800V AI Server Detailed Design

800V AI Server Detailed Design

800V AI 伺服器詳細設計文件

10U chassis   8 GPUs

10U 機箱 八顆 GPU

Revision 0.1 | 24 October 2026 | Engineering requirements and preliminary design

版本 0.1|2026 年 10 月 24 日|工程需求與初步設計

This document establishes a reviewable design basis for an 800V DC server. It specifies module responsibilities, interfaces, calculations and verification evidence. Architecture A and B remain alternatives until GPU, rack power and cooling requirements are frozen.

本文件建立可供審查的 800V 直流伺服器設計基準,定義模組責任、介面、計算與驗證證據。在 GPU、機櫃供電及冷卻需求凍結前,架構 A 與 B 均保留為候選。

Status: proposed design, not released for fabrication. The rendering is illustrative; component count, routing, spacing and cold-plate geometry must follow the engineering drawings. No existing GPU platform is claimed to accept 800V directly.

狀態:提案設計,尚未發行製造。產品圖僅為示意;零件數量、走線、間距與冷板幾何須以工程圖為準。不宣稱任何既有 GPU 平台可直接接入 800V。

01 Scope and Design Control

01 範圍與設計管制

The product boundary runs from the server HV connector to GPU, CPU, memory, storage and network rails, including local auxiliary power, cooling interfaces and management. Rack rectification, upstream protection and the CDU are external systems with mandatory interface agreements.

產品邊界由伺服器高壓連接器至 GPU、CPU、記憶體、儲存與網路供電軌,包含輔助電源、冷卻接口與管理。機櫃整流、上游保護及 CDU 為外部系統,必須簽定介面規格。

Basis
基準
Defined or pending
已定義或待確認
Fixed scope
固定範圍
10U enclosure; 8 GPUs; nominal 800V DC input.
10U 機箱、8 GPU、標稱 800V 直流輸入。
Design options
設計選項
A: 800V to 50V; B: 800V to 12V class.
A:800V 降至 50V;B:800V 降至 12V 級。
Open requirements
待定需求
GPU model, transient load, rail limits, input range, grounding, rack fault current, redundancy, coolant and ambient envelope.
GPU 型號、瞬態負載、電源軌限制、輸入範圍、接地、機櫃故障電流、備援、冷卻液及環境範圍。
Evidence classes
證據分類
REQ: proposed requirement; CALC: illustrative calculation; REF: public engineering evidence; TBD: unresolved.
REQ:提議需求;CALC:示例計算;REF:公開工程證據;TBD:尚待決定。

Release conditions
發行條件

Release schematics only after input and load envelopes are approved. Release PCB and mechanics after insulation, thermal and current-path reviews. Release manufacturing files after design verification, fault testing and configuration control. A module rating alone does not release a server design.

輸入與負載範圍核准後才能發行電路圖;絕緣、熱與電流路徑審查完成後發行 PCB 與機構;設計驗證、故障測試及組態管制完成後發行製造資料。單一模組額定值不能作為整機放行依據。

Document map
文件導覽

Sections 02–04: power budget, architecture and mechanics. Sections 05–08: HV protection, pre-charge and conversion. Sections 09–12: GPU rails, cooling, controls and service. Sections 13–16: verification, BOM, release actions and references.

第 02–04 節:功率預算、架構與機構。第 05–08 節:高壓保護、預充與轉換。第 09–12 節:GPU 供電、冷卻、控制與維修。第 13–16 節:驗證、BOM、發行行動與來源。

02 Power Budget and Operating Envelope

02 功率預算與操作範圍

CALC example only: allocate 1.2kW per GPU, 0.8kW for CPUs and memory, 0.6kW for network and storage, and 0.5kW for fans and auxiliaries. Delivered rail power is 11.5kW. These are planning assumptions, not vendor TDP values.

CALC 僅作示例:每 GPU 配置 1.2kW,CPU 與記憶體共 0.8kW,網路與儲存 0.6kW,風扇與輔助設備 0.5kW;供至各電源軌合計 11.5kW。這些是規劃假設,並非供應商 TDP。

Parameter
參數
Calculation
計算
Implication
含義
Delivered rails
電源軌功率
8 × 1.2 + 0.8 + 0.6 + 0.5 = 11.5kW Sum actual maximum loads.
須加總實際最大負載。
Illustrative end to end efficiency
假設端到端效率
95% Includes all conversion paths in this example.
本例包含各轉換路徑。
HV input
高壓輸入
11.5 / 0.95 = 12.105kW Loss = 605W
損失為 605W
Nominal input current
標稱輸入電流
12.105kW / 800V = 15.13A Not a connector rating.
不是連接器額定值。
Planning capacity
規劃容量
12.105 × 1.2 = 14.53kW 20% example margin; excludes redundancy sizing.
20% 示例餘裕;不含備援容量。

Use Iin,max = Pout,max /(Vin,min × ηmin). Add transient, tolerance, derating and current-sharing effects separately. Do not apply a peak converter efficiency to every load point. Specify continuous, peak-duration and startup envelopes independently.

