產業資訊

Industry Information

Fab Occupational Safety and Health Research Report

Fab Occupational Safety and Health Research Report

Fab 職業安全衛生研究報告

Comprehensive management planning and verification framework

完整管理規劃與驗證架構

26 October 2026

2026 年 10 月 26 日

Executive summary

執行摘要

Fab occupational safety and health requires coordinated control of process hazards, maintenance work, utilities, contractors and worker exposure. The report proposes ten work programs and a management system linking each major risk to its current site condition, named owner, operating restrictions, next evidence deliverable and delivery date. Unknown conditions are managed through explicit survey plans rather than assumed safe.

晶圓廠職業安全衛生須協同控制製程危害、維修作業、公用系統、承攬活動與人員暴露。本報告提出十大工作計畫,並將每項重大風險連結到現場狀態、具名責任、作業限制、下一份驗證證據與交付日期。未知條件以明確盤點計畫管理,不直接視為安全。

The principal management finding is that engineering completion, evidence acceptance and authorization to resume work are separate milestones. Interim controls require their own validity period and field checks. The deliverable includes a phased implementation plan, performance definitions and seven editable forms.

主要管理結論是:工程完成、證據驗收與恢復作業核准是三個不同里程碑。暫時控制須有獨立有效期限與現場查驗。本文件另提供分階段推動計畫、績效定義與七份可編輯表單。

Research approach and evidence boundary

研究方法與證據邊界

This is a literature-informed management synthesis and bilingual adaptation of the preceding Chinese report. It organizes official guidance and the proposed work practices developed in the discussion. No site inspection, exposure sampling, equipment testing or causal field study was conducted for this report. It does not claim measured risk reduction or certify site compliance. References support the stated management principles and hazard background; suggested timelines, forms and examples are proposed practices requiring site validation.

本報告以官方指引為參考,整合前述中文報告及討論中的工作規劃,製作英中雙語管理研究報告。本次未進行廠址查驗、暴露採樣、設備測試或現場因果研究,因此不主張已量測風險降低效果,也不認證廠址合規。引用資料支持管理原則與危害背景;建議時程、表單及案例屬須經廠址驗證的管理方案。

Purpose and use

文件目的與使用方式

This report consolidates the full discussion into a framework covering occupational safety and health in semiconductor fabs, ten work programs, major risk governance, operating restrictions, verification and release, surveys of unknown conditions, management dashboards and editable forms. Repeated material is organized together while retaining the management requirements and implementation details.

本文件整合本次討論全部主題,涵蓋晶圓廠職業安全衛生架構、十大工作計畫、重大風險治理、作業限制、驗證放行、未知範圍盤點、管理層儀表板與可編輯表單。重複內容集中編排,保留原有管理要求與實施細節。

Core requirement: every identified major risk must have a documented site condition, named owner, operating restrictions, next verification deliverable and delivery date. Unknown areas must also have a survey method, owner, deadline and interim controls.

核心要求:每項已辨識重大風險,均須說明現場狀態、具名責任、作業限制、下一份驗證證據與交付日期;尚未掌握的範圍,也須具備盤點方法、責任人、期限與期間控制。

The report is intended for plant management, manufacturing, process engineering, equipment engineering, facilities, EHS, occupational health personnel, procurement and contractor management. It covers cleanrooms, sub-fabs, chemical and gas supply areas, central utilities, laboratories, storage, wastewater and exhaust treatment, equipment moves and construction.

本規劃適用於廠長、製造、製程、設備、廠務、EHS、職業醫護、採購與承攬管理人員。涵蓋無塵室、Sub-fab、化學品與氣體供應區、中央廠務、實驗室、倉儲、廢水及廢氣處理、設備移入與施工。

This is a working document for establishing procedures and verifying site conditions, not proof that a particular facility has achieved compliance or safety approval. Examples, names, equipment identifiers and dates must be confirmed against actual site information. Applicable statutory requirements for inspection, monitoring, training and record retention must be established for the facility’s size, equipment, materials and work conditions.

本文件為制度建置與現場驗證的工作底稿,並非特定廠址已完成合規或安全驗證的證明。所有範例、人名、設備編號與期限均須依廠內實際資料確認。檢查、監測、教育訓練及紀錄保存的法定要求,須依實際規模、設備、物料與工作條件建立適用清單。

Management principles: an open improvement deadline does not authorize unrestricted work; completed construction does not establish control of risk; insufficient information must not be treated as evidence of safety. Management signatures cannot replace engineering tests or competent professional judgment.

管理原則:改善期限未到,不代表期間可以照常作業;工程完成,不代表風險已受控;資訊不足,不得直接判定安全。管理簽核不能取代工程測試與專業判定。

Version V1.0 bilingual edition. Prepared on 26 October 2026. English above Traditional Chinese.

版本 V1.0 雙語版 編製日期 2026 年 10 月 26 日 英文在上 繁體中文在下

Contents guide

內容導覽

Part I Governance and principal hazards: Chapters 1 to 3.

第一篇 治理與主要危害:第 1 至 3 章。

Part II Ten work programs: Chapters 4 to 13.

第二篇 十大工作計畫:第 4 至 13 章。

Part III Major risk governance and evidence management: Chapters 14 to 22.

第三篇 重大風險治理與證據管理:第 14 至 22 章。

Part IV Implementation schedule and performance: Chapters 23 to 24.

第四篇 推動時程與績效:第 23 至 24 章。

Part V Editable forms: Chapter 25.

第五篇 可編輯表單:第 25 章。

Part VI References and limitations: Chapter 26.

第六篇 參考資料與使用限制:第 26 章。

Part I Governance and principal hazards

第一篇 治理與主要危害

Chapter 1 Management objectives and control principles

第 1 章 管理目標與控制原則

Fab safety management must address acute incidents, long-term occupational exposure, and injuries during maintenance or abnormal operations. Cleanroom cleanliness does not establish worker safety. Cleanroom garments do not replace protection against chemical permeation, respiratory hazards or electrical hazards.

Fab 職安管理應同時預防急性事故、長期職業暴露,以及維修與異常處置時的人員傷害。無塵室潔淨度不等於人員安全;無塵服的潔淨功能不能取代化學滲透、呼吸或電氣防護。

Prioritize elimination, substitution and engineering controls, followed by administrative controls and personal protective equipment. Select PPE for the actual hazard, material compatibility and task. More frequent patrols or additional PPE cannot serve as a universal substitute for necessary safety functions.

控制順序以消除危害、替代、工程控制為優先,再安排管理措施與個人防護具。防護具應依實際危害、材質相容性及作業情境選用。不能以增加巡檢或加穿防護具,通用地替代必要安全功能。

The system must cover routine operation, material changes, sampling, maintenance, chamber opening, line breaking, cleaning, troubleshooting, decommissioning and emergency response. Include night shifts, work with limited staffing, contractors and handovers between departments.

制度須涵蓋正常操作、換料、採樣、維修、開腔、拆管、清洗、故障排除、設備除役及緊急處置,並將夜班、少人作業、承攬商與跨部門交接納入。

Occupational hygiene should focus on actual worker exposure, connecting sources, routes, timing, control effectiveness and health follow-up. Incident counts or zero reporting alone are insufficient measures of performance.

職業衛生以人員實際暴露為主軸,連結來源、途徑、時段、控制有效性與健康追蹤。管理績效不能只以事故件數或零通報評價。

Chapter 2 Principal hazards and priority situations

第 2 章 主要危害與優先情境

Hazard

風險領域

Typical situation

典型情境

Management focus

管理重點

Chemical exposure

化學品暴露

Cleaning, etching, solution changes, sampling and waste collection

清洗、蝕刻、換液、採樣及廢液收集

Inventory and SDS, compatibility, closed transfer, ventilation, containment and emergency washing

清冊與 SDS、相容性、密閉輸送、排氣、防洩漏及沖淋

Specialty gases

特殊氣體

Cylinder changes and maintenance of gas cabinets, valve boxes and piping

氣瓶更換、氣櫃、閥箱與管線維修

Detection, isolation and interlocks appropriate to toxicity, flammability, pyrophoricity and corrosivity

依毒性、可燃性、自燃性及腐蝕性設計偵測、隔離與連鎖

Oxygen deficiency

缺氧

Nitrogen leaks, interstitial spaces, tanks and confined spaces

氮氣洩漏、夾層、槽體與局限空間

Risk assessment, ventilation, monitoring, entry controls and rescue

風險評估、通風、監測、進入管制及救援

Fire and explosion

火災爆炸

Solvents, flammable gases, reactive deposits and hot work

溶劑、可燃氣體、反應性沉積物及動火

Reduced inventory, segregation, ignition control and equipment safeguards

降低存量、分隔、點火源控制及設備保護

Electrical and stored energy

電氣與儲能

Power distribution, RF power, capacitors, pneumatic and hydraulic systems

配電、RF 電源、電容、氣壓及液壓

Energy identification, LOTO, release of stored energy and verification of safe conditions

能源辨識、LOTO、釋能與安全狀態驗證

Maintenance residues

維修殘留

Chamber opening and cleaning of pumps or exhaust treatment equipment

開腔、泵浦及排氣處理系統清潔

By-product identification, isolation, decontamination, exposure control and restart review

副產物辨識、隔離、去污、暴露控制及復機審查

Machinery and handling

機械搬運

Robots, automated transport, lifting and equipment positioning

機械手臂、自動搬送、吊掛及設備定位

Guards and interlocks, traffic segregation, pinch and fall prevention, and handling plans

防護連鎖、人車分流、防夾防墜及搬運計畫

Physical hazards

物理危害

Noise, heat, lasers, UV and radiation from specific equipment

噪音、高溫、雷射、紫外線與特定設備輻射

Source shielding, separation, monitoring and task-specific controls

源頭屏蔽、隔離、監測與專屬管制

Ergonomics and health

人因健康

Shift work, night work, repetitive tasks and prolonged standing

輪班、夜班、重複動作與長時間站立

Workstation improvements, fatigue management, health services and psychosocial risk prevention

工位改善、疲勞管理、健康服務及心理社會風險預防

Contractor work

承攬施工

Shutdown maintenance, tool installation, piping modifications and simultaneous work

歲修、設備移入、管線改接與交叉施工

Qualification, hazard communication, coordination, permits and supervision

資格審查、危害告知、協調、許可及監督

 

Priority nonroutine tasks

優先管理的非例行工作

– Chamber opening and line breaking: confirm residual chemicals, by-products, temperature, pressure and energy isolation.

