AIDC Occupational Safety and Health Management
AI 資料中心職業安全衛生管理技術研究報告
Bilingual Technical Research Handbook | 3 November 2026 | Revision 1.0
|2026 年 11 月 3 日|版本 1.0
Purpose: a project-adaptable management framework, not a substitute for licensed engineering, authority approval or legal review.
目的:提供專案可調整的管理架構,不取代專業技師設計、主管機關核准或法律審查。
Executive Summary / 執行摘要
AIDC occupational safety must be designed across the entire asset lifecycle. The most consequential interfaces are high-energy electrical systems, batteries, dense racks, liquid cooling, fire response and simultaneous construction and operation.
AIDC 職安衛須涵蓋資產全生命週期;最關鍵的介面為高能量電力、電池、高密度機櫃、液冷、消防應變及施工營運並行。
Taiwan amended its Occupational Safety and Health Act in December 2025, with relevant amendments effective July 2026. Confirm deferred provisions and project applicability. NFPA 855 (2026) and NFPA 70E (2027) are technical references, not automatic Taiwan statutory mandates.
台灣於 2025 年 12 月修正職安法,相關修正於 2026 年 7 月施行;須確認緩衝施行條款及專案適用性。NFPA 855(2026)及 NFPA 70E(2027)為技術參考,不當然構成台灣法定義務。
Twenty Technical Chapters / 二十章技術正文
Chapter 1. AIDC OSH Fundamentals / 第 1 章 AIDC 職安衛概論
Technical scope / 技術範圍
Define the facility boundary, stakeholders, lifecycle and safety case. Include grid intake, substations, UPS, batteries, cooling, white space, loading dock and remote operations.
定義場域邊界、利害關係人、全生命週期及安全論證;納入受電、變電、UPS、電池、冷卻、白區、卸貨碼頭及遠端維運。
Required engineering and management controls / 工程與管理控制
Create an asset-zone register and assign accountable owners for each hazardous energy source.
建立資產分區清冊,並為每一危害能源指定負責人。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Approved OSH scope and asset-zone map.
最低交付成果:核准的職安衛範圍與設備分區圖。
Chapter 2. Taiwan Legal Compliance / 第 2 章 台灣法規遵循
Technical scope / 技術範圍
Apply the Occupational Safety and Health Act, OSH Management Regulations, OSH Facilities Rules, construction safety requirements, fire and building laws, electrical requirements and applicable environmental rules. Verify the effective date of each provision.
適用職業安全衛生法、管理辦法、設施規則、營造安全規定、消防建築法令、電氣及環境法規,逐條核對生效日。
Required engineering and management controls / 工程與管理控制
Determine legal entity, industry category, workforce size, contractor arrangements and authority having jurisdiction before assigning statutory staffing or inspection duties.
先確認法人、事業分類、員工人數、承攬關係及主管機關,再判定法定人員與檢查義務。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Clause-by-clause legal register with owner and evidence.
最低交付成果:逐條法規登錄表、權責與證據。
Chapter 3. ISO 45001 Management System / 第 3 章 ISO 45001 管理系統
Technical scope / 技術範圍
Establish context, worker participation, leadership, planning, support, operational control, performance evaluation and continual improvement.
建立組織處境、工作者參與、領導、規劃、支援、運作控制、績效評估及持續改善。
Required engineering and management controls / 工程與管理控制
Integrate management of change, procurement and contractor controls into design reviews and maintenance tickets.
將變更管理、採購及承攬管制整合至設計審查與維護工單。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: OSH policy, responsibility matrix and annual plan.
最低交付成果:職安政策、責任矩陣及年度計畫。
Chapter 4. Hazard Identification and Risk Assessment / 第 4 章 危害辨識與風險評估
Technical scope / 技術範圍
Use HAZID at concept, HIRA at facility level, JSA for tasks, and specialized arc-flash, fire, structural and battery studies. Assess normal, abnormal and emergency modes.
概念階段採 HAZID、設施採 HIRA、作業採 JSA,另執行電弧、消防、結構及電池專項分析,涵蓋正常、異常及緊急狀態。
Required engineering and management controls / 工程與管理控制
Score likelihood and severity before and after controls; prioritize elimination, substitution and engineered safeguards above PPE.