採用 Iin,max=Pout,max/(Vin,min × ηmin)。瞬態、公差、降額與均流效應另行計入。不能將轉換器峰值效率套用全部負載。連續、峰值持續時間及啟動範圍必須分別定義。

Eight GPUs require a coordinated rack power cap. Firmware must limit aggregate loading during startup and workload transitions, but hardware protection must still contain a controller or software failure.

八顆 GPU 需要協調機櫃功率上限。韌體須限制啟動及工作負載切換時的總負載,但硬體保護仍須能處理控制器或軟體失效。

03 Candidate Power Architectures

03 候選供電架構

Architecture A
架構 A

800V inlet → coordinated protection and pre-charge → isolated 800V to 50V conversion → zonal 50V distribution → local low-voltage conversion where required → POL → device rails. The exact intermediate rail follows the GPU board specification.

800V 入口 → 協調保護與預充 → 隔離式 800V 降至 50V → 分區 50V 配電 → 視需要就地低壓轉換 → POL → 元件電源軌。實際中間電壓依 GPU 板規格決定。

Architecture B
架構 B

800V inlet → coordinated protection and pre-charge → isolated conversion to a 12V-class rail near each load zone → local POL → device rails. Avoid a long shared 12V trunk. A 12.5V prototype is not automatically compatible with a nominal 12V platform.

800V 入口 → 協調保護與預充 → 負載分區附近隔離轉換至 12V 級 → 就地 POL → 元件電源軌。避免長距離共用 12V 主幹;12.5V 原型不代表能直接相容標稱 12V 平台。

Criterion
比較項
Architecture A
架構 A
Architecture B
架構 B
Placement
配置
Flexible 50V distribution
50V 配電較有彈性
Converters close to loads
轉換器貼近負載
Loss drivers
損失來源
Extra conversion and 50V path
額外轉換及 50V 路徑
High current joints and copper
大電流接點及銅材
Cooling
冷卻
Distributed heat sources
熱源可分區
Concentrated converter heat
轉換熱源集中
Acceptance
驗收
Full HV to device rail measurement
高壓至元件電源軌完整量測
Same endpoints and cooling
相同端點及冷卻比較

CALC: 98.1% × 98.5% = 96.63%; versus an assumed direct stage at 97%, the crossover downstream efficiency is 97/98.1 = 98.88%. This is a conditional stage comparison, excluding protection, distribution and POL. Choose using measured complete-path losses and service constraints.

CALC:98.1% × 98.5%=96.63%;相對假設直接轉換為 97%,後級效率交叉點為 97/98.1=98.88%。這是排除保護、配電與 POL 的條件式級間比較。最終應依完整路徑實測損失及維修限制選型。

04 Mechanical Layout and Interface Control

04 機構配置與介面管制

Reserve distinct HV, compute and coolant service zones. Treat the conceptual 2 × 4 GPU arrangement as a packaging study; vendor interconnect and substrate constraints may require a different physical layout. Verify 10U fit with rail hardware, cable bends and service travel.

配置獨立高壓、運算及冷卻維修區。2 × 4 GPU 只作封裝配置研究;供應商互連與基板限制可能要求不同佈局。10U 相容性須包含滑軌、線材彎曲及維修抽拉行程。

Interface ID
介面編號
Definition required
應定義內容
Owner
責任
IF01 HV inlet
高壓入口
Poles, polarity, PE, touch protection, interlock, voltage and fault ratings
極數、極性、PE、防觸電、連鎖、電壓與故障額定
Power and rack
電源與機櫃
IF02 LV output
低壓輸出
Rail tolerance, ripple, load step, capacitance, reverse current, sense points
電壓公差、漣波、負載階躍、電容、逆流、感測點
Power and GPU
電源與 GPU
IF03 Cooling
冷卻
Fluid, pressure, flow, temperatures, QD type, materials, leak detection
流體、壓力、流量、溫度、快接、材質、漏液偵測
Thermal and CDU
熱設計與 CDU
IF04 Management
管理
Isolation, pinout, address, register map, alarms and fail state
隔離、腳位、位址、暫存器、警報與失效狀態
BMC and power
BMC 與電源
IF05 Mechanics
機構
Datum, tolerance stack, mass, centre of gravity, insertion force and retention
基準、公差鏈、重量、重心、插入力及固定
Mechanical
機構

Locate liquid joints away from exposed HV surfaces and include controlled drainage or barriers. Chassis bonding must survive module replacement. Any connector claimed for live insertion needs the specific mating sequence and DC interruption capability validated; a mechanical fit alone is insufficient.

