. 危害、進入邊界、剩餘風險與人員管制。 |
Incident command and EHS; respect authority restrictions. 事故指揮與環安衛;遵循主管機關限制。 |
| G2 Facilities 建築廠務 |
Appropriate building inspection, fire protection, utilities and essential safety functions. 適當建築檢查、消防、公用服務及必要安全功能。 |
Facilities and qualified professionals. 廠務及合格專業人員。 |
| G3 Tools 設備 |
Damage, smoke or corrosion, interlocks, calibration and function. 損傷、煙塵或腐蝕、連鎖、校正及功能。 |
Equipment engineering and required suppliers. 設備工程與必要供應商。 |
| G4 Process 製程品質 |
Environment acceptance, WIP disposition, test wafers and qualification. 環境接受、在製品處置、試片與資格確認。 |
Process and quality. 製程與品質。 |
| G5 Ramp 產能恢復 |
Authorized capacity, monitoring, exceptions and rollback criteria. 核准產能、監測、異常及回退條件。 |
Manufacturing and site management. 製造與廠區主管。 |
Release by defined area, asset and permitted operating state. Record evidence IDs, restrictions, unresolved items, approver and time. Local acceptance does not release the entire fab. Unresolved safety-critical findings block release of affected scope.
按明確區域、資產及允許狀態放行,記錄證據編號、限制、未結事項、核准人與時間。局部通過不代表全廠通過;安全關鍵未結事項阻止受影響範圍放行。
Alarm clearance, re-energization and qualified production require separate decisions. Identify and hold or disposition WIP through the approved quality process. Assess contamination and product impact rather than assuming undamaged external appearance is sufficient.
警報解除、重新送電及合格生產須分別決策。在製品須識別並依核准品質程序隔離或處置;應評估污染與產品影響,不得只依外觀無損判定。
New alarms, leakage, odor, abnormal temperature or vibration, unstable utilities, changed damage observations and relevant aftershocks trigger reassessment under site criteria. Stop or restrict the affected scope when rollback conditions are met.
新增警報、洩漏、異味、異常溫度或振動、公用服務不穩、損傷觀察改變及相關餘震,依現場準則觸發重評;符合回退條件時停止或限制受影響範圍。
13 Ninety Day Implementation Programme
13 九十天推動計畫
| Period 期間 |
Main work 主要工作 |
Decision and evidence 決策與證據 |
| Days 1–15 第 1–15 天 |
Appoint roles; define scope; collect drawings; inventory impairments and major risks. 任命角色、定義範圍、收圖、盤點停用及重大風險。 |
Approve ownership, gaps and immediate controls. 核定權責、缺口及立即控制。 |
| Days 16–30 第 16–30 天 |
Prepare register, map, interfaces, objectives, analysis plan and draft procedures. 建立清冊、地圖、介面、目標、分析計畫及程序初稿。 |
Approve assessment basis and priorities. 核定評估基準與優先項目。 |
| Days 31–45 第 31–45 天 |
Review high-risk tools and shared systems; implement permit and impairment controls. 審查高風險設備與共用系統,導入許可及停用管制。 |
Approve work packages and pilot procedures. 核准工作包與試行程序。 |
| Days 46–60 第 46–60 天 |
Train staff; pilot selected areas; complete verification where prerequisites are met. 訓練、區域試行及具備條件項目驗證。 |
Confirm executable procedures and evidence quality. 確認可執行性及證據品質。 |
| Days 61–75 第 61–75 天 |
Run tabletop and suitable field exercises; sample night shifts and contractor work. 桌上與適當現場演練,抽查夜班及承攬作業。 |
Record findings, causes and actions. 形成缺失、原因及改善。 |
| Days 76–90 第 76–90 天 |
Verify corrections; conduct management review; issue system and phased investment plan. 複核改善、管理審查、發布制度與分期投資。 |
Accept completed scope and assign remaining gaps. 接受已完成範圍並指派剩餘缺口。 |
Control high-risk conditions immediately rather than waiting for programme completion. Major structural or fire-protection retrofits, shutdown work and long-lead procurement require separate schedules. Ninety days is a planning proposal, not a fire recovery commitment.
高風險事項須立即控制,不等待計畫完成。大型結構或消防補強、停機工程及長交期採購另訂時程。九十天為推動建議,不是火災復原承諾。
The programme sponsor reviews resource conflicts and dependencies at each decision point. Unavailable evidence is carried as an open item with restrictions, not marked complete to meet the calendar.