依控制前後之可能性與嚴重度評分,優先採消除、替代及工程防護,再考量個人防護具。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Risk register and residual-risk approval.
最低交付成果:風險登錄表及殘餘風險核准。
Chapter 5. Civil and Structural Works / 第 5 章 土建與鋼構工程安全
Technical scope / 技術範圍
Check floor loading, concentrated loads, vibration, anchorage, seismic restraints, lifting paths, temporary works, penetrations and fire stopping.
檢查樓板與集中荷重、振動、錨定、耐震固定、搬運動線、臨時支撐、穿孔及防火填塞。
Required engineering and management controls / 工程與管理控制
Require engineer-reviewed load paths and temporary stability plans before modifying existing steel or concrete.
修改既有鋼構或混凝土前,須由合格專業人員審核受力路徑及施工期間穩定計畫。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Structural review and lifting-route signoff.
最低交付成果:結構審查及搬運路徑簽核。
Chapter 6. High- and Low-Voltage Electrical Safety / 第 6 章 高低壓電氣安全
Technical scope / 技術範圍
Study short-circuit duty, protection coordination, shock boundaries, arc-flash incident energy, grounding, switching and alternate feeds.
分析短路容量、保護協調、觸電界限、電弧能量、接地、切換及替代電源。
Required engineering and management controls / 工程與管理控制
De-energize whenever practicable; isolate every source, verify absence of voltage with suitable instruments and control stored energy.
可行時一律先斷電;隔離所有電源、使用適當儀器驗證無電,並控制儲存能量。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Single-line diagram, switching plan and LOTO schedule.
最低交付成果:單線圖、切換計畫與上鎖掛牌清單。
Chapter 7. UPS and BESS Safety / 第 7 章 UPS 與 BESS 安全
Technical scope / 技術範圍
Assess DC shock, fault current, electrolyte, thermal runaway, propagation, ventilation, off-gas, suppression and emergency responder access. Chemistry and enclosure design matter.
評估直流觸電、故障電流、電解液、熱失控、延燒、通風、逸散氣體、抑制系統及救災動線;須依電池化學體系及箱體設計判斷。
Required engineering and management controls / 工程與管理控制
Review manufacturer test evidence, BMS limits, emergency shutdown, fire zoning, separation and incident isolation with fire specialists.
與消防專業人員審查原廠試驗證據、BMS 限制、緊急停機、防火分區、間距及事故隔離。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: BESS hazard study and emergency response card.
最低交付成果:BESS 危害分析及緊急應變卡。
Chapter 8. GPU Servers and Rack Safety / 第 8 章 GPU 伺服器與機櫃安全
Technical scope / 技術範圍
Assess rack mass, center of gravity, tipping, anti-seismic restraints, hot surfaces, service clearances, sharp edges and handling ergonomics.
評估機櫃重量、重心、傾倒、耐震固定、高溫表面、維修淨空、銳邊與搬運人因。
Required engineering and management controls / 工程與管理控制
Use rated handling aids and approved rack loading sequence; never infer floor adequacy from room area alone.
使用額定搬運工具及核准的上架順序,不得僅以機房面積推定樓板承載能力。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Rack installation method statement and inspection.
最低交付成果:機櫃安裝施工計畫與檢查。
Chapter 9. Liquid Cooling and Water Systems / 第 9 章 液冷與冷卻水系統安全
Technical scope / 技術範圍
Analyze CDU pressure, leaks, hose disconnection, water quality, chemical additives, condensation, burns, slip hazards and electrical segregation.
分析 CDU 壓力、漏液、軟管脫落、水質、添加劑、結露、燙傷、滑倒及與電氣設備分隔。
Required engineering and management controls / 工程與管理控制
Install leak detection, isolation valves, drainage and safe pressure-relief routes; validate coolant SDS and response procedures.
設置漏液偵測、隔離閥、排水及安全洩壓路徑,確認冷卻液安全資料表與處置程序。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Cooling P&ID, leak test and spill response plan.