– 開腔與拆管:確認殘留化學品、副產物、溫度、壓力及能源隔離狀態。

– Cylinder and container changes: check materials, connectors, piping and authorization, and perform leak checks under the approved procedure.

– 更換氣瓶與容器:核對物料、接頭、管線及授權,依核准程序完成洩漏確認。

– Pump and exhaust cleaning: do not infer deposit safety solely from raw-material SDS information.

– 泵浦與排氣管清潔:不得僅用原料 SDS 推定沉積物安全性。

– Alarms and troubleshooting: define shutdown, evacuation, notification and re-entry criteria; prohibit unauthorized bypasses.

– 警報與故障處置:明定停機、撤離、通報與重新進入條件,禁止擅自旁路。

– Modifications and restart: complete change assessment, functional verification, document updates and training before release.

– 改造與復機:完成變更評估、功能驗證、文件更新及人員訓練後放行。

Hydrofluoric acid requires dedicated protection and exposure-response procedures linked to occupational medicine, emergency care and receiving hospitals. It can cause deep tissue injury and systemic toxicity; pain intensity alone cannot establish exposure severity. [3]

氫氟酸應建立專門防護與暴露處置程序,並與職業醫療、急救及接收醫院銜接。其可能造成深層組織傷害及全身性毒性,不能只依疼痛程度判斷嚴重性。[3]

Chapter 3 Responsibilities and common release gates

第 3 章 組織責任與共同放行關卡

Role

角色

Main work

主要工作

Decision responsibility

決策責任

Plant manager or responsible executive

廠長或事業負責人

Policy, staffing, budgets and major improvements

政策、人力、預算及重大改善

Stop-work decisions, resources and operational restrictions

停工、資源調度與營運限制

Manufacturing manager

製造主管

Routine operation, handover and abnormal response

日常操作、交接及異常處置

Qualifications and work scheduling in production areas

資格與製造區作業安排

Process engineering manager

製程主管

Review materials, conditions, by-products and changes

物料、條件、副產物與變更審查

Technical approval of new processes and modifications

新製程及變更技術核准

Equipment manager

設備主管

Isolation, maintenance, safeguards and restart

隔離、維修、防護與復機

Equipment safety release

設備安全放行

Facilities manager

廠務主管

Power, gas, exhaust, fire protection and treatment systems

電力、供氣、排氣、消防及處理系統

System switching, isolation and restoration

系統切換、隔離與恢復

EHS

EHS

Legal applicability, methods, reviews and audits

法規辨識、方法、審查與稽核

Professional assessment against safety release criteria

安全條件符合性專業判定

Occupational health personnel

職業醫護

Health services, fitness for work and exposure follow-up

健康服務、工作適性及暴露追蹤

Individual protection and work-adjustment recommendations

個別保護與工作調整建議

Procurement and contracting

採購及發包

Safety requirements in purchases and contracts

採購與合約納入安全要求

Supplier and contractor entry conditions

供應商及承攬進場條件

Contractor site supervisor

承攬現場主管

Personnel, tools, procedures and supervision

人員、工具、程序及現場監督

Start, suspension and correction of contractor work

開始、暫停與改善

Workers

工作者

Pre-task checks, procedural compliance and reporting

作業前確認、依程序執行與通報

Stop and report hazardous conditions

危險時停止並通報

 

Gate 1 Planning approval: hazards, scope, responsible persons and controls are established.

共同關卡一:規劃核准。危害、範圍、負責人及控制措施已確認。

Gate 2 Authorization to start: qualifications, isolation, environment and rescue readiness meet requirements.

共同關卡二:開工放行。人員資格、隔離、環境及救援準備符合要求。

Gate 3 Completion inspection: tools, materials, waste, temporary arrangements and abnormalities are addressed.

共同關卡三:完工查驗。工具、物料、廢棄物、暫時設施與異常已處理。

Gate 4 Restart release: safeguards are restored, interlocks tested and documents handed over.

共同關卡四:復機放行。防護恢復、連鎖測試及文件交接完成。

Do not release work when hazards are unresolved, necessary safety functions have failed, isolation cannot be verified, or site conditions differ from the approved scope.

危害未釐清、安全功能失效、隔離無法驗證,或現場與核准內容不符時,不應放行。

Part II Ten work programs

第二篇 十大工作計畫

Chapter 4 Hazard identification and risk assessment

第 4 章 危害辨識與風險評估

Build an inventory covering routine, nonroutine and emergency situations to support priorities and resource decisions. Department managers own the assessments, with EHS supporting methods and review.

目標是建立正常、非例行與緊急情境的完整清冊,讓改善排序及資源分配有依據。各部門主管負責,EHS 協助方法與查核。

Step

步驟

Work

執行工作

Deliverable

交付成果

1 Define areas

1 劃分區域

Establish boundaries by floor, process, equipment group and utility system

依樓層、製程、設備群與公用系統劃界

Area map and ownership

區域圖與責任區

2 List tasks

2 建立作業清冊

Include operation, changes, sampling, maintenance, chamber opening, line breaking and decommissioning

列操作、換料、採樣、保養、開腔、拆管及除役

Task-to-equipment matrix

作業設備對照表

3 Joint walkthrough

3 共同走查

Operators, maintenance, engineers and EHS identify hazards together

操作、維修、工程及 EHS 現場辨識

Hazard records

危害辨識紀錄

4 Examine abnormalities

4 檢查異常

Assess power, exhaust, cooling, gas and detection failures and operating errors

評估停電、排氣、冷卻、供氣及偵測失效與誤操作

Abnormal scenario list

異常情境清單

5 Assess risk

5 評估風險

Record consequences, likelihood, exposure and reliability of controls

記錄後果、可能性、暴露與控制可靠度

Initial risk assessment

初始風險評估

6 Select improvements

6 決定改善

Apply the hierarchy of controls and allocate resources

按控制層級安排措施與資源

Improvement plan and budget

改善計畫及預算

7 Verify effectiveness

7 驗證效果

Check the site and identify any new hazards introduced

現場確認改善及是否引入新危害

Residual risk and closure evidence

剩餘風險與結案證據

 

Do not limit assessments to raw materials or individual tools. Include deposits, waste liquids and cascading effects involving shared exhaust, gas and electrical systems. The absence of past incidents does not justify classifying a high-consequence scenario as low risk.

評估不可只看原料或單機,應包含沉積物、廢液、共用排氣、供氣與電力的連鎖影響。高後果情境不能因過去未發生就直接判低風險。

Assess before introducing equipment, materials, tasks or major changes; reassess after incidents, control failures or new hazard information. Every major risk requires an owner, controls, deadlines and evidence, not merely a score.

新設備、新物料、新作業與重大變更前實施評估;事故、控制失效或發現新危害後重新檢討。每項重大風險必須有責任人、措施、期限與證據,不能只有風險分數。

Chapter 5 Chemical and specialty gas lifecycle management

第 5 章 化學品與特殊氣體全生命週期管理

Maintain control of identity, hazards, movement and operating conditions from pre-purchase review through disposal. Process engineering, procurement, storage, facilities and EHS share defined tasks.

目標是從採購前到廢棄處理,掌握身分、危害、流向與控制條件。由製程、採購、倉儲、廠務及 EHS 分工執行。

Stage

階段

Detailed work

詳細工作

Release condition

放行條件

Introduction

導入

Confirm name, composition, CAS number, concentration, quantity, SDS and use; establish supplier contact for confidential ingredients

確認名稱、成分、CAS、濃度、用量、SDS與用途;機密成分建立聯繫機制

Information adequate for assessment

資訊足以評估

Process review

製程審查

Assess reactions, by-products, substitutes, maintenance residues and waste

評估反應、副產物、替代物、維修殘留及廢棄物

Technical and safety reviews completed

完成技術與安全審查

Facility review

設施審查

Check materials, exhaust, detection, containment, fire protection and emergency washing

材質、排氣、偵測、洩漏控制、消防與沖淋

Site capability meets requirements

現場能力符合需求

Purchase and receipt

採購收貨

Specify packaging, labels, transport, shelf life and documentation

包裝、標示、運輸、有效期限與文件

Intact containers and correct materials

容器完整、物料相符

Storage

儲存

Segregate by compatibility; secure containers and address impact, leaks and inventory limits

相容性分區、固定、防撞、防洩漏與存量上限

Approved storage conditions

儲位符合核准條件

Delivery and use

配送使用

Define routes, container and connection identification, and changeover checks

路線、容器與接點辨識、換料核對

Authorized personnel and correct connections

人員授權且接點正確

Maintenance and abnormalities

維修異常

Control disassembly, decontamination, residual checks and exposure response

拆卸、去污、殘留確認及暴露處置

Approved procedures followed

依核准程序執行

Disposal and removal

廢棄退場

Classify, label, store temporarily and track handover

分類、標示、暫存、交付與流向

Complete records; no arbitrary mixing of unknown waste liquids

紀錄完整,不任意混合未知廢液

 

For each specialty gas, link the inventory to its cabinet, valve box, piping, consuming tool, detectors, emergency isolation and treatment system. Alarm settings and shutdown logic require an engineering basis; do not copy another site’s values without assessment.

特殊氣體專項清冊須將每種氣體連結到氣櫃、閥箱、管線、使用設備、偵測、緊急切斷與處理系統。警報及切斷邏輯須有工程依據,不直接套用別廠數值。

Required records include approved materials, SDS, compatibility, stock, supply diagrams, changeovers, waste movement and emergency information. Every container and gas connection must be traceable to its material, hazards, owner and procedure.

必備文件包括核准物料表、SDS、相容性表、庫存、供應圖、換料與廢棄物流向,以及應變資料。驗收時,任何容器與供氣接點均應能追溯物料、危害、責任及程序。

Chapter 6 High-risk work permits

第 6 章 高風險作業許可

Permits support pre-start checks, supervision and completion handover. Conduct a joint site review, establish isolation and protection, then authorize work and hold the pre-task briefing.