專案主管於各決策點審查資源衝突與相依條件。證據未取得者列為未結並保留限制,不得為配合日期而標示完成。
14 Investment and Work Package Planning
14 投資與工作包規劃
Prioritize personnel exposure, hazardous release, common-cause interruption, bottleneck production and execution constraints. Assign packages to immediate controls, priority engineering or planned recovery improvements.
排序考慮人員暴露、危害物質洩漏、共因中斷、瓶頸產能及執行限制;工作包分配至立即控制、優先工程或計畫性復原改善。
| Budget group 預算類別 |
Scope 範圍 |
| Survey and data 調查與資料 |
Asset survey, drawing reconciliation and inventory verification. 資產調查、圖說核對及庫存確認。 |
| Engineering 工程分析 |
Risk studies, interface analysis, design and independent review. 風險研究、介面分析、設計與獨立審查。 |
| Physical improvements 硬體改善 |
Approved tool, compartment, detection, protection or utility work. 核准機台、區劃、偵測、防護或公用改善。 |
| Inspection and testing 檢查測試 |
Installation acceptance, functional checks and integrated verification. 安裝驗收、功能檢查與整合驗證。 |
| Training and exercise 訓練演練 |
Role training, scenario exercises and effectiveness checks. 角色訓練、情境演練及有效性確認。 |
| Maintenance and spares 維護備品 |
Critical spares, service arrangements and recurring inspection. 關鍵備品、服務安排與定期檢查。 |
Each package records scope, drawings, quantities, cost basis, dependencies, procurement lead time, outage window, interim measures, installation checks, functional acceptance and closure authority. Separate supplier quotations, estimates and allowances.
每個工作包須記錄範圍、圖說、數量、成本依據、相依條件、採購交期、停機窗口、臨時措施、安裝檢查、功能驗收及結案權責;區分供應商報價、工程估算與暫列金額。
No monetary estimate is offered before scope and quantities are confirmed. Track approved budget, commitments, actual costs and forecast separately, including taxes, currency assumptions and contingency basis when applicable.
範圍與數量未確認前不提供虛構金額。分開追蹤核定預算、承諾支出、實支及預測;適用時記錄稅額、幣別假設及預備金依據。
15 Performance Measures and Management Review
15 績效指標與管理審查
| Metric 指標 |
Definition and reporting boundary 定義與報告邊界 |
| Critical protection verification 關鍵防護驗證率 |
Verified critical safeguards / identified critical safeguards. Also disclose inventory completeness and evidence validity. 有效驗證項目/已識別關鍵項目;另揭露盤點完整度及證據有效性。 |
| Overdue high-risk findings 逾期高風險缺失 |
Counts and age by priority, with interim-control status. 依優先級記錄件數、逾期時間與臨時措施狀態。 |
| Impairment exposure 防護停用暴露 |
Hours by system and area, including overlapping impairments. 按系統與區域記錄時數,包含重疊停用。 |
| Permit compliance 作業許可符合率 |
Compliant sampled permits / sampled permits; disclose sample and severe exceptions. 抽查符合件數/抽查件數;揭露樣本及重大違規。 |
| Training competence 訓練能力達成率 |
Personnel passing role confirmation / personnel required to complete it. 通過角色能力確認人數/應完成確認人數。 |
| Action effectiveness 改善有效率 |
Verified effective corrections / corrections due for verification. 經驗證有效件數/應完成驗證件數。 |
| Recovery performance 復原表現 |
Essential utility restoration time and qualified capacity relative to the defined pre-event baseline. 必要公用恢復時間與相對已定義震前或事件前基準的合格產能。 |
Define scope, denominator, observation period, owner and data source before reporting. An undefined or zero denominator is not automatically 100% compliance. Separate exercise times from actual incident results.
報告前定義範圍、分母、觀察期間、主責及資料來源。分母未定義或為零不代表百分之百符合;演練時間與實際事件結果分開呈現。
Set targets after baseline review. Monthly review addresses trends, repeated failures, overdue actions and resources; scheduled management review accepts defined evidence and assigns remaining gaps. Zero reported incidents alone does not establish effectiveness.