液體接點應避開裸露高壓表面,並設計排液或隔板。機殼搭接須在模組更換後保持有效。任何宣稱可帶電插拔的連接器,都須驗證插拔順序與直流切斷能力;機構可插合並不充分。

05 High Voltage Input and Protection

05 高壓入口與保護

REQ HV01: define whether the rack uses a two-wire 800V bus, a bipolar bus or another arrangement. Specify conductor-to-chassis stresses, fault return paths and all live conductors to be disconnected. Protective earth is distinct from the DC return.

REQ HV01:定義機櫃採兩線式 800V、雙極母線或其他架構。列明導體對機殼應力、故障回流路徑及須切斷的全部帶電導體。保護接地與直流回路不同。

REQ HV02: combine upstream DC-rated protection, local fast electronic protection, controlled pre-charge, residual-energy discharge and sensing. Select the order and location by fault-zone analysis. An eFuse or semiconductor switch does not by itself provide a service isolation gap.

REQ HV02:結合上游直流額定保護、本地快速電子保護、受控預充、殘能放電及感測。順序與位置依故障區分析決定。eFuse 或半導體開關本身不構成維修隔離間隙。

Event
事件
Required response
要求處置
Evidence
證據
Output short
輸出短路
Limit energy and interrupt within validated device SOA; prevent backfeed
在已驗證 SOA 內限制能量並切斷,防止回灌
Current, VDS and timing traces
電流、VDS 與時序波形
Switch stuck on
開關短路失效
Independent upstream or series disconnect path; inhibit restart
獨立上游或串聯切斷路徑,禁止重啟
Single fault test
單一故障測試
Over or undervoltage
過壓或欠壓
Block start or shut down with hysteresis and controlled recovery
禁止啟動或關機,設遲滯與受控恢復
Threshold and ramp sweep
門檻與斜率掃描
Control supply loss
控制電源消失
Defined off behavior including normally-on JFET bias dependencies
定義關斷行為,納入常開 JFET 偏壓相依
Loss-of-bias test
偏壓消失測試

Coordinate local and upstream protection across minimum and maximum prospective fault currents and bus inductance. Record interruption overshoot, clamp energy, fuse I²t and clearing selectivity. Specify reverse-energy paths from parallel modules and charged output capacitors.

以最小及最大預期故障電流與母線電感協調本地和上游保護。記錄切斷過衝、箝位能量、熔絲 I²t 及選擇性。明列並聯模組與輸出電容的反向供能路徑。

06 Precharge and Residual Energy

06 預充與殘留能量

REQ PC01: converters remain disabled during pre-charge. Start only after input validity, interlocks and sensor plausibility pass. Ramp current under the switch SOA and thermal limits; qualify the final voltage difference and slope before enabling conversion. Timeout or abnormal slope latches a fault.

REQ PC01:預充期間停用轉換器。輸入、連鎖及感測合理性通過後才開始。依開關 SOA 與熱限制升流;確認最終壓差及斜率後才允許轉換。逾時或異常斜率須鎖定故障。

CALC example
計算示例
Result
結果
C = 300µF, V = 800V, t = 1.5s; ideal constant current
理想定電流預充
I = C × V / t = 0.16A
Capacitor stored energy
電容儲能
E = ½CV² = 96J
Fixed bus and disabled load
固定母線且負載停用
Series-path dissipation ≈ 96J
串聯路徑耗散約 96J
Initial and average switch power
初始及平均開關耗散
Pinitial = 128W; Pavg = 64W
初始 128W;平均 64W
Scaling to 1mF with same time
相同時間擴至 1mF
0.533A and 320J stored; ≈320J series loss
0.533A、儲能 320J、串聯耗散約 320J

These equations omit tolerances, load leakage and switching dynamics. Validate hot-case SOA using the actual VDS–ID trajectory, transient thermal impedance and repeated-start cooldown. A published 300µF test cannot qualify a larger server capacitance. [1][2]

上述公式未含公差、負載漏電及切換動態。須以實際 VDS–ID 軌跡、暫態熱阻及重複啟動冷卻間隔驗證熱態 SOA。公開的 300µF 測試不能直接認證更大整機電容。[1][2]

For passive discharge, V(t)=V0 exp(−t/RC), so R ≤ t/[C ln(V0/Vrelease)]. Define Vrelease and release time through the applicable safety assessment, not an assumed universal threshold. Rate resistor pulse energy, initial power V0²/R and open-circuit failure; measure residual voltage independently before service.