作業許可用於開工前查驗、作業中監督與完工交接。申請後須共同勘查,完成隔離與防護,再核准開工並做班前說明。

Work type

作業類型

Pre-start checks

開工前檢查

Controls during work

作業中管制

Hot work

動火

Combustibles, adjacent processes, isolation, fire compartments, detection and firefighting provisions

可燃物、鄰近製程、隔離、防火區劃、偵測與消防

Watch, changing conditions and risk-based post-work monitoring

監視、環境確認及依風險安排完工監看

Confined space

局限空間

Identification, isolation, testing, ventilation, communications and rescue

辨識、隔離、檢測、通風、通訊與救援

Entry register, attendant and appropriate continuous monitoring

進出登記、監視及適用持續檢測

Line breaking

管線開放

Identity, contents, pressure, temperature, isolation and residues

身分、內容物、壓力、溫度、隔離與殘留

Exclusion zone, prevention of wrong-line opening and contamination spread

警戒、防錯拆及污染擴散

Work at height

高處

Platforms, openings, fall protection, anchors and rescue

平台、開口、防墜、錨定與救援

Falling-object zones and supervision

落物區及現場監督

Electrical work

電氣

Scope, backfeed, competence, isolation and verification

範圍、回送電、資格、隔離與驗證

Approach boundaries, tools and protection

接近範圍、工具及防護

Lifting and installation

吊掛移入

Weight, center of gravity, route, floor capacity, lifting equipment and direction

重量、重心、路徑、樓板、機具及指揮

Segregation, unified signals and no access beneath suspended loads

隔離、統一指揮,禁止進入吊物下方

Safety system impairment

安全系統暫停

Scope, affected equipment, alternative controls and restoration deadline

範圍、影響、替代措施及恢復期限

Visible impairment status, tracking and necessary operating limits

顯示停用狀態、追蹤及必要營運限制

 

Specify permit scope and validity. Reconfirm conditions at shift changes, scope changes, alarms or environmental changes. At completion, reconcile tools and materials, inspect and hand over restored systems. Signatures alone are insufficient; retain testing, isolation and site-check evidence.

許可須有有效範圍與期限。換班、範圍改變、警報發生或環境變更時重新確認。完工須清點、查驗與恢復交接。驗收不能只看簽名,必須保留檢測、隔離及現場查驗證據。

Chapter 7 Energy isolation and lockout tagout

第 7 章 能源隔離與上鎖掛牌

Prevent unexpected startup, energy release and inadvertent energization by others. Equipment or facilities teams prepare tool-specific procedures, authorized workers apply them, and supervisors perform checks.

目標是防止意外啟動、能源釋放與他人誤送能。設備或廠務建立專屬程序,授權工作者實施,主管抽查。

  1. Map electrical, capacitive, pneumatic, hydraulic, vacuum, gravitational, thermal and chemical supply energy.
  2. 建立能源圖,涵蓋電力、電容、氣壓、液壓、真空、重力、高溫與化學供應。
  3. Identify every isolation point, including primary power, UPS, backup, shared feeds and possible backfeed.
  4. 識別主電源、UPS、備援、共享供應與回送來源等全部隔離點。
  5. Prepare equipment-specific stopping, isolation, locking, dissipation and verification steps.
  6. 編製設備專屬停止、隔離、上鎖、釋能及驗證程序。
  7. Notify affected personnel and assess adjacent equipment and shared systems.
  8. 通知受影響人員,確認相鄰及共用系統影響。
  9. Apply isolation and personal locks; use appropriate group lockout and lock management for multiple workers.
  10. 執行隔離與個人鎖定;多人工作使用適用群組鎖定與鎖具管理。
  11. Control residual capacitor energy, pressure, gravity and heat.
  12. 控制電容、壓力、重力與高溫等殘餘能量。
  13. Verify safe conditions using methods appropriate to the equipment; a stopped indication on a display is not isolation verification.
  14. 依特性驗證安全狀態;畫面顯示停止不等於隔離驗證。
  15. Maintain uninterrupted isolation during maintenance, contractor participation and shift handover, with named acknowledgment.
  16. 維修、外包加入與跨班時維持隔離連續性,具名交接。
  17. Restore energy under the procedure only after personnel clear the area, tools are reconciled, guards restored and notifications completed.
  18. 人員撤離、工具清點、防護復原與通知完成後,依程序復能。

Keep energy maps, isolation-point photographs, equipment procedures, group-lock records, handovers and exceptional lock-removal procedures. Competence assessment must include identification and verification in the field, not only a written test.

必備文件為能源圖、隔離點照片、專屬程序、群組鎖定、交接與異常拆鎖程序。能力確認需包含現場識別與驗證實作,不能只以筆試通過認定。

Chapter 8 Safety-critical equipment and protective functions

第 8 章 安全關鍵設備與保護功能

Assign every critical asset an identifier, owner, test method, acceptance criteria and interval. Determine intervals from risk, applicable law, manufacturer requirements and failure history.

每個關鍵資產須有編號、責任人、方法、允收標準與週期。週期依風險、法規、製造商及失效紀錄訂定。

Function

功能

Management work

管理工作

Evidence

證據

Gas detection

氣體偵測

Target gas, location, range, environmental effects and calibration

適用氣體、位置、範圍、環境影響與校正

Calibration, functional tests and failures

校正、功能及故障紀錄

Oxygen monitoring

氧氣監測

Deficiency scenarios, location, alarms and response

缺氧情境、位置、警報及反應程序

Tests and site checks

測試與現場查驗

Local exhaust

局部排氣

Capture, airflow, duct condition and abnormal alarms

捕集、氣流、管路及異常警報

Measurements and improvements

量測與改善

Emergency isolation

緊急切斷

Integrated response of detection, logic, valves and controlled equipment

偵測、邏輯、閥件與受控設備整體反應

End-to-end tests

端到端測試

Equipment interlocks

設備連鎖

Doors, guards, cooling, exhaust and abnormal shutdown

門蓋、防護、冷卻、排氣與異常停機

Procedures and results

程序與結果

Emergency showers and eyewash

沖淋洗眼

Access, water supply, function and identification

可達性、供水、功能及標示

Inspection and maintenance

檢查與維護

Fire protection and compartments

消防區劃

Equipment, doors, penetration seals and construction damage

設備、門、貫穿封堵及施工損傷

Defects and repairs

缺失與修復

Backup supply

備援供應

Required detection, control and exhaust during power loss

失電時必要偵測、控制與排氣能力

Transfer and failure-scenario verification

切換及失效情境驗證

 

Sensor calibration and complete protective-function testing are not interchangeable. Track bypasses, impairments and faults together, including scope, deadlines and operating limits. Assess testing hazards in advance; do not create dangerous leaks or exposure to prove a function.

感測器校正與整體保護功能測試不能互相替代。旁路、停用與故障要列於同一狀態清單,標示影響、期限與營運限制。測試本身須先評估風險,不能為驗證製造危險洩漏或暴露。

Acceptance must demonstrate the protective chain from detection to final action and establish executable operating restrictions when it fails.

驗收須證明從偵測到最終動作的保護鏈有效;失效時須有可執行限制。

Chapter 9 Management of change and pre-startup review

第 9 章 變更管理與啟用前審查

Include material type, concentration, specification and quantity; temperature, pressure, flow and reactions; materials of construction, seals, valves and piping; exhaust, cooling, power and alarms; PLCs, safety interlocks and remote operation; procedures, staffing, shifts and maintenance; and temporary supplies, hoses, bypasses and emergency repairs.

納入物料種類、濃度、規格及用量;溫度、壓力、流量及反應;材質、密封件、閥件與管線;排氣、冷卻、供電及警報;PLC、安全連鎖與遠端操作;程序、人力、班別及維修;臨時供應、軟管、旁路與緊急修復。

Stage

階段

Work

工作

Completion condition

完成條件

Request

申請

Reason, scope, duration and impact

原因、範圍、期限與影響

Named requester and system owner

申請及系統負責人明確

Assessment

評估

Hazards before and after the change, failures and legal implications

前後危害、失效及法規影響

Controls established

控制措施確定

Design

設計

Drawings, logic and installation requirements

圖面、邏輯與施工要求

Review findings addressed

審查意見處理

Installation and testing

施工測試

Follow the design and record deviations

依設計執行,記錄差異

Acceptance criteria met

結果符合允收標準

Startup review

啟用審查

Safeguards, documents, training, emergency response and open items

防護、文件、訓練、應變及未結事項

Critical safety items closed

關鍵安全項目關閉

Follow-up

追蹤

Observe operation, exposure and alarms

運轉、暴露與警報觀察

No new uncontrolled risk

無新增未受控風險

 

Set expiry dates for temporary changes and restore or reauthorize them at expiry. Elapsed time does not make a temporary arrangement permanent. Align the site, drawings, software, SOPs and training. Assessment and control of changes are also elements of the Taiwan occupational safety and health management system guidance. [1]

臨時變更設定到期日,屆期恢復或重新核准,不因時間變長默認永久化。現場、圖面、程式、SOP 與訓練應一致。變更影響與控制亦為臺灣職業安全衛生管理系統指引要素。[1]

Chapter 10 Contractors and simultaneous work

第 10 章 承攬與交叉施工

Stage

階段

Work

工作

Before contracting

發包前

Describe environment, hazards, isolation, schedule, qualifications and deliverables; budget necessary safety costs

說明環境、危害、隔離、工期、資格與交付;編入必要安全費用

Qualification

資格審查

Review competence, supervisors, training, methods and corrective capability

專業、主管配置、訓練、作業方法及改善能力

Planning

施工規劃

Review method statements, risks, staffing, tools, rescue and simultaneous work

方法書、風險、人力、工具、救援及交叉作業

Entry

入廠

Communicate hazards, orient personnel, explain assembly points and verify qualifications

危害告知、導覽、集合點與資格核對

Daily start

每日開工

Confirm scope, changes, permits, isolation and the responsible person for the day

範圍、變化、許可、隔離及當日責任人

Execution

作業中

Coordinate production, hot work, lifting, openings and piping; maintain safeguards

協調製程、動火、吊掛、開孔及管線;維持防護

Abnormalities

異常

Define stopping, reporting, correction and restart conditions

停工、通報、改善與重新開工條件

Demobilization

退場

Remove waste, restore seals and protection, and submit as-built and test information

廢棄物、封堵、防護恢復及竣工測試資料

Evaluation

評估

Review major findings, recurrence, effective correction and supervisor accountability

重大缺失、重複違規、有效改善及主管履責

 

Create a daily area, time and task coordination matrix. Assess interactions between floors, work on the same piping and shared exhaust. Assign one coordination contact per isolation boundary. Recheck qualifications and hazard communication when personnel or subcontractors change; provide appropriate owner contacts and supervision at night and on holidays.