最低交付成果:冷卻 P&ID、漏液試驗及洩漏應變計畫。
Chapter 10. Fire Protection and Evacuation / 第 10 章 消防、防爆與避難
Technical scope / 技術範圍
Integrate detection, alarm, suppression, compartmentation, smoke management, egress and fire-service interface; assess oxygen-displacement and re-entry hazards.
整合偵測、警報、滅火、防火區劃、排煙、逃生與消防介面;評估缺氧及復入風險。
Required engineering and management controls / 工程與管理控制
Test interlocks without exposing workers to accidental discharge or unsafe shutdown; obtain required fire authority approvals.
測試連動時避免人員暴露於誤噴放或不安全停機,並取得必要消防審查核准。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Fire cause-and-effect matrix and drill report.
最低交付成果:消防因果矩陣與演練報告。
Chapter 11. Contractor and Construction Safety / 第 11 章 承攬商與施工安全
Technical scope / 技術範圍
Prequalify contractors, disclose hazards, coordinate simultaneous operations, control excavations, scaffolds, hot work, lifting and confined spaces.
審查承攬商資格、危害告知、共同作業協調,管制開挖、施工架、動火、吊裝及局限空間。
Required engineering and management controls / 工程與管理控制
Hold daily coordination meetings and stop work for uncontrolled interface hazards.
每日召開作業協調會議,對未受控制的交界危害立即停工。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Contractor EHS plan and coordination minutes.
最低交付成果:承攬商 EHS 計畫及協議紀錄。
Chapter 12. Permit to Work and LOTO / 第 12 章 工作許可與上鎖掛牌
Technical scope / 技術範圍
Use permits for energized work, hot work, height, lifting, confined space and line breaking. Identify owner, scope, hazards, isolations, test and restoration.
針對帶電、動火、高處、吊裝、局限空間及拆管作業設工作許可,記載權責、範圍、危害、隔離、測試與復原。
Required engineering and management controls / 工程與管理控制
Apply personal locks, independent verification where needed, shift handover and controlled release of equipment.
落實個人鎖具、必要時獨立複核、跨班交接及受控復電。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: PTW, LOTO certificate and restoration record.
最低交付成果:工作許可、LOTO 證明及復原紀錄。
Chapter 13. Maintenance and Management of Change / 第 13 章 設備維護與變更管理
Technical scope / 技術範圍
Risk-review firmware, power topology, battery configuration, rack density, cooling flow, protection settings and temporary bypasses before implementation.
實施前審查韌體、供電拓樸、電池配置、機櫃密度、冷卻流量、保護設定及臨時旁通。
Required engineering and management controls / 工程與管理控制
Require change classification, rollback, testing, documentation and authorization; prohibit undocumented bypasses.
要求變更分級、回復方案、測試、文件更新及核准,禁止未記錄的旁通。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: MOC register and commissioning checklist.
最低交付成果:變更登錄與試運轉檢查表。
Chapter 14. Occupational Health and Human Factors / 第 14 章 職業健康與人因工程
Technical scope / 技術範圍
Address shift fatigue, lone work, heat stress, noise, manual handling, psychosocial hazards, workplace violence and appropriate health surveillance.
處理輪班疲勞、單人作業、熱危害、噪音、人工搬運、心理社會危害、職場不法侵害及適當健康監測。
Required engineering and management controls / 工程與管理控制
Design work-rest cycles, ergonomic access, buddy rules for critical tasks and confidential reporting.
規劃工作休息週期、人因維修空間、關鍵作業雙人制度及保密通報。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Health risk plan and fatigue controls.
最低交付成果:健康風險計畫與疲勞管制。
Chapter 15. Emergency Preparedness and Investigation / 第 15 章 緊急應變與事故調查
Technical scope / 技術範圍
Plan for electric shock, arc flash, battery off-gassing, thermal runaway, coolant release, fire, flooding, earthquake and loss of cooling.
規劃觸電、電弧、電池逸氣、熱失控、冷卻液外洩、火災、淹水、地震及冷卻喪失之應變。
Required engineering and management controls / 工程與管理控制
Define alarm thresholds, evacuation, incident command, utility isolation, external responders and evidence preservation.