被動放電採 V(t)=V0 exp(−t/RC),故 R ≤ t/[C ln(V0/Vrelease)]。維修放行電壓及時間須由適用安全評估定義,不能假設通用門檻。驗證電阻脈衝能量、初始功率 V0²/R 與開路失效,維修前獨立量測殘壓。

07 Isolated Conversion and Magnetic Design

07 隔離轉換與磁性設計

A candidate implementation uses input-series output-parallel modules. Series connection reduces nominal module input stress, but startup, imbalance and one-module failure can create unequal voltages. A 650V device must not be placed directly across an 800V bus without a topology that bounds its worst-case stress.

候選實作採輸入串聯、輸出並聯模組。串聯降低標稱模組輸入應力,但啟動、失衡及單模組失效會造成不均分壓。650V 元件不能直接跨接 800V 母線,除非拓撲能限制其最壞應力。

Design requirement
設計要求
Review evidence
審查證據
CV01 Voltage sharing
分壓
Startup, shutdown, open and short module cases; tolerances and balancing losses
啟停、模組開短路、公差及平衡損失。
CV02 Output sharing
輸出均流
Cable/contact mismatch, thermal drift, circulating current and reverse blocking
線材接點差異、熱漂移、循環電流及逆流阻擋。
CV03 Magnetics
磁性元件
Flux over the operating envelope, core/copper losses, leakage, insulation and winding temperature
操作範圍磁通、鐵銅損、漏感、絕緣及繞組溫度。
CV04 Resonant operation
諧振操作
Gain, soft-switching range, dead time, parasitics and abnormal startup
增益、軟切換範圍、死區、寄生及異常啟動。
CV05 Insulation
絕緣
Working/transient voltage, pollution, material, altitude and accessible circuits
工作與暫態電壓、污染、材質、海拔與可接觸電路。

A fixed-ratio DCX does not regulate a constant rail. CALC: an ideal 64:1 ratio with 760–840V input produces 11.875–13.125V. This assumed input range must be approved; the GPU board must tolerate the resulting rail or another regulation stage is required.

固定變比 DCX 不會保持恆定輸出。CALC:理想 64:1 變比、輸入 760–840V 時,輸出為 11.875–13.125V。此假設輸入範圍須核准;GPU 板必須容許其變動,否則須增加穩壓級。

Define conducted and radiated emission test setups, common-mode return paths and isolation capacitance. Safety spacing and dielectric test levels remain TBD pending compliance engineering; they cannot be inferred solely from nominal 800V.

定義傳導與輻射測試配置、共模回流及隔離電容。安全間距與耐壓測試值待合規工程確認,不能僅由標稱 800V 推定。

08 SiC GaN and Silicon Selection

08 SiC GaN 與矽元件選型

Function
功能
Candidate
候選
Selection evidence
選型證據
HV pre-charge and interruption
高壓預充與切斷
SiC JFET cascode plus controller
SiC JFET cascode 與控制器
Linear SOA, bias loss behavior, short-circuit energy, retries and thermal path
線性 SOA、失偏壓行為、短路能量、重試與熱路徑。
HF primary conversion
高頻一次側轉換
GaN with bounded voltage stress
受控電壓應力下的 GaN
Switching loss, dv/dt immunity, driver loop, overshoot and package thermal limits
切換損失、dv/dt 耐受、驅動迴路、過衝與封裝熱限制。
Secondary rectification
二次側整流
Si or GaN
矽或 GaN
Conduction loss, dead time, commutation, parallel sharing and cost
導通損失、死區、換流、並聯均流與成本。
GPU POL
GPU 負載端穩壓
Qualified multiphase Si or GaN stage
經驗證多相矽或 GaN 功率級
Vendor rail requirements, load step, package inductance and cooling
原廠電源軌要求、負載階躍、封裝電感與冷卻。
Control and sensing
控制與感測
Controller, isolation and sensors
控制器、隔離與感測器
Accuracy across temperature, isolation and deterministic fault response
全溫精度、隔離及確定性故障反應。

REF: public engineering literature supports a SiC JFET cascode for high-voltage protection and GaN in high-frequency conversion. The paper also uses silicon in secondary rectification; no material is mandated for every stage. [1]

REF:公開工程文獻支持 SiC JFET cascode 高壓保護及 GaN 高頻轉換;論文也使用矽元件作二次側整流,並非每一級都指定同一材料。[1]

Infineon announced XDP8HD40S-1 in October 2026 for high-voltage power-path protection and monitoring. Treat it as a sourcing candidate, not a drop-in replacement for the paper’s controller. Obtain the complete datasheet, supported external switch configuration, samples and qualification evidence before design freeze. [3]

Infineon 於 2026 年 10 月公布 XDP8HD40S-1 高壓電源路徑保護與監測控制器。此為採購候選,不是論文控制器的直接替換。設計凍結前須取得完整規格、支援外部開關配置、樣品及資格證據。[3]

09 GPU Board and Point of Load Regulation

09 GPU 運算板與負載端穩壓

REQ GPU01: obtain the selected accelerator platform’s rail table, sequence, voltage tolerance, ripple limits, load-step waveform, power cap behavior and management interface. Do not design core voltage or phase count from GPU TDP alone. Preserve vendor high-speed interconnect topology and mechanical keep-outs.