交叉施工建立每日區域、時段及作業對照表,評估上下層、同管路與共用排氣互相影響。每個隔離邊界指定唯一協調窗口。新增再承攬或更換人員時重核資格與告知;夜班與假日配置相應業主窗口和監督資源。

Acceptance depends on actual personnel, work and equipment matching approved information, not merely on contract clauses.

驗收以現場人員、作業、設備與核准資料相符為準,不能只依合約要求。

Chapter 11 Occupational hygiene and health

第 11 章 職業衛生與健康

Work

工作

Implementation

執行內容

Deliverable

交付

Exposure groups

暴露族群

Group operators, chamber maintenance, pump cleaning, cylinder changes and waste handling

按操作、開腔、泵浦、換氣瓶及廢液工作分類

Similar exposure group inventory

相似暴露族群清冊

Source survey

來源盤點

Raw materials, by-products, deposits, cleaners, dust and physical hazards

原料、副產物、沉積物、清潔劑、粉塵與物理危害

Exposure source map

暴露來源圖

Assessment design

評估設計

Personal or area and short-term or full-shift sampling, including representative and high-exposure conditions

個人或區域、短時或全班,涵蓋代表與高暴露情境

Monitoring plan

監測計畫

Interpretation

結果判讀

Applicable limits, conditions, uncertainty and uncovered tasks

適用限值、條件、不確定性與未涵蓋工作

Assessment report

評估報告

Control improvement

控制改善

Enclosure, exhaust, tools, methods and PPE

密閉、排氣、工具、方法及防護具

Improvement and reassessment

改善與再評估

Respiratory protection

呼吸防護

Selection, appropriate health assessment, fit testing, maintenance and replacement

選型、適用健康評估、密合度、維護與更換

Protection program

防護計畫

Health services

健康服務

Risk- and law-based examinations, follow-up and fitness for work

依風險與法規安排檢查、追蹤與工作適性

Health follow-up

健康追蹤

Ergonomics

人因

Handling, repetition, workstation height, force and standing

搬運、重複、工位高度、施力與站立

Workstation improvements

工位改善

Shift and psychosocial factors

輪班心理

Hours, rest, workload, workplace violence or harassment and help channels

工時、休息、負荷、不法侵害與求助

Fatigue and mental-health measures

疲勞與心理健康措施

 

Normal-operation measurements do not represent chamber opening or cleaning. One nondetect result does not establish safety for every task. Assess inhalation, skin, eye and contamination-transfer routes, as well as changeovers, cleaning and emergency response.

正常運轉結果不能代表開腔或清洗;一次未檢出不能代表所有工作無風險。應分別評估吸入、皮膚、眼睛與污染轉移途徑,以及換料、清潔與事故處置時段。

Authorized health personnel manage individual records; management reporting should normally use de-identified information. Establish prompt symptom and exposure reporting and medical assessment. Each high-exposure group needs an assessment basis, controls and follow-up, with evidence of improvement.

個人健康資料由授權醫護管理,管理報表原則採去識別資訊。症狀與暴露事件建立即時通報及醫療評估管道。高暴露族群須有依據、控制與追蹤,改善後證明效果。

Chapter 12 Emergency response and medical coordination

第 12 章 緊急應變與醫療銜接

Scenario

情境

Preparation

事前準備

Exercise checks

演練查核

Gas alarm

氣體警報

Zoned alarms, evacuation, remote isolation and information

分區警報、撤離、遠端切斷與資訊

Correct evacuation and prevention of entry

正確撤離及防誤入

Chemical splash or exposure

化學潑灑暴露

Decontamination, SDS, medical contacts and trained personnel

除污、SDS、醫療聯繫與受訓人員

Decontamination and medical-transfer information

除污與送醫資訊

Oxygen deficiency or collapse

缺氧或倒臥

No unprotected entry, competent rescue and communications

禁止無防護進入、專業救援與通訊

Prevention of impulsive rescue

避免盲目施救

Fire or smoke

火災煙霧

Evacuation, fire-service notification and safe process conditions

撤離、消防通報與製程安全狀態

Accountability, routes and handover

清點、通道及交接

Exhaust or power loss

排氣電力中斷

Shutdown, backup and evacuation conditions

停機、備援與撤離條件

Shared-system effects

共用系統影響

Earthquake

地震

Shelter, leak checks and damage inspection

避難、洩漏與損傷查驗

Re-entry and restart authority

重入與復機權限

Multiple casualties

多人受傷

Triage, ambulance routes and medical capacity

分流、救護動線與醫療量能

Command and external coordination

指揮及外部協調

 

Each shift must confirm its incident commander and alternate, reporting and evacuation contacts, rescue competence and equipment, external access routes, material location maps, and re-entry and restart conditions.

每班確認指揮官與代理、通報撤離清點窗口、救援資格與裝備、外部進入路線、物料位置圖,以及重新進入與復機條件。

Record actual reporting, evacuation, accountability and handover times in drills; set scenario-based targets rather than arbitrary uniform times. Include night shifts and contractors. An alarm clearing is not authorization to lift restrictions; re-entry requires environmental safety evidence and approval.

演練應記錄通報、撤離、清點與交接實測時間,按情境設定目標,不任意使用統一秒數。夜班與承攬商也須能執行。警報停止不等於可解除管制,重入須有環境安全證據及授權。

Chapter 13 Incident learning audits and continual improvement

第 13 章 事故學習 稽核與持續改善

  1. Prioritize rescue and hazard control, and make required notifications.
  2. 優先救援及控制危害,依適用要求通報。
  3. Preserve the scene, equipment state and information without obstructing rescue.
  4. 不妨礙救援下保留現場、設備狀態與資料。
  5. Collect alarm trends, maintenance records, permits and interviews.
  6. 蒐集警報趨勢、維修、許可及訪談。
  7. Build a timeline distinguishing facts, hypotheses and matters requiring verification.
  8. 建立時間序列,區分事實、推測及待驗證事項。
  9. Examine equipment, procedures, work arrangements, training and management causes.
  10. 分析設備、程序、工作安排、訓練與管理原因。
  11. Assign corrective actions, owners, deadlines and verification methods.
  12. 設矯正措施、責任、期限與驗證方法。
  13. Check similar equipment or other sites.
  14. 檢查其他相似設備或廠區。
  15. Close only after effectiveness verification.
  16. 完成有效性驗證後結案。

Do not stop root-cause analysis at human error. Ask how the error became possible, why safeguards failed and how work conditions contributed. Issuing a memo or holding training does not establish effective closure.

根因不得停在「人員疏失」,應追問錯誤如何發生、保護為何失效及工作條件如何促成。發文或上課不等於有效結案。

Suggested frequency

頻率建議

Work

工作

Output

輸出

Each shift

每班

Handover of alarms, isolation, bypasses, permits and unfinished work

警報、隔離、旁路、許可與未完成工作交接

Shift record

交接表

Daily

每日

Coordinate high-risk work and major findings

高風險協調及重大缺失

Work and restriction list

當日作業與限制

Weekly

每週

Cross-functional checks and overdue review

跨部門查核與逾期檢討

Risk improvement report

風險改善週報

Monthly

每月

Critical equipment, exposure, contractors and health performance

關鍵設備、暴露、承攬與健康績效

Monthly report

月報

Quarterly

每季

Themed audits, trends and exercise scheduling

主題稽核、趨勢與演練安排

Focused improvements

專項改善

Annually

每年

Management review, resources and planning

管理審查、資源與計畫

Next-year targets and budget

次年度目標預算

 

These are management cadences, not replacements for statutory or manufacturer intervals.

以上為管理節奏,不取代法定或製造商要求的週期。

Part III Major risk governance and evidence management

第三篇 重大風險治理與證據管理

Chapter 14 Identifying uncontrolled major risks

第 14 章 未受控重大風險判定

Criterion

判定條件

Example

範例

Management implication

管理意義

Severe consequences with missing controls

嚴重後果且缺少控制

Toxic-gas detection or isolation unavailable

有毒氣體偵測或隔離不可用

Decide immediately on stopping or restricting work

立即決定停止或限制

Critical function failed or bypassed

關鍵功能失效旁路

Inadequate exhaust, bypassed interlock or failed shutoff

排氣不足、連鎖旁路、切斷失效

Do not treat only as a routine work order

不只列一般工單

Safety cannot be demonstrated

安全狀態無法證明

Unknown line contents or unclear isolation points

管線內容不明、隔離點不清

Treat unknowns as matters requiring control

未知列為待控制

Inadequate temporary measures

暫時措施不足

Patrol cannot detect a rapid leak in time

巡檢不能及時發現快速洩漏

Strengthen controls or stop

強化或停止

Effects across systems

跨系統擴散

Shared exhaust affecting multiple tools

共用排氣影響多機

Cross-functional decisions

跨部門決策

Recurring major findings

重複重大缺失

Repeated wrong connections, unisolated work or bypasses

錯接、未隔離、旁路再發

Review systems and resources

檢討制度資源

Completed work without verification

完工無驗證

Detector replaced but isolation not tested

換偵測器但未驗證切斷

No automatic closure

不得直接結案

 

Risk scores support prioritization; low likelihood must not obscure severe consequences and failed safeguards.