明訂警報門檻、疏散、事故指揮、公用系統隔離、外部救援與證據保存。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: ERP, drill scenarios and corrective-action log.
最低交付成果:應變計畫、演練情境及改善追蹤。
Chapter 16. Smart OSH Monitoring / 第 16 章 智慧職安衛監測
Technical scope / 技術範圍
Connect BMS, EPMS, DCIM, fire alarm and leak sensors using secure read-only safety dashboards; separate operational alarms from life-safety controls.
整合 BMS、EPMS、DCIM、消防及漏液感測,以安全唯讀儀表板監控,區分營運告警與生命安全控制。
Required engineering and management controls / 工程與管理控制
Validate sensor calibration, alarm routing, fail-safe behavior, cybersecurity and manual fallback.
驗證感測校正、告警派送、失效安全、資安及人工備援。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Alarm matrix and response-time log.
最低交付成果:告警矩陣與應變時間紀錄。
Chapter 17. OSH KPIs and Audit / 第 17 章 職安衛績效與稽核
Technical scope / 技術範圍
Track leading indicators: overdue critical actions, permit compliance, LOTO verification, training, inspection and near misses; lagging indicators require consistent definitions.
追蹤重大改善逾期、工作許可符合率、LOTO 複核、訓練、檢查及虛驚事件等先行指標;落後指標須有一致定義。
Required engineering and management controls / 工程與管理控制
Use monthly reviews, independent audits and evidence-based closeout, not injury counts alone.
每月檢討、獨立稽核及以證據結案,不可只看傷害件數。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: KPI dashboard and audit corrective-action plan.
最低交付成果:KPI 儀表板與稽核改善計畫。
Chapter 18. Safety Design and Acceptance / 第 18 章 安全設計與驗收
Technical scope / 技術範圍
Conduct design safety reviews at concept, 30/60/90 percent design, pre-energization, integrated systems testing and operational handover.
於概念、30/60/90% 設計、送電前、系統整合測試及營運移交時進行安全審查。
Required engineering and management controls / 工程與管理控制
Hold points: structural approval, protection study, fire approval, BESS study, pressure testing, evacuation routes, training and as-built documentation.
停留點包括結構核准、保護研究、消防核准、BESS 分析、壓測、逃生路徑、訓練及竣工圖。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Safety acceptance dossier and punch list.
最低交付成果:安全驗收卷宗與缺失清單。
Chapter 19. Accident Scenarios and Lessons / 第 19 章 事故情境與案例分析
Technical scope / 技術範圍
Use scenario exercises: energized panel intervention, UPS backfeed, BESS smoke, coolant leak near busway, rack overturning and failed cooling during maintenance.
採情境演練:帶電盤體介入、UPS 逆送電、BESS 冒煙、匯流排附近漏液、機櫃傾倒及維修期間冷卻故障。
Required engineering and management controls / 工程與管理控制
For each scenario document initiating event, failed barriers, detection, immediate actions, recovery and lessons learned.
各情境記錄起始事件、失效防線、偵測、立即處置、復原及經驗回饋。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Bow-tie scenario sheets and action tracker.
最低交付成果:蝴蝶結風險情境表與行動追蹤。
Chapter 20. Forms and Implementation Roadmap / 第 20 章 管理表單與實施計畫
Technical scope / 技術範圍
Deploy controlled forms, training, pilot audits, corrective action and executive review in a phased rollout.
分階段導入受控表單、訓練、試行稽核、改善措施及高階管理審查。
Required engineering and management controls / 工程與管理控制
Assign document owner, revision, retention period and electronic evidence link for every record.
每項紀錄指定文件負責人、版次、保存年限及電子證據連結。
Implementation and verification / 執行與驗證
Responsible parties shall define an accountable owner, review the latest drawings and equipment manuals, document pre-task hazards, verify controls in the field, retain signed records and stop work when critical safeguards fail.
責任單位應指定負責人、審查最新版圖說與設備手冊、記錄作業前危害、現場驗證控制措施、保存簽核紀錄,重大防護失效時立即停止作業。
Minimum deliverable: Controlled OSH handbook and implementation schedule.