REQ GPU01:取得選定加速器平台的電源軌表、時序、電壓公差、漣波、負載階躍、功率限制及管理介面。不能只由 GPU TDP 決定核心電壓或相數。保留原廠高速互連拓撲與機構禁布區。

Requirement
要求
Implementation and check
實作與檢查
GPU02 Local regulation
就地穩壓
Place POL and decoupling close to load; verify DC drop and transient impedance at specified sense points.
POL 與去耦靠近負載;於指定感測點驗證直流壓降及瞬態阻抗。
GPU03 Sequencing
上電時序
Auxiliary rails and power-good first; enable GPU rails only after input and cooling readiness.
先建立輔助供電與 power-good;輸入及冷卻就緒後啟用 GPU 電源軌。
GPU04 Fault zones
故障分區
Define per-GPU or grouped protection, backfeed paths and coordinated host shutdown.
定義逐 GPU 或群組保護、回灌路徑與協調主機關機。
GPU05 Power transients
功率瞬態
Test simultaneous and staggered load steps, idle-to-maximum and workload oscillation.
測試同步及錯開階躍、待機至最大負載及工作負載振盪。

CALC at 1.2kW per GPU before local regulation: ideal current is 24A at 50V, 96A at 12.5V and 100A at 12V. Eight 12V branches total 800A. Use local branches rather than assuming one connector carries the aggregate current. Actual current includes downstream losses.

CALC:每 GPU 在本地穩壓前為 1.2kW,理想電流在 50V 為 24A、12.5V 為 96A、12V 為 100A。八支 12V 分路合計 800A;採本地分路,不假設由單一連接器承載總電流。實際值還須包含後級損失。

Use ΔV = I × R for steady drop and ΔV ≈ ΔI × ESR + ΔI × Δt/C as a first transient estimate. Complete frequency-domain and time-domain checks with regulator response, ESL and package impedance. Remote-sense open/short faults must not drive overvoltage.

穩態壓降採 ΔV=I × R;瞬態初估採 ΔV ≈ ΔI × ESR+ΔI × Δt/C。納入穩壓器響應、ESL 及封裝阻抗完成頻域與時域驗證。遠端感測開短路不得導致過壓。

10 Liquid Cooling and Thermal Design

10 液冷與熱設計

REQ TH01: cold plates cover the selected GPU package contact areas; power modules and magnetics receive separately validated cooling paths. Residual air cooling remains necessary for memory, NICs, storage, connectors and unplated components unless their heat is captured elsewhere.

REQ TH01:冷板涵蓋所選 GPU 封裝接觸面;電源模組與磁性元件的冷卻路徑另行驗證。記憶體、NIC、儲存、連接器及未覆冷板元件,除非另有散熱路徑,仍須空氣冷卻。

CALC: for 12kW captured by liquid, water approximation cp = 4.18kJ/(kg·K) and a 10K rise gives mass flow Q/(cpΔT) = 0.287kg/s, approximately 17.2L/min. This is a heat-balance example, not a specified pump flow. Actual coolant properties, branch distribution and pressure drop govern the design.

CALC:液體帶走 12kW 熱量,採水比熱約 4.18kJ/(kg·K)、升溫 10K,質量流率 Q/(cpΔT)=0.287kg/s,約 17.2L/min。此為熱平衡示例,不是泵流量規格;實際設計依冷卻液物性、支路分流及壓降決定。

Check
檢查
Required evidence
要求證據
Hydraulic
水力
Pressure-flow curve for all branches, QDs and manifold; worst branch flow and blocked-branch behavior
全支路、快接及歧管壓流曲線;最弱支路及堵塞行為。
Thermal
熱
Junction and case estimates at maximum inlet temperature, minimum flow, aged TIM and component tolerances
最高入口溫度、最低流量、老化 TIM 及公差下的接面與殼溫。
Materials
材質
Coolant compatibility, galvanic corrosion, seals, particles and maintenance interval
冷卻液相容、電偶腐蝕、密封、微粒與維護週期。
Abnormal cooling
異常冷卻
Leak, pump loss, flow sensor failure, condensation and fan failure responses
漏液、停泵、流量感測失效、結露及風扇故障反應。

Set warning, throttling and shutdown thresholds from thermal characterization and sensor delay. Flow loss must trigger a response fast enough for local thermal capacitance; average outlet temperature cannot alone protect a single blocked GPU branch.