基線審查後核定目標。每月檢討趨勢、重複失效、逾期措施及資源;定期管理審查接受明確證據並指派剩餘缺口。僅零通報事故不能證明有效。
16 Deliverable Acceptance and Document Control
16 成果驗收與文件管制
| Deliverable 交付成果 |
Acceptance requirements 驗收要求 |
| D1 Risk register and hazard map 風險清冊與危害地圖 |
Consistent IDs and revisions; evidence-backed ratings; all open items assigned. 編號版本一致、分級有證據、未結事項有主責。 |
| D2 Protection interface matrix 防護介面矩陣 |
Signals, actions, safety functions, dependencies, failure behavior and responsibilities documented. 訊號、動作、安全功能、相依、失效行為與責任完整。 |
| D3 Analysis and verification report 分析與驗證報告 |
Traceable basis, configuration, methods, results, deviations, limitations and raw records. 基準、組態、方法、結果、偏差、限制及原始紀錄可追溯。 |
| D4 Retrofit and procurement plan 補強與採購計畫 |
Priorities, cost basis, lead time, outages and acceptance defined; engineering closure verified. 優先級、成本、交期、停機與驗收明確;工程結案經驗證。 |
| D5 Response and release manual 應變與放行手冊 |
Shift authority, reporting, boundaries, WIP controls and G1–G5 established. 各班權限、通報、邊界、在製品及 G1–G5 完整。 |
| D6 Exercise and action register 演練與改善清冊 |
Actual and simulated records separated; causes, actions, deadlines and effectiveness evidenced. 區分實際模擬;原因、措施、期限與有效性有證據。 |
Every deliverable requires ID, revision, date, preparer, reviewer, approver, evidence index and open-item list. Use OPEN, UNDER REVIEW, ACCEPTED and SUPERSEDED status values. Approval identifies the exact accepted scope and any restrictions.
各成果須有編號、版本、日期、編製、審查、核准、證據索引及未結清單。狀態區分未結、審查中、已接受及已取代;核准須明定接受範圍與限制。
At publication, distinguish approved procedures, demonstrated staff competence, verified engineering protection and outstanding improvements. Confirm site, adopted requirements, owners, inspection intervals, emergency contacts and authority before operational adoption.
制度發布時區分程序已核定、人員具執行能力、工程防護已驗證及尚待改善。納入運轉前須確認廠址、採用要求、主責、檢查週期、緊急聯絡及權限。
Appendix A D1 Fire Risk and Hazard Map Record
附錄 A D1 火災風險與危害地圖紀錄
Copy this editable form for each record. Blank fields mean incomplete information, not acceptance. Attach calculations, drawings and tests by evidence ID.
每筆紀錄可複製本可編輯表單。空白代表待填,不代表通過。計算、圖說及試驗依證據編號附掛。
01 Risk ID and asset ID
風險編號與資產編號
____________________________________________________________________________
02 Floor zone grid and map revision
樓層、分區、軸線及地圖版本
____________________________________________________________________________
03 Operating state and initiating event
運轉狀態與起始事件
____________________________________________________________________________
04 Failure mechanism and consequences
失效機制與後果
____________________________________________________________________________
05 Materials inventory and exposed persons or processes
物料庫存與暴露人員或製程
____________________________________________________________________________
06 Existing safeguards and evidence IDs
現有防護與證據編號
____________________________________________________________________________
07 Rating basis priority and uncertainty
分級依據、優先級與不確定性
____________________________________________________________________________
08 Interim controls and restrictions
臨時措施與限制
____________________________________________________________________________
09 Corrective action owner and due date
改善措施、主責與期限
____________________________________________________________________________
10 Residual risk reviewer and status
剩餘風險、審查人與狀態
____________________________________________________________________________
Status: OPEN / UNDER REVIEW / ACCEPTED / SUPERSEDED
狀態:未結/審查中/已接受/已取代
Appendix B D2 Interface and Scenario Action Record
附錄 B D2 介面與情境動作紀錄
Copy this editable form for each record. Blank fields mean incomplete information, not acceptance. Attach calculations, drawings and tests by evidence ID.