風險評分用於排序,不能用低機率淡化嚴重後果及保護失效。

Separate risk status from operating status

風險狀態與作業狀態分開

Risk status

風險狀態

Definition

定義

Uncontrolled

未受控

Necessary controls are absent, failed or inadequately evidenced

必要控制不存在、失效或證據不足

Temporarily controlled

暫時受控

Interim measures verified for a defined scope and period

暫時措施已查驗,在限定範圍期限有效

Awaiting verification

待驗證

Permanent improvement completed but required verification outstanding

永久改善完成,尚未通過必要驗證

Verified as controlled

已驗證受控

Functions meet acceptance criteria

功能符合允收標準

Closed with follow-up

已結案並追蹤

Documents, training, handover and follow-up arrangements established

文件、訓練、交接及再查驗完成安排

 

Operating status

作業狀態

Application

適用方式

Stopped

停止

Relevant work prohibited except approved safe intervention and repair

禁止相關工作,僅准核准安全處置與修復

Restricted

限制

Specified equipment, materials, times, methods or load only

指定設備、材料、時段、方式或負載

Controlled testing

受控測試

Approved isolation, supervision and test plan

依核准隔離、監視及測試計畫進行

Normal

正常

Released, with established controls and monitoring maintained

完成放行,維持既定控制與監測

 

For example: risk awaiting verification; production stopped, with approved testing only. Construction at 100 percent does not establish a controlled risk.

例如「風險待驗證;作業停止生產,僅准核准測試」。施工完成率達 100% 不能直接改為已受控。

Chapter 15 Five required items and the major risk register

第 15 章 五項必填資訊與重大風險總表

Item

管理項目

Required information

必填

Inadequate entry

不合格

Acceptable example

合格範例

Site condition

現場狀態

Location, defect, impact, time and inspector

位置、缺失、影響、時間與查驗人

Detector abnormal

偵測器異常

GC-017 failed its functional test; related gas supply stopped and isolation checked

GC-017 未通過功能測試,相關供氣停止,已查驗隔離

Named responsibility

具名責任

Name, role, alternate and collaborators

姓名、職務、代理與協作

Facilities to handle

廠務處理

Owner [name], alternate [name], controls engineer [name]

主要〔姓名〕、代理〔姓名〕、控制工程〔姓名〕

Operating restrictions

作業限制

Prohibitions, permissions, prerequisites, expiry and stop triggers

禁止、允許、前提、期限與停止條件

Be careful

注意安全

No gas supply; approved repair and testing only

禁止供氣,僅准核准維修及測試

Next evidence

下一份證據

Name, scope, criteria, executor and reviewer

名稱、範圍、標準、執行與審查

Improvement report

改善報告

Detection-to-isolation test with results, abnormalities and retests

偵測至切斷測試,含結果、異常與重測

Delivery date

交付日期

Date and time, dependencies and delay response

年月日時、依賴與延誤處置

As soon as possible

儘速完成

Deliver by the specified time; escalate resource shortages in advance

指定日期時間前交付,提前提出資源不足

 

Timestamp site conditions. Yesterday’s status does not establish the condition after a shift change, maintenance or switching.

現場狀態須有時間戳記。昨日狀態不能直接代表換班、維修或切換後狀態。

The register also needs a risk ID, scenario, consequences, reason controls are inadequate, known evidence, unknowns, engineering executor, verifier and release authority, resources, milestones and next decision date.

總表還需列風險編號、危害情境、可能後果、未受控原因、已知證據、待確認事項、工程執行人、驗證與放行人、資源、里程碑及下次決策日期。

Example description: GC-017 target-gas detection cannot be demonstrated as effective. A leaking connection may not trigger timely alarm and isolation as designed. The scope includes the cabinet and downstream tools. Related supply is stopped pending functional verification and a restoration request.

描述範例:GC-017 目標氣體偵測功能無法證明有效。若供氣接點洩漏,可能無法依設計及時警報及切斷。影響包含氣櫃及下游設備。相關供氣已停止,待功能驗證後申請恢復。

Link the risk card to work orders, drawings, tests and permits. Retain revision history. When dates change, retain the original deadline, reason and approval rather than overwriting them.

管理卡連結工單、圖面、測試及許可,保留修改歷程。變更期限須保留原期限、原因與核准,不直接覆蓋。

Chapter 16 Single ownership and decision authority

第 16 章 單一責任人與決策權限

Assign one primary owner per risk. Collaboration does not justify listing only multiple departments. Name an alternate and record cross-shift handover.

每項風險只設一位主要責任人,多人協作不能以部門共同掛名代替。缺席設代理,跨班具名交接。

Role

角色

Work

工作

Core accountability

核心責任

Plant and operations management

廠長及營運主管

Shutdowns, staffing, budgets and priorities

停機、人力、預算、優先順序

Operating decisions

營運決策

Primary risk owner

風險主要責任人

Integrate plans, dependencies and escalation

整合計畫、依賴及升級

Overall progress

整體進度

Shift supervisor

當班主管

Restrictions, handover and confirmation

現場限制、交接與確認

Actual implementation

限制實際執行

Engineering lead

工程負責人

Design, installation, testing and records

設計、施工、測試與資料

Technical quality

技術品質

EHS and specialist reviewers

EHS及專業審查

Hazards, controls and verification requirements

危害、控制及驗證要求

Professional advice and objections

專業意見與異議

Verifier

驗證人

Check against predefined criteria

依預定標準查驗

Adequacy of evidence

證據足夠性

Release authority

放行主管

Confirm conditions and restoration scope

確認條件及恢復範圍

Authorization to resume

恢復授權

 

Verification of major risks should involve appropriately competent personnel and not rely solely on the installer’s declaration. Management approval cannot replace tests.

重大風險宜由具適當能力且不只依賴施工者自我宣告的人員參與驗證。管理簽核不能替代測試。

Chapter 17 Operating restriction orders and field implementation

第 17 章 作業限制令與現場執行

The order specifies scope, prohibitions, permitted work, prerequisites, site identification, physical or system controls, shift checks, failure triggers, validity and release conditions.

限制令包含生效範圍、禁止事項、允許事項、必要前提、現場標示、實體或系統控制、每班查驗、失效條件、有效期限與解除條件。

Implement in sequence: define tools and shared-system effects; apply isolation, locks, exclusion zones or permissions; notify personnel; inspect the site; obtain receiving-shift confirmation; define stopping conditions for failed controls, environmental changes or unavailable required personnel.

實施順序:界定設備及共用影響;落實隔離、鎖定、警戒或權限;通知相關人員;現場查驗;接班確認;定義控制失效、環境改變及必要人員缺席時的停止條件。

Situation

情境

Restriction approach

限制方向

Insufficient basis alone for resumption

不足以單獨恢復的措施

Gas detection or isolation failed

氣體偵測切斷失效

Stop supply and control isolation and residual hazards under an approved procedure

停供氣,核准程序處理隔離與殘餘危害

More patrols

增加巡視

Exhaust capacity unknown

排氣能力未知

Suspend emission-generating processes and open operations

暫停釋放有害物製程及開放作業

Fan running indication

風機顯示運轉

Isolation points unclear

隔離點不明

No intrusive maintenance until energy boundaries are established

禁侵入維修,先確認能源邊界

Stop button or signs

停止鍵或告示

Unknown deposits

沉積物未知

No arbitrary opening, scraping or mixed cleaning

禁任意開腔、刮除或混洗

Raw-material SDS

原料 SDS

Route or load capacity unknown

路徑承載未知

No equipment movement into the affected area

禁設備搬入相關區域

More signal persons

增加指揮人員

Rescue capability incomplete

救援條件不全

No confined-space entry; assess non-entry methods

禁局限空間進入,評估非進入方法

Detector alone

只有偵測器

 

Field restriction

現場限制

Check

查驗方式

Responsible role

執行責任

No startup

禁止啟動

Equipment state and physical or system controls

狀態與實體或系統控制

Shift equipment supervisor

當班設備主管

No line opening

禁止開管

Permit, isolation and labels

許可、隔離及標示

Work supervisor

作業主管

Testing only

僅准測試

Plan, scope, personnel and protection

計畫、範圍、人員與防護

Test lead

測試負責人

No unauthorized entry

禁未授權進入

Exclusion zones, access and records

警戒、門禁與紀錄

Area supervisor

區域主管

Interim controls maintained

暫時控制維持

Effectiveness and expiry

有效性與到期日

Assigned inspector

指定查驗人

 

Reduced output, added staffing or more PPE require supporting assessment. Expiry does not remove the risk; no automatic resumption without reassessment or release.

減產、增員或增加防護具須有評估支持。限制到期不代表風險消失,未完成重評或放行不得自動恢復。

Chapter 18 Four improvement workstreams and date management

第 18 章 四條改善工作線與日期管理

Workstream

工作線

Work

工作

Completion evidence

完成證據

Immediate control

立即控制

Stop or restrict, establish scope, hand over and notify

停止限制、範圍確認、交接與通報

Restriction order and checks

限制令與查驗

Permanent engineering

永久工程

Cause, design, review, procurement, installation and testing

原因、設計、審查、採購、施工與測試

Design, installation and results

設計施工及結果

Management capability

管理能力

SOPs, maintenance, spares, training and permissions

SOP、維修、備品、訓練及權限

Documents and practical competence

文件與實作確認

Verification and release

驗證放行

Acceptance criteria, checks, closure and restoration

允收標準、查驗、缺失關閉及恢復

Report, release and follow-up

報告放行與追蹤

 

Show dependencies: delivery, installation, calibration, alarm and shutoff tests, abnormal-condition checks, documents and release. Arrange shutdowns, supplier support and measurement resources when opening the case.

計畫標示依賴:交貨、安裝、校正、警報切斷、異常確認、文件及放行。停機、供應商與量測資源應在立案時安排。

Three milestone dates

三個里程碑日期

Engineering completion is the end of installation or repair. Evidence delivery is when acceptable reports and supporting records are ready for review. Operating release is completion of approval and field handover. Failed tests require revised evidence and release dates rather than a misleading on-time status.

工程完成日:安裝修復完成。驗證證據交付日:合格報告及資料可供審查。作業恢復核准日:完成審查及現場交接。測試失敗應更新後兩個日期,不維持假性如期完成。

Two deadline controls

雙期限控制

The evidence deadline governs investigation, engineering and verification. The interim-control expiry governs whether restricted work remains authorized. Delayed parts do not automatically extend interim controls; reassessment and approval are required before expiry.

證據交付期限管理調查、工程與驗證;暫時控制有效期限管理能否維持受限工作。零件延遲不會自動延長暫時控制。到期前須重評並核准。

A forecast-delay report must identify the affected evidence, implications for safety decisions, effectiveness of current restrictions, whether wider stoppage is needed, revised dates and decisions required. Budget or delivery difficulties do not automatically justify continued operation.