警告、降載與關機門檻須由熱特性及感測延遲決定。流量消失的反應速度須符合局部熱容量;平均出口溫度不能單獨保護被堵塞的 GPU 支路。

11 Control States and Telemetry

11 控制狀態與遙測

State
狀態
Entry and action
進入與動作
Exit
離開條件
S0 Isolated
隔離
Main power off; residual energy monitored
主電力關閉,監測殘能
Service closed and authorized
維修關閉且授權
S1 Check
檢查
Validate auxiliary, bus, sensors, cooling and interlock
驗證輔助電源、母線、感測、冷卻及連鎖
All checks pass
全部通過
S2 Pre-charge
預充
Converters disabled; controlled current ramp
轉換器停用,受控電流斜升
Voltage and slope qualified
電壓與斜率合格
S3 Ready
待命
Establish intermediate rails and power-good
建立中間電源軌及就緒訊號
Host enable
主機允許
S4 Run
運行
Enable rails; monitor limits; manage power cap
啟用電源軌、監控限制、管理功率
Stop request or fault
停機要求或故障
S5 Discharge
放電
Disable load, disconnect source, discharge
停負載、切來源、放電
Residual voltage verified
殘壓確認
SF Latched fault
故障鎖定
Fast hardware action; retain fault context
快速硬體動作,保留故障資訊
Authorized reset and recheck
授權重設後重檢

Asynchronous hardware faults override normal sequencing. Classify communication loss as a controlled fallback, sensor implausibility as a safety-related fault, and maintenance interlock opening as a power-removal request. Define restart permissions per fault; repeated blind retries are prohibited.

非同步硬體故障優先於一般時序。通訊消失採受控降級,感測不合理列為安全相關故障,維修連鎖開啟則要求移除電力。逐故障定義重啟權限,禁止無條件反覆重試。

Telemetry shall include HV input/output voltage, input current, module currents, device temperatures, coolant inlet/outlet temperature, flow, leak state, interlock, pre-charge duration and fault counters. Each field needs unit, range, accuracy, update interval, timestamp and invalid-data behavior. Fast protection remains local hardware; BMC logging is not the interruption loop.

遙測須含高壓輸入輸出電壓、輸入電流、模組電流、元件溫度、冷卻進出口溫度、流量、漏液、連鎖、預充時間及故障計數。每欄定義單位、範圍、精度、更新間隔、時間戳及無效資料行為。快速保護由本地硬體執行,BMC 記錄不作切斷迴路。

12 Service Isolation and Fault Containment

12 維修隔離與故障限制

REQ SV01: define the replaceable units and whether replacement requires server shutdown or a validated live-rack procedure. Keeping adjacent servers running does not mean the serviced module is energized. Establish an isolation boundary that prevents alternate feeds and output backfeed.

REQ SV01:定義可更換單元,以及更換是否須停整機或使用已驗證的帶電機櫃程序。相鄰伺服器持續運轉不代表被維修模組仍帶電。隔離邊界須防止替代來源及輸出回灌。

Fault
故障
Containment action
限制措施
Service implication
維修要求
HV switch short
高壓開關短路
Independent disconnection and fault latch
獨立切斷並鎖定
Do not rely on software off
不可依賴軟體關閉
Converter short
轉換器短路
Zone protection, reverse isolation, upstream selectivity
分區保護、反向隔離、上游選擇性
Inspect source and load damage
檢查來源及負載損傷
Liquid leak
漏液
Remove affected power using validated response; maintain event record
依已驗證反應切受影響電源並留紀錄
Inspect and qualify before restart
檢查合格後才重啟
Discharge path open
放電路徑開路
Detect residual voltage; inhibit access release
偵測殘壓,禁止放行
Use approved recovery procedure
依核准程序處置
Sensor or BMC failure
感測或 BMC 故障
Hardware protection and defined degraded state
硬體保護與明確降級
No automatic assumption of safety
不能自動視為安全

Service sequence: stop workloads and confirm rail shutdown; isolate all relevant sources; secure against re-energization; discharge and verify absence of hazardous voltage with the approved method; isolate coolant if needed; replace the unit; restore bonding and interlocks; perform post-service checks and controlled pre-charge. Qualified service procedures must define the actual measurement points and instruments.

維修順序:停止工作負載並確認電源軌關閉;隔離所有相關來源;防止再送電;依核准方法放電並確認無危險電壓;視需要隔離冷卻;更換單元;恢復搭接與連鎖;執行維修後檢查及受控預充。合格維修程序須指定實際量測點及儀器。

13 Verification and Acceptance Matrix

13 驗證與驗收矩陣

Every test report shall retain hardware/BOM revision, firmware, instrument calibration, input impedance, coolant conditions, load waveform and uncertainty. Numerical acceptance limits remain tied to approved requirements; TBD limits must be closed before formal qualification.