最低交付成果:受控職安衛手冊及實施時程。
Legal and Standards Applicability / 法規與標準適用矩陣
| Source / 依據 | Application / 適用內容 | Classification / 性質 |
| Taiwan OSH Act / 職安法 | Employer duties, design, contractors / 雇主、設計、承攬 | Law / 法律 |
| OSH Management Regulations / 管理辦法 | Risk assessment, staffing, plans / 風險評估、人員、計畫 | Regulation / 法規 |
| OSH Facilities Rules / 設施規則 | Electrical, machinery, worksite / 電氣機械現場 | Regulation / 法規 |
| Construction safety and engineering rules / 營造及工程安全法規 | Construction interface / 工程交界 | Verify applicability / 核對適用 |
| ISO 45001 | Management system / 管理系統 | Voluntary unless required / 視契約 |
| NFPA 70E (2027) | Electrical safe work / 電氣安全作業 | Technical reference / 技術參考 |
| NFPA 855 (2026) | Stationary ESS / 固定式儲能 | Technical reference / 技術參考 |
| IEC 62485 / ISO 31000 | Battery safety / risk process / 電池與風險 | Technical reference / 技術參考 |
Project Implementation Roadmap / 專案實施路線圖
| Phase / 階段 | Activities / 活動 | Gate / 管制點 |
| 0–30 days / 0–30天 | Asset/legal register, baseline HAZID / 資產法規與初始危害辨識 | Management approval / 管理核准 |
| 31–60 days / 31–60天 | Engineering studies, PTW/LOTO, contractor onboarding / 專項分析與承攬導入 | Critical risk controls / 重大風險控制 |
| 61–90 days / 61–90天 | Emergency drills, inspections, audit / 演練檢查稽核 | Evidence closeout / 證據結案 |
| Before energization / 送電前 | Electrical/fire/structural acceptance / 電氣消防結構驗收 | Written release / 書面放行 |
| Operations / 營運 | Monthly KPI, MOC, annual review / 月度指標與變更及年度審查 | Continual improvement / 持續改善 |
Editable Management Forms / 可編輯管理表單
Blank cells are intentionally unapproved templates. Adapt to site, law and equipment before use.
空白欄位僅為未核准範本;使用前須依場址、法規與設備調整。
F01 Hazard Register / 危害登錄表
| Field / 欄位 | Entry / 填寫 |
| ID / 編號 | [To complete / 待填] |
| Area / 區域 | [To complete / 待填] |
| Task / 作業 | [To complete / 待填] |
| Hazard / 危害 | [To complete / 待填] |
| Existing controls / 現有控制 | [To complete / 待填] |
| L / 可能性 | [To complete / 待填] |
| S / 嚴重度 | [To complete / 待填] |
| Residual risk / 殘餘風險 | [To complete / 待填] |
| Owner / 負責人 | [To complete / 待填] |
| Due / 期限 | [To complete / 待填] |
F02 Job Safety Analysis / 工作安全分析
| Field / 欄位 | Entry / 填寫 |
| Task step / 步驟 | [To complete / 待填] |
| Hazard / 危害 | [To complete / 待填] |
| Control / 控制 | [To complete / 待填] |
| PPE / 防護具 | [To complete / 待填] |
| Supervisor / 主管 | [To complete / 待填] |
| Worker briefing / 告知 | [To complete / 待填] |
F03 Permit to Work / 工作許可
| Field / 欄位 | Entry / 填寫 |
| Permit ID / 許可編號 | [To complete / 待填] |
| Location / 地點 | [To complete / 待填] |
| Scope / 範圍 | [To complete / 待填] |
| Validity / 有效期間 | [To complete / 待填] |
| Isolation / 隔離 | [To complete / 待填] |
| Gas/fire watch / 偵測監火 | [To complete / 待填] |
| Approvals / 核准 | [To complete / 待填] |
| Closeout / 結案 | [To complete / 待填] |
F04 LOTO Verification / 上鎖掛牌驗證
| Field / 欄位 | Entry / 填寫 |
| Equipment / 設備 | [To complete / 待填] |
| Energy sources / 能源 | [To complete / 待填] |
| Isolation point / 隔離點 | [To complete / 待填] |
| Lock owner / 鎖具人 | [To complete / 待填] |
| Zero energy test / 零能驗證 | [To complete / 待填] |