預期延誤報告須說明哪份證據延誤、對安全判斷影響、限制是否有效、是否擴大停工、新期限及所需決策。預算與交期困難不構成繼續作業的自動理由。

Chapter 19 Effective evidence and release criteria

第 19 章 有效證據與放行標準

Evidence must identify the tested equipment, version and scope; acceptance basis; executor and reviewer; method, instruments, calibration and conditions; actual results, failures and retests; and the extent and limitations of the conclusion.

證據須回答:測什麼設備版本與範圍;依何允收依據;誰執行審查;方法、儀器、校正與條件;實際結果與失敗重測;能證明的範圍及限制。

Photographs, purchase orders, completion notices and attendance sheets can support the record but cannot alone demonstrate a safety function.

照片、採購單、完工通知與簽到可以輔助,不能單獨證明安全功能。

Current issue

目前問題

Next evidence

下一份證據

Decision supported

支持決策

Unclear impact

影響不清

Trace piping, tools and shared systems

管線設備與共用系統追查

Whether to broaden restrictions

擴大限制與否

Cause unresolved

原因未定

Diagnosis and field tests

診斷及現場測試

Repair approach

修復方案

Design unapproved

設計未准

Design and risk review

設計與風險審查

Procurement or construction

採購施工

Work completed

工程已完

Installation quality inspection

安裝品質查驗

Readiness for controlled testing

可否受控測試

Function unproven

功能待定

Functional and abnormal-scenario verification

功能及異常情境驗證

Whether to restore operation

可否恢復

Exposure effect unknown

暴露效果未知

Representative exposure assessment

代表性暴露評估

Need for further controls

是否再改善

Operation restored

已恢復

Operating observations and reinspection

運轉觀察與再查驗

Sustained effectiveness

是否持續有效

 

Risk

風險

Verification scope

驗證規劃

Common gap

常見缺口

Gas protection

氣體保護

Sensing, alarm, logic, final isolation and abnormal response

感測、警報、邏輯、最終切斷及異常反應

Calibration only

只有校正

Exhaust

排氣

Operating-condition measurements, capture, alarms and interlocks

工況量測、捕集、警報與連鎖

Fan photograph only

只有風機照片

Energy isolation

能源隔離

Inventory, boundaries, field verification and demonstration

清冊、邊界、現場驗證與實作

Generic procedure only

只有通用程序

Chemical exposure

化學暴露

Representative assessment, control effectiveness and repeat measurements

代表性評估、控制效果及再量測

Routine fixed-point data only

只有正常定點結果

Piping changes

管線改接

Drawing-to-site match, materials, connections and applicable tests

圖面現場、材質、接點與適用測試

Completion signature only

只有完工簽名

Fire compartments

防火區劃

Material and system suitability, quality and integrity

材料系統適用、品質與完整性

Surface photograph only

只有表面照片

Heavy handling

重物搬運

Loads, routes, lifting equipment and actual conditions

荷重路徑、機具與現場條件

Experience statement only

只有經驗說明

Confined spaces

局限空間

Isolation, atmosphere testing, ventilation, communications and rescue

隔離、檢測、通風、通訊與救援

Signed permit only

只有許可簽名

 

Seven review gates

七個查核關卡

Complete case: clear scenario, scope, knowns and unknowns. Assigned responsibility: named owner, executor and alternate. Controlled site: restrictions checked and handed over. Executable plan: resources, dependencies and deadlines. Interpretable evidence: results and criteria complete, failures disclosed. Supported release: necessary verification passed and authorization completed. Traceable closure: documents, training and reinspection arranged.

立案完整:情境、範圍、已知未知清楚。責任落實:主要、執行與代理具名。現場受控:限制有查驗交接。計畫可執行:資源、依賴及期限明確。證據可判讀:結果與標準完整,失敗揭露。放行有依據:必要驗證通過及授權完成。結案可追蹤:文件、訓練及再查驗安排。

If evidence is insufficient, record the specific gap and next action. More signatures cannot substitute for missing evidence.

證據不足應寫明缺口與下一步,不能用增加簽核人數替代補證。

Chapter 20 Surveys of unknown conditions and completion criteria

第 20 章 未知範圍盤點與完成標準

For every unknown area, assign a named owner, start and finish dates, survey method, interim controls, resources and immediate escalation for major findings.

每個未知範圍列具名負責人、起訖日、調查方法、期間控制、所需資源及重大缺失即時升級方式。

Scope

範圍

Survey work and method

盤點工作及方法

Completion evidence

完成證據

Equipment and utilities

設備公用系統

Reconcile drawings, site, energy and shared interfaces

圖面、現場、能源及共用接口核對

Equipment and system inventory

設備系統清冊

Chemicals and gases

化學品氣體

Cross-check procurement, storage, processes and site

採購、倉儲、製程與現場交叉查證

Material location register

物料位置表

By-products and residues

副產物殘留

Process and supplier information and necessary specialist analysis

製程、供應商及必要專業分析

Hazard assessment and restrictions

危害與限制評估

Nonroutine work

非例行工作

Interviews, work orders and observations

訪談、工單與作業觀察

Task and risk inventory

作業與風險清冊

Protective functions

保護功能

Assets, logic, bypasses and test reconciliation

資產、邏輯、旁路及測試比對

Functional gap list

功能缺口表

Contractors and subcontractors

承攬再承攬

Contracts, entry lists, qualifications and site checks

合約、入廠、資格與現場核對

Personnel and responsibility matrix

人員責任表

Nights and holidays

夜班假日

Staffing, supervision, rescue, handover and drills

人力、監督、救援、交接與演練

Shift capability gaps

班別能力缺口

Occupational exposure

職業暴露

Groups, timing, observation and monitoring planning

族群、時段、觀察與監測規劃

Follow-up assessment plan

補查計畫

 

Immediately transfer a control gap with potential for severe injury into major risk management; do not wait for the entire survey to finish.

發現可能造成嚴重傷害的控制缺口,立即轉重大風險管理,不等待盤點全案完成。

Use a defined denominator. For example, inventory N tools, n completed surveys, a with complete information, b requiring further checks, and c with major gaps. Information completeness and control-gap risk are different dimensions; define categories to prevent invalid totals.

盤點完成率須有分母。例如清冊 N 台,完成程序 n 台;資訊完整 a 台、待補查 b 台、重大缺口 c 台。資訊完整度與缺口風險屬不同維度,應明確定義分類避免誤加總。

Metric

指標

Definition

定義

Survey coverage

盤點涵蓋率

Items completing the required survey procedure divided by currently identified in-scope items

完成規定盤點程序項目/目前確認應盤點項目

Information completeness

資訊完整率

Items with required information complete divided by currently identified in-scope items

必要資訊齊備項目/目前確認應盤點項目

Major-gap control rate

重大缺口受控率

Major gaps with effective controls divided by identified major gaps

具有效控制重大缺口/已辨識重大缺口

 

Survey completion does not mean corrective work is complete. Update the denominator and explain changes when new equipment, tasks or omissions are found.

盤點完成不等於改善完成。新增設備、作業或遺漏時更新分母並說明。

Chapter 21 Escalation management meetings and dashboards

第 21 章 升級 管理會議與儀表板

The following are suggested internal response times, not statutory notification deadlines. Meet statutory reporting duties separately.

以下為內部建議時效,不是法定通報期限;法定通報另行遵循。

Time or trigger

時點或觸發

Required action

必須完成

Imminent harm

迫切人員危害

Stop, evacuate or isolate immediately and notify

立即停止、撤離或隔離並通報

Same shift

同一班別

Confirm scope, restrictions, owner and handover

確認範圍、限制、責任及交接

Normally within 24 hours

原則 24 小時

Open the case, name the owner and approve interim controls

立案、指定責任、核准暫時控制

Normally within 3 working days

原則 3 工作日

Provide plan, resources, milestones and verification; identify missing information

方案、資源、里程碑與驗證;列待確認資料

Each handover

每次換班

Confirm restrictions, alarms, changes and unfinished work

確認限制、警報、變化及未完成工作

Forecast delay

預期延誤

Present implications and alternatives before the deadline

提前提出影響與備案

Failed control or changed conditions

控制失效或變更

Reassess immediately and stop additional work if needed

即時重評,必要時升級停止

Restriction expiry

限制到期

No automatic extension without renewed approval

未重新核准不得自動延長

Recurrence

同類再發

Escalate across equipment or sites

跨設備或跨廠區專案

 

Weekly management meeting

每週管理會議

For new risks, decide on stoppage and surveys. For uncontrolled risks, assess restrictions. For temporarily controlled risks, review validity and effectiveness. Resolve procurement, shutdown and resource obstacles. Review test readiness, restoration evidence, recurrence and common causes requiring broader action.

新增風險決定停工與盤點;未受控項目確認限制足夠性;暫時受控項目審查期限與有效性;工程進度處理採購、停機及資源;待驗證項目審查測試;申請恢復項目審查證據;重複與共因問題決定擴大。

Record explicit decisions, such as: maintain shutdown; the named manager completes the isolation test by the specified date; controls engineering and EHS review it; no gas restoration before acceptance. Do not record only “continue tracking.”

紀錄應寫具體決策,例如「維持停用;指定主管於日期前完成切斷測試,控制工程與 EHS 審查;未通過不得恢復供氣」,不能只寫持續追蹤。

One-page dashboard

一頁儀表板

Show uncontrolled risks, stopped or restricted operations, expiring controls, actual and forecast delays, evidence due this week, restoration requests and management decisions required.

顯示未受控風險、停止限制範圍、即將到期控制、逾期與預期延誤、本週證據、恢復申請及管理層待決策事項。

Suggested colors: red for uncontrolled risks or failed controls; amber for temporary control with restrictions; blue for completed engineering awaiting verification; green for verified and released work. Always include text status rather than relying on color alone.

顏色建議:紅色為未受控或控制失效;橙色為暫時受控且有限制;藍色為工程完成待驗證;綠色為驗證及放行完成。色彩須搭配文字,不單靠顏色傳遞狀態。

Each row includes the risk or unknown scope, latest site status, named owner, restrictions, next evidence, date and decision request. Prioritize uncontrolled conditions, expiring controls, delayed evidence and unknowns with potentially severe consequences.