每份測試報告須保留硬體與 BOM 版本、韌體、儀器校正、輸入阻抗、冷卻條件、負載波形及量測不確定度。數值驗收門檻依核准需求;正式資格驗證前必須關閉 TBD。

Test ID
編號
Condition and measurement
條件與量測
Acceptance basis
驗收依據
V01 / HV01 Input min/max and polarity; conductor-to-chassis faults
輸入極值、極性及導體對機殼故障
No unsafe stress or accessible energy
無不安全應力或可接觸能量
V02 / PC01 Cold/hot start, max C, restart and timeout
冷熱啟動、最大電容、重啟與逾時
SOA and temperature within approved limits
SOA 與溫度符合核准限制
V03 / HV02 Minimum/maximum fault current and inductance
故障電流與電感極值
Contained failure and selectivity
故障受控且符合選擇性
V04 / CV01–04 Sharing, load sweep, module loss and fixed-ratio range
分壓均流、負載掃描、模組消失及變比範圍
All device and rail limits met
符合元件與電源軌限制
V05 / GPU02–05 Simultaneous GPU load steps and sensing faults
GPU 同步階躍與感測故障
Rail tolerance and host stability
電壓公差與主機穩定
V06 / TH01 Worst inlet/flow; blocked branch; fan/pump loss
最差入口與流量、堵支路、停風扇停泵
Thermal limits and timely action
熱限制與及時處置
V07 / SV01 Interlock, discharge failure, alternate backfeed
連鎖、放電失效、其他回灌
Access blocked until release criteria met
符合放行條件才允許接近
V08 / System Dielectric, bonding, EMC, cycling and endurance
耐壓、搭接、EMC、循環及耐久
Applicable standards and approved test plan
適用標準與核准計畫

Measure complete-system efficiency with synchronized power boundaries and calibrated instruments; identify whether fan, pump and auxiliary power is included. Report a load curve and uncertainty, not only peak efficiency. Endurance duration, sample size and allowable failures require a reliability plan.

完整系統效率須同步量測邊界並使用校正儀器;說明風扇、泵及輔助電源是否計入。提供負載曲線及不確定度,不能只報峰值效率。耐久時間、樣本數與容許故障數須由可靠度計畫定義。

14 Preliminary BOM and Supplier Deliverables

14 初步 BOM 與供應商交付

Item
項目
Quantity basis
數量基準
Required supplier data
供應商資料
GPU modules
GPU 模組
8 Platform rail and thermal specifications
平台電源軌與熱規格
HV inlet assembly
高壓入口組件
Per selected feed arrangement
依進線配置
DC ratings, mating sequence, insulation, temperature rise
直流額定、插拔順序、絕緣、溫升
Protection/pre-charge board
保護預充板
Per fault zone
依故障分區
SOA, startup/fault waveforms, controller and switch BOM
SOA、啟動故障波形、控制及開關 BOM
Isolated converters
隔離轉換器
N satisfying derated capacity
N 須符合降額容量
Full efficiency map, current sharing, transient range
完整效率圖、均流及瞬態範圍
POL assemblies
負載端穩壓組件
By vendor rail and phase needs
依原廠電源軌與相數
Rail compliance, load-step data, firmware compatibility
電源軌符合性、階躍資料、韌體相容
Cold plates and manifold
冷板及歧管
8 GPU interfaces plus other heat sources
8 GPU 接觸面另加其他熱源
Pressure-flow map, thermal resistance and leak qualification
壓流圖、熱阻及漏液驗證
Sensors and BMC interface
感測及 BMC 介面
By monitoring points
依監測點
Accuracy, isolation, calibration and register map
精度、隔離、校正及暫存器表
Chassis and interconnect
機箱與互連
1 chassis; paths by zone
1 機箱;路徑依分區
Tolerance, bonding, busbar/contact loss and service life
公差、搭接、匯流排接點損失及壽命

Capacity rule: N × Pmodule,derated ≥ Prequired. If N+1 is required, validate (N−1) × Pmodule,derated ≥ Prequired together with post-fault current sharing, cooling and topology behavior. Input-series modules may fail as a group; arithmetic spare capacity does not prove redundancy.