每筆紀錄可複製本可編輯表單。空白代表待填,不代表通過。計算、圖說及試驗依證據編號附掛。
01 Interface ID connected assets and drawing revision
介面編號、連接資產與圖說版本
____________________________________________________________________________
02 Scenario trigger and confirmation conditions
情境、觸發及確認條件
____________________________________________________________________________
03 Required function demand and units
要求功能、需求與單位
____________________________________________________________________________
04 Demonstrated capability configuration and evidence
已證明能力、組態與證據
____________________________________________________________________________
05 Isolation action and safety functions to maintain
隔離動作與須維持安全功能
____________________________________________________________________________
06 Response to power signal or utility loss
斷電、訊號或公用喪失反應
____________________________________________________________________________
07 Manual authority and reset prerequisites
手動權限與復歸前提
____________________________________________________________________________
08 Supplier and site responsibilities
供應商與現場責任
____________________________________________________________________________
09 Gap corrective action owner and due date
缺口、改善、主責與期限
____________________________________________________________________________
10 Approval point restrictions and status
核准節點、限制與狀態
____________________________________________________________________________
Status: OPEN / UNDER REVIEW / ACCEPTED / SUPERSEDED
狀態:未結/審查中/已接受/已取代
Appendix C D3 Analysis and Verification Record
附錄 C D3 分析與驗證紀錄
Copy this editable form for each record. Blank fields mean incomplete information, not acceptance. Attach calculations, drawings and tests by evidence ID.
每筆紀錄可複製本可編輯表單。空白代表待填,不代表通過。計算、圖說及試驗依證據編號附掛。
01 Document ID objectives and adopted criteria
文件編號、目標與採用準則
____________________________________________________________________________
02 Asset configuration and drawing revisions
資產組態與圖說版本
____________________________________________________________________________
03 Inputs sources assumptions and uncertainty
輸入、來源、假設與不確定性
____________________________________________________________________________
04 Method model checks and excluded scope
方法、模型檢核與排除範圍
____________________________________________________________________________
05 Approved test procedure and representative state
核准試驗程序與代表狀態
____________________________________________________________________________
06 Instrumentation calibration and prechecks
儀器、校正與試前檢查
____________________________________________________________________________
07 Acceptance criteria and abort conditions
驗收準則與中止條件
____________________________________________________________________________
08 Raw evidence results failures and deviations
原始證據、結果、失敗與偏差
____________________________________________________________________________
09 Separate containment function and quality conclusions
分列密封、功能與品質結論
____________________________________________________________________________
10 Limitations reassessment triggers reviewer and date
限制、重評觸發、審查人與日期
____________________________________________________________________________
Status: OPEN / UNDER REVIEW / ACCEPTED / SUPERSEDED
狀態:未結/審查中/已接受/已取代
Appendix D D4 Retrofit and Procurement Work Package
附錄 D D4 補強與採購工作包
Copy this editable form for each record. Blank fields mean incomplete information, not acceptance. Attach calculations, drawings and tests by evidence ID.
每筆紀錄可複製本可編輯表單。空白代表待填,不代表通過。計算、圖說及試驗依證據編號附掛。
01 Package ID linked risks and priority
工作包編號、連結風險與優先級
____________________________________________________________________________
02 Scope drawings quantities and exclusions
範圍、圖說、數量與排除項
____________________________________________________________________________
03 Quotation estimate or allowance and cost basis
報價、估算或暫列金額及成本依據
____________________________________________________________________________
04 Currency taxes contingency and budget approval
幣別、稅額、預備金及預算核准
____________________________________________________________________________
05 Dependencies lead time and supplier support
相依、交期與供應商支援
____________________________________________________________________________
06 Outage window permits and interim measures
停機窗口、許可與臨時措施
____________________________________________________________________________
07 Configuration and substitution review
組態與替代品審查
____________________________________________________________________________
08 Installation inspection and functional acceptance
安裝查驗與功能驗收
____________________________________________________________________________
09 Training spares and drawing updates
訓練、備品與圖說更新
____________________________________________________________________________
10 Evidence outstanding items and closure authority
證據、未結事項與結案權責
____________________________________________________________________________
Status: OPEN / UNDER REVIEW / ACCEPTED / SUPERSEDED
狀態:未結/審查中/已接受/已取代
Appendix E D5 Controlled Production Release Record
附錄 E D5 受控生產放行紀錄
Copy this editable form for each record. Blank fields mean incomplete information, not acceptance. Attach calculations, drawings and tests by evidence ID.