每列至少含風險或未知範圍、最新現場狀態、具名責任、限制、下一份證據、日期及決策需求。優先審查未受控、控制到期、證據延誤及可能嚴重傷害的未知範圍。

Chapter 22 Example of an abnormal gas protective function

第 22 章 氣體保護功能異常示範

This is an illustration, not an actual incident record. Replace equipment identifiers, names and dates with verified information.

本案例為示意,非現場事故紀錄;實際設備、人名及日期須替換。

Item

項目

Plan

規劃內容

Risk

風險

GC-017 detection and isolation have not been demonstrated effective

GC-017 偵測及切斷功能尚未證明有效

Consequence

後果

Exposure if a leak is not promptly alarmed and isolated

洩漏未及時警報隔離,造成人員暴露

Unknowns

未知

Whether sensing, control logic and valves are all affected

感測、控制邏輯及閥件是否均有問題

Responsibility

責任

Facilities gas-system manager [name]; shift personnel and authorized maintenance execute

主要為廠務氣體主管〔姓名〕;執行為當班及授權維修人員

Restriction

限制

Stop related supply; control isolation and residual hazards under an approved procedure

停相關供氣,按核准程序控制隔離與殘餘危害

Permitted work

允許

Approved diagnosis, repair and controlled tests

核准診斷、維修與受控測試

Permanent action

永久改善

Determine causes and correct component and management deficiencies

查明原因並修復元件及管理缺口

Engineering milestone

工程里程碑

Repair, installation and quality inspection completed

安裝修復及施工品質確認完成

Evidence milestone

證據里程碑

Calibration, alarms, isolation, abnormal response and retest reports

校正、警報、切斷、異常反應及重測報告

Verification participants

驗證參與

Controls engineering, facilities and appropriate safety specialists

控制工程、廠務與適當安全專業人員

Release

放行

Acceptable tests, updated documents, training, handover and relevant findings closed; authorized manager approves

測試合格、文件訓練交接及相關缺失關閉;授權主管核准

Follow-up

後續

Observation and checks of similar tools based on the failure cause

依失效原因安排觀察及同型設備檢查

 

Repairing the detector does not authorize restoration if the isolation test fails. The next evidence may first be a diagnostic report supporting the repair choice, followed by final functional verification.

偵測器修復但切斷測試未通過,仍不得恢復相關作業。下一份證據可以先是診斷報告,用於決定修復方案,再安排最終功能驗證。

Part IV Implementation schedule and performance

第四篇 推動時程與績效

Chapter 23 Thirty-day ninety-day and engineering improvement plans

第 23 章 三十天 九十天與工程改善計畫

Thirty-day system launch

三十天制度啟動

Timing

時程

Work

工作

Deliverable

交付

Days 1 to 3

第 1 至 3 天

System owner, major-risk definition and stop-work authority

制度負責人、重大風險定義及停工權限

Rules and responsibility matrix

規則責任矩陣

Days 4 to 7

第 4 至 7 天

Consolidate findings, bypasses, incidents and open engineering work

彙整缺失、旁路、事故及未完工程

Initial register

初版清冊

Days 8 to 14

第 8 至 14 天

Inspect the site, issue restrictions and assign named owners

現場查驗、限制令及具名責任

Executable controls

可執行控制

Days 15 to 21

第 15 至 21 天

Plans, standards, dependencies and resources

方案、標準、依賴與資源

Improvement and verification plans

改善驗證計畫

Days 22 to 30

第 22 至 30 天

Management review, handover checks and trial releases

管理審查、交接抽查及試行放行

Dashboard and decisions

儀表板與決策

 

The thirty-day acceptance criterion is an operational system: five required items for every major risk and a plan for unknowns, not completion of all engineering work.

三十天驗收重點是制度可運作:每項重大風險可說明五項必要資訊;未知範圍有盤點計畫,不要求所有工程完成。

Full establishment and first verification cycle

整體建置與首輪驗證

Timing

時程

Work

工作

Completion criteria

完成標準

Days 1 to 7

第 1 至 7 天

Responsibilities, stopping rules and immediate hazards

責任、停工原則與立即危害控制

Organization and urgent action list

組織及緊急改善清單

Days 8 to 30

第 8 至 30 天

Survey areas, materials, equipment, nonroutine work and contractors

區域、物料、設備、非例行與承攬盤點

Baseline risks and priorities

基線風險與優先順序

Days 31 to 60

第 31 至 60 天

Permits, LOTO, materials, MOC, contractors, emergencies and training

許可、LOTO、物料、MOC、承攬、應變與訓練

Approved documents, functional checks and exposure-assessment arrangements

核准文件、功能與暴露評估安排

Days 61 to 90

第 61 至 90 天

Practical checks, protective-function verification, exercises and audits

實作抽查、安全功能驗證、演練及稽核

First review and open-item list

首輪查驗與未結項目

Days 91 to 180

第 91 至 180 天

Procurement, design and engineering requiring outages

採購、設計及需停機的工程改善

Engineering acceptance and residual risks

工程驗收及剩餘風險

 

The ninety-day work can also be scheduled as surveying in the first fifteen days, critical procedures in days sixteen to thirty, inspection and training in days thirty-one to sixty, and exercises and audits in days sixty-one to ninety. Programs run concurrently; do not wait for documents before controlling high risks.

原先九十天工作可細分為前十五天盤點、十六至三十天建立關鍵程序、三十一至六十天查驗與訓練、六十一至九十天演練稽核。各計畫並行,不等待文件完成才控制高風險。

Ninety days is not a commitment to close every engineering issue. Outstanding major improvements require shutdown, restrictions or other verified interim controls.

九十天不是所有工程結案承諾。未完成重大改善須有適當停用、限制作業或其他經驗證暫時控制。

Chapter 24 Performance and resource management

第 24 章 績效與資源管理

Metric

指標

Definition and use

定義與使用

Overdue high-risk findings

高風險逾期數

Show interim controls and expiry for each case, not only counts

逐項列暫時控制及到期,不只看件數

Critical-function test rate

關鍵功能測試率

Tests completed on time and accepted divided by tests due

期限內完成且合格/當期應測

LOTO compliance

LOTO符合率

Checks meeting all critical requirements divided by checks performed; list major failures separately

全部關鍵要求符合抽查件數/抽查件數;重大缺失另列

Permit compliance

許可符合率

Complete permits matching the site divided by checks performed

現場一致且完整/抽查件數

Exposure verification

暴露驗證率

Effectiveness checks completed divided by checks due

有效性確認完成/當期應完成

Change completeness

變更完整率

Changes with required reviews before startup divided by changes started

啟用前完成必要審查/啟用變更

Repeated contractor findings

承攬重複缺失

Track recurrence and examine contracting and supervision causes

追蹤同類再發,檢查發包監督原因

Corrective effectiveness

矯正有效率

Effective rechecks divided by rechecks due

再查驗有效/到期應查驗

Survey and information rates

盤點及資訊率

Track scope coverage and information completeness separately

分別追蹤範圍涵蓋與資訊齊備

 

Do not target fewer near-miss reports. Resource plans should include engineering costs, personnel, outage windows, suppliers, measurement and specialist support, distinguishing immediate controls, permanent improvements and ongoing maintenance.

不以降低未遂通報數作為績效目標。資源表應列工程費、人力、停機窗口、供應商、量測及專業支援,並區分立即控制、永久改善與持續維護費用。

Standard improvement fields: identifier, location, problem and consequence, existing and immediate controls, permanent action, owner and deadline, resources, acceptance method, residual risk, closure evidence and reinspection date.

每項改善統一欄位:編號、位置、問題後果、現有措施、立即措施、永久改善、責任期限、資源、驗收方法、剩餘風險、結案證據與再查驗日期。

Part V Editable forms

第五篇 可編輯表單

Chapter 25 Field and management forms

第 25 章 現場與管理表單

Copy and complete the following forms. Brackets indicate fields to be filled, not completed review or approval. Evidence may use controlled document IDs or internal links. Do not include individual medical information in general management registers.

以下表單供複製使用。中括號均為待填欄位,不代表已完成審查或核准。電子證據可填受控文件編號或內部連結,個人健康資料不得放入一般管理表。

Form 1 Major risk management card

表單一 重大風險管理卡

Field

欄位

Entry

待填內容

ID and creation

編號及建立日期

[FAB-OHS-year-sequence] [date and time]

〔FAB-OHS-年度-流水號〕 〔日期時間〕

Location equipment and scope

位置設備及範圍

[building, floor, area, tool, piping and shared systems]

〔棟樓層區域、設備、管線與共用系統〕

Scenario and consequence

危害情境與後果

[trigger, substance or energy, persons and consequences]

〔觸發、物質或能量、人員及可能後果〕

Known facts and evidence

已知及證據

[observations, measurements, tests and document IDs]

〔觀察、量測、測試、文件編號〕

Unknowns

未知與待確認

[gaps, assumptions and investigation method]

〔缺口、假設、調查方法〕

Risk and operating status

風險及作業狀態

[risk status] [stopped, restricted, testing or normal]

〔狀態〕 〔停止/限制/測試/正常〕

Owner and alternate

主要責任及代理

[name, role and contact] [alternate]

〔姓名職務聯繫〕 〔代理姓名〕

Engineering and verification

工程與查驗人

[executor] [verifier]

〔執行姓名〕 〔驗證姓名〕

Site restrictions

現場限制

[prohibited and allowed work, prerequisites and failure triggers]

〔禁止、允許、必要前提及失效條件〕

Validity and inspection

限制效期及查驗

[expiry] [latest inspector, time and result]

〔到期時間〕 〔最近查驗人時間結果〕

Immediate and permanent action

立即及永久改善

[measures, dependencies, staffing, budget and outage]

〔措施、依賴、人力預算停機〕

Next evidence

下一份證據

[name, scope, method, criteria and reviewer]

〔名稱、範圍、方法、允收與審查人〕

Delivery and decision

交付及決策日期

[evidence date and time] [decision date and person]

〔證據日期時間〕 〔決策日期與人〕

Closure and reinspection

結案及再查驗

[criteria, approval, restrictions and follow-up date]

〔條件、核准、限制、追蹤日期〕

 

Form 2 Operating restriction order

表單二 作業限制令

Field

欄位

Entry

待填內容

Related risk and version

關聯風險及版本

[ID] [version]