容量規則:N × Pmodule,derated ≥ Prequired。若要求 N+1,須驗證 (N−1) × Pmodule,derated ≥ Prequired,並檢查故障後均流、冷卻及拓撲。輸入串聯模組可能成組失效,算術備用容量不等於已證明備援。

15 Engineering Deliverables and Open Decisions

15 工程交付與待決策事項

Gate
關卡
Deliverables
交付
Release decision
放行決策
G1 Requirements
需求
GPU and rack interface specification; power and thermal envelope; architecture comparison
GPU 與機櫃介面規格、功率熱範圍、架構比較
Choose A or B and close critical TBDs
選 A 或 B 並關閉關鍵 TBD
G2 Design review
設計審查
Schematics, PCB stackup and layout, insulation map, magnetic design, mechanical CAD, FMEA
電路圖、PCB 疊構佈局、絕緣圖、磁性、機構 CAD、FMEA
Approve prototype build
核准原型製作
G3 Verification
設計驗證
V01–V08 results, thermal/EMC fixes, firmware state tests, supplier qualification
V01–V08 結果、熱與 EMC 修正、韌體狀態測試、供應商資格
Approve pilot configuration
核准試點組態
G4 Production
量產
Controlled BOM, drawings, test fixtures, calibration, traceability, service manual and yield criteria
受控 BOM、圖面、測試治具、校正、追溯、維修手冊及良率門檻
Manufacturing and quality signoff
製造與品質簽核

Decisions that block schematic release
阻礙電路圖發行的決策

Power architect: approve input range, topology, grounding and prospective fault current. GPU/platform owner: freeze accelerator type, rail envelope and load transients. Thermal owner: approve coolant, flow/pressure limits and inlet range. Mechanical owner: approve rack, mass and service interfaces. Compliance owner: establish applicable editions and test conditions.

電源架構負責人:核准輸入範圍、拓撲、接地及預期故障電流。GPU/平台負責人:凍結加速器型號、電源軌範圍及負載瞬態。熱設計負責人:核准冷卻液、流壓限制與入口範圍。機構負責人:核准機櫃、重量及維修介面。合規負責人:建立適用版本與測試條件。

This revision provides detailed requirements and sizing methods. Fabrication-ready schematics, pin assignments, component values, Gerbers, winding drawings, tolerance drawings and signed test limits require the above decisions and engineering analysis. Maintain each open item with an owner, due date and closure evidence.

本版提供詳細需求與估算方法。可製造電路圖、腳位、元件值、Gerber、繞線圖、公差圖及簽核測試門檻,須以上述決策及工程分析完成。每項未決事項須指定責任人、期限及關閉證據。

16 References and Evidence Boundaries

16 參考資料與證據邊界

[1] Kasper et al. Power Conversion Solutions for Future Server Boards Operating Directly From High-Voltage DC. CPSS TPEA 11(1), 2026. DOI 10.24295/CPSSTPEA.2026.00003.

https://tpea.cpss.org.cn/uploads/allimg/260330/10.24295CPSSTPEA.2026.00003.pdf

[2] onsemi. AND90399/D EliteSiC JFET Based High Voltage Hot-Swap Application. December 2025 Rev 0.

https://www.onsemi.com/download/application-notes/pdf/and90399-d.pdf

[3] Infineon. XDP8HD40S-1 high-voltage hot-swap controller. 12 October 2026 announcement and product page.

https://www.infineon.com/technology-news/2026/inftn202610-006

[4] Infineon. MGX AI Factory ecosystem and power delivery. 29 May 2026 webpage.

https://www.infineon.com/press-release/2026/infxx202605-092

[5] IEC. IEC 62368-1:2023 product safety standard catalog, corrected version noted August 2025.

https://webstore.iec.ch/en/publication/69308

Sources checked on 24 October 2026. Public papers support feasibility under their prototype conditions; supplier announcements establish product direction, not this server’s qualification. Equations and scenario budgets in this document are independent engineering calculations.

來源查核日期為 2026 年 10 月 24 日。公開論文支持其原型條件下的可行性;供應商公告證明產品方向,並非本伺服器通過驗證。本文公式及情境預算為獨立工程計算。

The paper’s 300µF / approximately 1.5s abstract example and 150µF / approximately 210ms main-text waveform use different conditions. Its 98.13% full-load result concerns a 400V-to-50V 3kW submodule; the approximately 97% 6kW result concerns a 12.5V nominal prototype with liquid cooling. None is a complete 10U server efficiency rating. [1]

論文摘要 300µF/約 1.5 秒與正文 150µF/約 210ms 波形屬不同條件。98.13% 滿載結果屬 400V→50V、3kW 子模組;約 97% 的 6kW 結果屬標稱 12.5V 液冷原型。均不是完整 10U 伺服器效率額定。[1]

IEC 62368-1 provides a safety framework; this document does not reproduce its normative requirements or claim certification. Applicable national adoption, EMC, connector and cooling requirements must be determined with the target-market compliance team. [5]

IEC 62368-1 提供安全框架;本文件未重製其規範要求,亦不宣稱取得認證。目標市場的國家採用版本、EMC、連接器及冷卻要求須由合規團隊判定。[5]