每筆紀錄可複製本可編輯表單。空白代表待填,不代表通過。計算、圖說及試驗依證據編號附掛。
01 Incident ID gate and record revision
事件編號、關卡與紀錄版本
____________________________________________________________________________
02 Area assets and permitted operating state
區域、資產與允許運轉狀態
____________________________________________________________________________
03 Access limits and remaining hazards
進入限制與殘餘危害
____________________________________________________________________________
04 Facilities protection and utilities evidence
廠務、防護與公用證據
____________________________________________________________________________
05 Equipment inspection calibration and interlock evidence
設備檢查、校正與連鎖證據
____________________________________________________________________________
06 Environmental acceptance WIP and qualification evidence
環境接受、在製品與資格證據
____________________________________________________________________________
07 Approved capacity monitoring and observation period
核准產能、監測及觀察期間
____________________________________________________________________________
08 Restrictions open items and rollback criteria
限制、未結事項與回退準則
____________________________________________________________________________
09 Required reviewers and external restrictions
必要審查人與外部限制
____________________________________________________________________________
10 Approver timestamp and subsequent reassessment
核准人、時間及後續重評
____________________________________________________________________________
Status: OPEN / UNDER REVIEW / ACCEPTED / SUPERSEDED
狀態:未結/審查中/已接受/已取代
Appendix F D6 Exercise and Corrective Action Record
附錄 F D6 演練與改善追蹤紀錄
Copy this editable form for each record. Blank fields mean incomplete information, not acceptance. Attach calculations, drawings and tests by evidence ID.
每筆紀錄可複製本可編輯表單。空白代表待填,不代表通過。計算、圖說及試驗依證據編號附掛。
01 Exercise ID scenario assumptions and boundaries
演練編號、情境、假設與邊界
____________________________________________________________________________
02 Participants roles shifts and resources
參與人員、角色、班別與資源
____________________________________________________________________________
03 Timeline and actual versus simulated actions
時間軸及實際與模擬動作
____________________________________________________________________________
04 Decisions notifications and blocked gates
決策、通報與未放行關卡
____________________________________________________________________________
05 Finding delays information and resource gaps
缺失、延遲、資訊與資源缺口
____________________________________________________________________________
06 Cause analysis and linked risk or procedure
原因分析與連結風險或程序
____________________________________________________________________________
07 Interim control corrective action owner and due date
臨時控制、改善、主責與期限
____________________________________________________________________________
08 Verification evidence and repeat exercise or test
驗證證據與重複演練或測試
____________________________________________________________________________
09 Effectiveness and independent closure reviewer
有效性與獨立結案審查人
____________________________________________________________________________
10 Closure date status and remaining restrictions
結案日期、狀態與剩餘限制
____________________________________________________________________________
Status: OPEN / UNDER REVIEW / ACCEPTED / SUPERSEDED
狀態:未結/審查中/已接受/已取代
References and Evidence Use
參考來源與證據使用
Sources accessed on 26 October 2026. These sources establish reference scope; they do not certify this site or prove completion of any inspection or test.
來源查閱日期為 2026 年 10 月 26 日。引用資料用於建立參考範圍,不認證本廠,也不證明任何檢查或試驗已完成。
[1] NFPA — NFPA 318 Standard Development
NFPA 318 標準官方頁面
https://www.nfpa.org/codes-and-standards/nfpa-318-standard-development/318
Supports the semiconductor facility scope; adopted edition and full requirements must be obtained and reviewed.
支持半導體設施範圍;採用版本及完整要求須取得並審查。
[2] SEMI — Standards Safety
SEMI 安全標準官方目錄
https://www.semi.org/en/products-services/standards/safety
Lists SEMI S14 for equipment fire risk assessment and mitigation. No claim of full-clause compliance is made.
列出設備火災風險評估與減災的 SEMI S14;不宣稱符合全部條文。
[3] OSHA — 29 CFR 1910.39 Fire Prevention Plans
美國 OSHA 防火計畫公開要求
https://www.osha.gov/laws-regs/regulations/standardnumber/1910/1910.39
Provides fire prevention plan elements. US jurisdictional applicability must be distinguished from use as a management reference.
提供防火計畫要素;美國法規適用性須與管理參考用途區分。
Before issue for operation, add the site-specific legal register, approved fire designs, adopted standards with edition dates, supplier manuals, material safety data, inspection records and test evidence. Record access restrictions and missing documents as open items.
發布供運轉使用前,補入廠址法規清冊、核准消防設計、採用標準與版本日期、供應商手冊、物料安全資料、檢查及試驗證據。存取限制與缺漏文件列入未結事項。
All priorities, management cadence, approval roles, forms and the ninety-day programme in this report are proposals for site adoption. No invented inspection result, protection capacity, inventory, cost or recovery target is included.
本報告的優先級、管理節奏、核准角色、表單及九十天計畫均為現場採用建議;未虛構檢查結果、防護能力、庫存、成本或復原目標。