〔編號〕 〔版本〕

Scope and effective time

生效範圍與時間

[equipment, piping, area and people] [date and time]

〔設備管線區域及人員〕 〔日期時間〕

Prohibitions

禁止事項

[work not permitted]

〔不可執行工作〕

Permissions and prerequisites

允許事項及前提

[allowed work, permit, isolation, supervision and rescue]

〔准許工作、許可、隔離、監視、救援〕

Physical and system controls

實體及系統控制

[locks, exclusion zones, permissions and labels]

〔鎖定、警戒、權限與標示〕

Notification and field check

通知與現場確認

[units, people, time and results]

〔單位、人員、時間及查驗結果〕

Shift checks and handover

每班查驗與交接

[items, owner, receiving person and time]

〔項目、責任、接班人與時間〕

Stop triggers

停止觸發條件

[control failure, changed conditions or staffing shortage]

〔控制故障、環境改變或人員不足〕

Validity and reassessment

有效期限及重評

[expiry, assessor and approver]

〔到期時間、重評人、核准人〕

Release conditions

解除條件

[required evidence and authorization]

〔必要證據及放行授權〕

 

Form 3 Improvement and evidence tracking

表單三 改善與證據交付追蹤

Workstream

工作線

Owner and deadline

責任與期限

Evidence and status

證據及狀態

Immediate control

立即控制

[name and time]

〔姓名/時間〕

[restriction order and site check]

〔限制令與現場查驗〕

Permanent engineering

永久工程

[name and time]

〔姓名/時間〕

[design, installation and tests]

〔設計、施工及測試〕

Management capability

管理能力

[name and time]

〔姓名/時間〕

[documents, training and demonstration]

〔文件、訓練與實作〕

Verification and release

驗證放行

[name and time]

〔姓名/時間〕

[report, release and follow-up]

〔報告、放行與追蹤〕

 

Engineering completion [date]; evidence delivery [date and time]; restoration approval [date and time]. Original deadline [date]; reason for change [details]; impact and interim controls [details]; approval [name and date].

工程完成日〔日期〕;證據交付日〔日期時間〕;恢復核准日〔日期時間〕。原期限〔日期〕;變更原因〔內容〕;影響與暫時控制〔內容〕;核准〔姓名日期〕。

Form 4 Survey plan for unknown conditions

表單四 未知範圍盤點計畫

Field

欄位

Entry

待填內容

Area and subject

區域與對象

[equipment, task, material or shift]

〔設備、作業、物料或班別〕

Unknowns and consequences

未知事項與可能後果

[gaps and possible injury]

〔缺漏與可能傷害〕

Responsibility and support

負責及協作

[named owner, alternate and collaborators]

〔具名主責、代理、協作〕

Survey method

盤點方法

[record comparison, walkthrough, interview, observation or test]

〔資料比對、走查、訪談、觀察或測試〕

Interim controls

期間控制

[prohibitions, permissions, restrictions and checks]

〔禁止、允許、限制及查驗〕

Resources and dependencies

資源及依賴

[information, tools, specialists and outages]

〔資料、工具、專業、停機〕

Start and completion

開始與完成

[date] [date and time]

〔日期〕 〔日期時間〕

Denominator and progress

分母與進度

[scope N] [completed n] [information-complete a]

〔應盤點N〕 〔完成n〕 〔資訊完整a〕

Findings and transfer

發現與轉案

[gap and major risk ID]

〔缺口及重大風險編號〕

Evidence and review

完成證據及審查

[document, reviewer and date]

〔文件、審查人與日期〕

 

Form 5 Shift restriction check and handover

表單五 每班限制查驗與交接

Check

檢查項目

Result and record

結果與紀錄

Scope matches actual conditions

範圍與現況是否一致

[compliant, noncompliant or not applicable, with reason]

〔符合/不符/不適用及原因〕

Isolation exclusion zones and permissions effective

隔離警戒權限是否有效

[result and evidence]

〔結果及證據〕

Permits and interim controls remain valid

許可與暫時控制是否到期

[expiry and action]

〔期限及處置〕

Alarms environment or staffing changed

警報環境人員有無改變

[change and reassessment]

〔變更與重評〕

Work allowed and prohibited this shift

當班允許及禁止工作

[list]

〔清單〕

Unfinished work and next evidence

未完成工作與下一份證據

[details and date]

〔內容與日期〕

Handover and receiving confirmation

交接及接班確認

[both names, date and time]

〔雙方姓名日期時間〕

 

Form 6 Verification and operating release review

表單六 驗證與恢復作業審查

Review item

審查項目

Result and evidence

結果與證據

Equipment version and scope clear

設備版本及驗證範圍清楚

[acceptable or supplement required]

〔符合/待補〕

Method and criteria have technical basis

方法與允收有技術依據

[document ID]

〔文件編號〕

Instruments and conditions traceable

儀器與測試條件可追溯

[records]

〔資料〕

Results failures and retests complete

實際結果及失敗重測完整

[results]

〔結果〕

Required functions accepted and findings closed

必要功能通過且缺失關閉

[open items and restrictions]

〔未結項及限制〕

Drawings procedures training and handover complete

圖面程序訓練交接完成

[versions and records]

〔版本及紀錄〕

Residual risks and follow-up

剩餘風險與追蹤安排

[scope, conditions and date]

〔範圍、條件與日期〕

Review and release

審查與放行

[verifier] [approver] [time]

〔驗證人〕 〔核准人〕 〔時間〕

Decision

決策

[return, maintain restrictions, controlled test or resume specified work]

〔退回/維持限制/准受控測試/恢復指定作業〕

 

Form 7 Management weekly meeting and one-page report

表單七 管理層週會與一頁報告

Reporting period [start and end]; uncontrolled [count]; temporarily controlled [count]; awaiting verification [count]; unknown scopes [count]; expiring controls [count]; delayed evidence [count].

報告期間〔起訖〕;未受控〔件〕;暫時受控〔件〕;待驗證〔件〕;未知範圍〔項〕;即將到期〔項〕;證據延誤〔項〕。

Use the following record per item. Retain links to full records when consolidating into one page.

每項使用下列紀錄,彙整為一頁時保留完整文件連結。

Field

欄位

Entry

待填內容

Risk or unknown scope

風險或未知範圍

[ID and description]

〔編號及描述〕

Latest site condition

最新現場狀態

[status and inspection time]

〔狀態、查驗時間〕

Owner and restrictions

主要責任與作業限制

[name] [prohibited and permitted work]

〔姓名〕 〔禁止及允許〕

Next evidence and delivery

下一份證據及交付

[name and decision supported] [date and time]

〔名稱與支持決策〕 〔日期時間〕

Management decision needed

需要管理決策

[outage, budget, people, scope or escalation]

〔停機、預算、人力、範圍或升級〕

Decision made

本次決議

[specific decision and conditions]

〔具體決定及有效條件〕

Executor and next review

執行與下一次審查

[name] [date and time]

〔姓名〕 〔日期時間〕

 

Part VI References and limitations

第六篇 參考資料與使用限制

Chapter 26 Sources and document maintenance

第 26 章 來源與文件維護

This report consolidates the management planning developed in the discussion. Technical measures, frequencies, response times, statuses and forms are primarily proposed practices, not regulatory approval of a particular site. Sources support management principles and hazard background; they do not validate every example deadline or equipment design.

本文件由本次對話全部管理規劃整合而成。技術措施、頻率、時效、狀態與表單主要為建議制度;不是主管機關對個別廠址的核准。來源供核對管理原則與危害背景,不能視為支持每個示例時程或特定設備設計。

[1] Occupational Safety and Health Administration, Taiwan Occupational Safety and Health Management System Guidelines. Supports the framework for risk control, change and contractor management.

[1] 勞動部職業安全衛生署,臺灣職業安全衛生管理系統指引。支援風險控制、變更及承攬管理架構。

https://www.osha.gov.tw/media/g3jh2qjw/臺灣職業安全衛生管理系統指引.pdf

[2] Occupational Safety and Health Administration, Risk Assessment Guidelines. Supports pre-task identification and assessment methods.

[2] 勞動部職業安全衛生署,風險評估指引。用於建立事前辨識與評估工作方法。

https://www.osha.gov.tw/48110/48713/48735/212505/

[3] Occupational Safety and Health Administration, Reference Guidelines for Recognition of Occupational Hydrofluoric Acid Poisoning. Hazard background only; site first aid should follow approved procedures and professional medical arrangements.

[3] 勞動部職業安全衛生署,職業性氫氟酸中毒認定參考指引。用於氫氟酸危害背景;現場急救應依經核准程序與醫療專業安排。

https://www.osha.gov.tw/media/gapj50wn/5職業性氫氟酸中毒認定參考指引.pdf?mediaDL=true

[4] Laws and Regulations Database, Occupational Safety and Health Act. Use to determine legal applicability and check current provisions and effective dates.

[4] 全國法規資料庫,職業安全衛生法。用於建立法規適用清單,應核對現行條文與施行日期。

https://law.moj.gov.tw/LawClass/LawAll.aspx?pcode=N0060001

[5] Laws and Regulations Database, Occupational Safety and Health Management Regulations. Use to check applicability of management requirements.

[5] 全國法規資料庫,職業安全衛生管理辦法。用於管理制度適用性查核。

https://law.moj.gov.tw/LawClass/LawAll.aspx?pcode=N0060027

The source-review baseline for the discussion is 26 October 2026. Before adoption, revise against current law, manufacturer requirements, process information, site conditions and competent professional judgment. This general report does not prescribe universal exposure limits, detection settings, test methods, health examinations or retention periods.

本次對話來源查閱基準為 2026 年 10 月 26 日。正式採用前,應依現行法規、設備製造商、製程資訊、廠址條件及專業判定修訂。安全限值、偵測設定、測試方法、健康檢查與紀錄保存期限不在本通用文件中一律指定。

Document owner [name and role]; approver [name and role]; effective date [date]; next review [date]. Review earlier after major changes, incidents, protective-function failures or changes in legal applicability, retaining versions and reasons for revision.

文件維護責任人〔姓名職務〕;核准人〔姓名職務〕;生效日〔日期〕;下次檢討〔日期〕。重大變更、事故、保護功能失效或法規適用變化時,應提前檢討,保留版本與修訂原因。

返回頂端