| Release approval / 解除核准 | [To complete / 待填] |
F05 BESS Inspection / 儲能檢查
| Field / 欄位 | Entry / 填寫 |
| Chemistry / 化學體系 | [To complete / 待填] |
| BMS alarms / 警報 | [To complete / 待填] |
| Thermal monitoring / 溫度 | [To complete / 待填] |
| Ventilation / 通風 | [To complete / 待填] |
| Fire interface / 消防 | [To complete / 待填] |
| Defects / 缺失 | [To complete / 待填] |
| Action / 改善 | [To complete / 待填] |
F06 Cooling Leak Response / 液冷洩漏處置
| Field / 欄位 | Entry / 填寫 |
| CDU/loop / 系統 | [To complete / 待填] |
| Fluid/SDS / 液體資料 | [To complete / 待填] |
| Detection / 偵測 | [To complete / 待填] |
| Electrical isolation / 電力隔離 | [To complete / 待填] |
| Containment / 圍堵 | [To complete / 待填] |
| Disposal / 清除 | [To complete / 待填] |
| Restart authorization / 復機核准 | [To complete / 待填] |
F07 Contractor Coordination / 承攬協調
| Field / 欄位 | Entry / 填寫 |
| Company / 公司 | [To complete / 待填] |
| Crew / 人員 | [To complete / 待填] |
| SIMOPS / 共同作業 | [To complete / 待填] |
| Hazard notice / 危害告知 | [To complete / 待填] |
| Permit / 許可 | [To complete / 待填] |
| Inspection / 巡檢 | [To complete / 待填] |
| Signature / 簽名 | [To complete / 待填] |
F08 Incident and Near Miss / 事故虛驚
| Field / 欄位 | Entry / 填寫 |
| Time / 時間 | [To complete / 待填] |
| Location / 地點 | [To complete / 待填] |
| Event / 事件 | [To complete / 待填] |
| Immediate action / 立即處置 | [To complete / 待填] |
| Root causes / 根因 | [To complete / 待填] |
| Corrective action / 改善 | [To complete / 待填] |
| Verification / 驗證 | [To complete / 待填] |
F09 MOC Review / 變更審查
| Field / 欄位 | Entry / 填寫 |
| Change / 變更 | [To complete / 待填] |
| Reason / 原因 | [To complete / 待填] |
| Risk assessment / 風險 | [To complete / 待填] |
| Affected drawings / 圖說 | [To complete / 待填] |
| Test / 測試 | [To complete / 待填] |
| Rollback / 回復 | [To complete / 待填] |
| Approval / 核准 | [To complete / 待填] |
F10 Pre-Energization Checklist / 送電前查核
| Field / 欄位 | Entry / 填寫 |
| SLD approved / 單線圖 | [To complete / 待填] |
| Protection settings / 保護設定 | [To complete / 待填] |
| Grounding / 接地 | [To complete / 待填] |
| LOTO released / 隔離解除 | [To complete / 待填] |
| Fire clearance / 消防 | [To complete / 待填] |
| Training / 訓練 | [To complete / 待填] |
| Authorization / 放行 | [To complete / 待填] |
Reference Register / 參考資料
Taiwan OSH Act — https://law.moj.gov.tw/LawClass/LawAll.aspx?PCode=N0060001
Taiwan OSH Management Regulations — https://law.moj.gov.tw/LawClass/LawAll.aspx?PCode=N0060027
Ministry of Labor 2026 implementation notice — https://www.osha.gov.tw/48110/48713/207079/207115/207278/post
NFPA 855 standard development — https://www.nfpa.org/codes-and-standards/nfpa-standard-development-process/855
NFPA 70E standard development — https://www.nfpa.org/codes-and-standards/7-0-codes-and-standards/70E
Evidence status: cited legislation and edition information were checked against public sources on the report date. Site-specific electrical studies, fire approvals, structural calculations, staffing classification and equipment data remain to be verified.
證據狀態:法規及標準版本資訊已依公開資料核對;場址電氣研究、消防核准、結構計算、人員配置分類及設備資料仍待查證。